Court Emphasizes Strict Compliance in Construction Contracts

In a recent ruling, a New York appellate court sided with a contractor in a dispute over a 33-story building project.[1] The contractor initially hired a subcontractor to supply equipment for the project, but the subcontract was later assigned to another entity. Shortly thereafter, the contractor alleged breaches of the subcontract, terminated the agreement, and took possession of the equipment. The contractor then filed a lawsuit seeking compensation for delays and additional costs resulting from the defendants’ defective work. In response, the defendants counterclaimed for breach of contract and sought foreclosure of mechanic’s liens. They also filed a third-party claim against the property owner and its surety, seeking to foreclose on the liens.

The court dismissed the defendants’ counterclaims and third-party claims, highlighting the defendants’ reliance on unsigned and unnotarized requisitions and change orders, which failed to meet the contractual requirements. The court citing precedent underscored that payment requisitions must be both signed and notarized, and that change orders must be formally documented and mutually approved in strict compliance with the terms of the contract.[2]

Additionally, the court found that the contractor had provided sufficient evidence to support its claims for delay damages. The contractor presented documentation detailing additional work performed by other vendors, as well as payments made to replacement subcontractors, due to the delays attributed to the defendants. The court found that such evidence raised genuine issues of material fact regarding the impact of the defendants’ actions on the project’s timeline and costs, prompting the court to deny the defendants’ motion for summary judgment on this issue.

The court also rejected the defendants’ claims for unpaid equipment rental, as they were unable to demonstrate that the proposed monthly rental rates had been agreed upon. The subcontract specified only a 12-month rental period, and the defendants could not provide evidence of any additional rental terms beyond that period.

This decision highlights the  importance of adhering to contractual documentation and approval processes in construction projects. It serves as a reminder to contractors and subcontractors alike to ensure that all requisitions and change orders are properly signed, notarized, and approved to avoid disputes and potential legal challenges. Furthermore, the ruling underscores the necessity of maintaining thorough records and evidence to substantiate claims for damages and delays. The court’s decision reinforces the judiciary’s commitment to enforcing strict compliance with agreed upon contract terms.

Jose A. Aquino (@JoseAquinoEsq on X) is a special counsel in the New York office of Duane Morris LLP, where he is a member of the Construction Group and of the Cuba Business Group.  Mr. Aquino focuses his practice on construction law, lien law and government procurement law. This blog is prepared and published for informational purposes only and should not be construed as legal advice. The views expressed in this blog are those of the author and do not necessarily reflect the views of the author’s law firm or its individual attorneys.

[1] Hudson Meridian Construction Group LLC v. Bayport Construction Corp., 228 A.D.3d 531, 215 N.Y.S.3d 78 (1st Dept. 2024)

[2] F. Garofalo Elec. Co. v. New York Univ., 270 A.D.2d 76, 80, 705 N.Y.S.2d 327 (1st Dept. 2000), lv dismissed 95 N.Y.2d 825, 712 N.Y.S.2d 450, 734 N.E.2d 762 (2000); Martin Iron & Constr. Corp. v. Howell Co., 242 A.D.2d 608, 609, 664 N.Y.S.2d 746 (2d Dept. 1997).

Duane Morris Attorneys Named “Lawyers of the Year” for Construction Law and Litigation

Duane Morris partners Frederick Cohen and Allen J. Ross have been recognized by Best Lawyers® as 2025 “Lawyers of the Year.” The recognition is given to only one attorney for each practice area and city. Lawyers are selected based on high marks received during peer-review assessments conducted by Best Lawyers each year.

Cohen has been selected as the “Lawyer of the Year” in New York City for Construction Law. He also received this distinction in 2018 and was named for Litigation – Construction in 2014.

Ross has been selected as the “Lawyer of the Year” in New York City for Litigation – Construction. He also received this distinction in 2015 and 2016.

Continue reading “Duane Morris Attorneys Named “Lawyers of the Year” for Construction Law and Litigation”

New York NY Court Dismisses Construction Defect Case Over Statute of Limitations

The New York Appellate Division, Second Department, recently affirmed the dismissal of a breach of contract lawsuit related to alleged construction defects.[1] The plaintiff claimed that the defendant had breached their remodeling contract by improperly installing flooring in the plaintiff’s basement. However, the appellate court affirmed the lower court’s ruling that the plaintiff’s claim was barred by the statute of limitations.

Under New York law, breach of contract claims are subject to a six-year statute of limitations.[2] This limitations period begins to run upon the contractor’s completion of the work. In this case, the court determined that the claim accrued on May 26, 2015, the date on which the plaintiff made the final payment under the contract, with no subsequent work performed. The plaintiff filed the lawsuit on January 21, 2022, well beyond the six-year statutory period.

The court also considered the potential tolling of the statute of limitations due to executive orders issued during the COVID-19 pandemic. However, even with these tolling provisions, the court found the plaintiff’s action untimely. Consequently, the lower court’s dismissal of the complaint was upheld on appeal.

In affirming the lower court’s decision, the Appellate Division emphasized that the burden rests with the defendant to establish that the statute of limitations has expired. Once this burden is met, the plaintiff must then demonstrate a factual basis for tolling the statute of limitations or show that the claim was filed within the statutory period. In this case, the plaintiff failed to present a factual issue that could preclude dismissal, resulting in the affirmation of the dismissal the complaint.

The ruling underscores the critical importance of understanding and adhering to the statute of limitations in construction-related disputes. It also highlights the necessity for plaintiffs to act promptly when they believe they have a claim, as delays can easily result in losing the right to sue.

Jose A. Aquino (@JoseAquinoEsq on X) is a special counsel in the New York office of Duane Morris LLP, where he is a member of the Construction Group and of the Cuba Business Group.  Mr. Aquino focuses his practice on construction law, lien law and government procurement law. This blog is prepared and published for informational purposes only and should not be construed as legal advice. The views expressed in this blog are those of the author and do not necessarily reflect the views of the author’s law firm or its individual attorneys.

[1] Hillaire v. Jose A. Torres, ___ N.Y.S.3d ___, 2024 WL 3281628 (2d Dep’t 2024).

[2] N.Y. C.P.L.R. § 213(2)

Equitable Subrogation: Insights Into Legal Complexities In Recovery

The principle of equitable subrogation plays a central role in ensuring that the party responsible for causing loss or damage is held accountable. This doctrine allows an insurer, who has compensated the insured for a loss, to assume the legal rights of the insured to seek recovery from the third party responsible for the loss.

The recent decision of New York Municipal Insurance Reciprocal v. Stewart’s Shops Corporation, 228 A.D.3d 1116, 212 N.Y.S.3d 859 (3d Dep’t 2024), presents a scenario involving property damage, insurance claims, and the intricacies of equitable subrogation. In 2016, Stewart’s Shops Corporation acquired properties with the intention of constructing a new store. The development required the removal of an underground fuel storage tank and contaminated soils, a task undertaken by its contractor. However, the remediation project led to structural damage in a neighboring building owned by the Village of Middleburgh.

In response to the damage, the Village’s insurance company initiated a subrogation action against both Stewart’s and its contractor. The defendants countered by moving for summary judgment challenging plaintiff’s standing. Defendants noted the absence of payment under the policy prior to the commencement of the action and argued that any future attempt to do so was barred by the statute of limitations.

The lower court’s decision to deny the defendants’ motion for summary judgment was reversed on appeal. The appellate court held that the insurer for the owner of a building damaged by a contractor’s work on adjacent property lacked standing to bring a claim as the owner’s subrogee. This was because standing accrues only upon payment of the loss, and the insurer filed suit before making any payments. According to established precedent, an insurer’s right to subrogation arises upon payment of the loss, which must be directed toward satisfying an actual claim rather than a potential liability. This right arises independently of any contractual agreement between the insurer and the insured.

The appellate court’s ruling underscores that the insurer, as an equitable subrogee, is subject to the same defenses that could have been raised against the insured, including the statute of limitations.

The case serves as a reminder of the legal complexities surrounding equitable subrogation. It highlights the importance of timely payment by insurers to secure their subrogation rights.

Jose A. Aquino (@JoseAquinoEsq on X) is a special counsel in the New York office of Duane Morris LLP, where he is a member of the Construction Group and of the Cuba Business Group.  Mr. Aquino focuses his practice on construction law, lien law and government procurement law. This blog is prepared and published for informational purposes only and should not be construed as legal advice. The views expressed in this blog are those of the author and do not necessarily reflect the views of the author’s law firm or its individual attorneys.

Revisiting The Intricacies Of New York Lien Law § 38

In the realm of construction law, disputes over the enforcement and validity of mechanic’s liens are fairly common. The recent case of  176 Washington Park LLC v. Empire Core Group LLC, 2024 N.Y. Slip Op. 50906(U) (Sup. Ct., NY Co., June 21, 2024), serves as a classic illustration of the complexities involved.

New York Lien Law § 38 is clear in its mandate: a lienor must provide a detailed statement of the labor and materials that constitute the claimed lien amount. This includes a comprehensive breakdown of materials used, their quantities, costs, and the specifics of labor, including the nature of the work, hours spent, and the rates charged.

In 176 Washington Park LLC v. Empire Core Group LLC, the defendant’s submission fell short of these requirements. The court found the provided classifications of costs, such as “Porta Potty,” “Construction Site Signs,” “Waste Removal,” “DOB Drawings,” and “DOT Permits,” to be too general. They lacked the necessary detail regarding the nature of the labor and the hours and wages expended. Furthermore, payments to subcontractors were listed without adequate information about the services rendered or the basis for the charges.

The materials section was similarly lacking, with no specifics on the quantity or costs of materials used, despite listing the suppliers and amounts disbursed. This lack of detail ultimately led to the court’s decision to grant the plaintiff’s motion in part, requiring the defendant to provide a proper verified itemized statement within 30 days. Failure to comply would result in the discharge of the mechanic’s lien.

This case underscores the importance of record-keeping and transparency in construction projects. It emphasizes the need of contractors and subcontractors to adhere to the requirements of Lien Law § 38 to ensure the enforceability of their liens.

Jose A. Aquino (@JoseAquinoEsq on X) is a special counsel in the New York office of Duane Morris LLP, where he is a member of the Construction Group and of the Cuba Business Group.  Mr. Aquino focuses his practice on construction law, lien law and government procurement law. This blog is prepared and published for informational purposes only and should not be construed as legal advice. The views expressed in this blog are those of the author and do not necessarily reflect the views of the author’s law firm or its individual attorneys.

Duane Morris Named to Construction Executive’s Top 50 Construction Law Firms List

Duane Morris has been named named to Construction Executive’s Top 50 Construction Law Firms list for the fourth consecutive year.

Construction Executive is the leading source for news, market developments and business issues impacting the construction industry. In its June 2024 issue, CE published a comprehensive ranking of the Top 50 Construction Law Firms featuring breakouts and analysis accompanied by an article in which leading legal experts discuss their construction clients’ most pressing business concerns. Read the article for more information.

Flaws In Project Scope Lead To Court Most Often, Report Says

Jeffrey L. Hamera, vice chair of Duane Morris’ Construction Group , was quoted in the Law360 article, “Flaws In Project Scope Lead To Court Most Often, Report Says.”

From Law360:

[Mr. Hamera said] that project owners have looked toward reducing design or project delivery costs by starting construction before design work wraps up entirely, in a trend that’s been building for years.

Hamera said those objectives can be valid, although they can distress a project if parties haven’t planned for it.

“If the parties are sophisticated and understand there’s going to be some completion of the design after the initial bids are in place, it’s something that can be managed,” he said. “There’s always a friction between what’s anticipated from the design on which the contractor’s bids are based, and what’s really a change that wasn’t anticipated and couldn’t be anticipated.”

To read the full article, please visit the Law360 website (subscription may be required).

 

Duane Morris’ Benton T. Wheatley Named Austin Construction “Lawyer of the Year” by Best Lawyers

Duane Morris partner Benton T. Wheatley has been recognized by Best Lawyers® as the “2024 Construction Lawyer of the Year” in Austin, Texas. The recognition is given to only one attorney for each practice area and city. Lawyers are selected based on high marks received during peer-review assessments conducted by Best Lawyers each year.

Continue reading “Duane Morris’ Benton T. Wheatley Named Austin Construction “Lawyer of the Year” by Best Lawyers”

Can We Learn Anything from Adjudications in Expedited Arbitrations?

Construction projects are a ripe ground for disputes. When these disputes arise, they often threaten to bring the project itself to a halt if not resolved expeditiously. However, many large-scale construction projects (particularly international ones) provide for their disputes to be referred to arbitration.

To read the full text of this post by Selvam LLC attorney Luis Duhart, please visit the Duane Morris International Arbitration Blog,

© 2009- Duane Morris LLP. Duane Morris is a registered service mark of Duane Morris LLP.

The opinions expressed on this blog are those of the author and are not to be construed as legal advice.

Proudly powered by WordPress