Court Emphasizes Strict Compliance in Construction Contracts

In a recent ruling, a New York appellate court sided with a contractor in a dispute over a 33-story building project.[1] The contractor initially hired a subcontractor to supply equipment for the project, but the subcontract was later assigned to another entity. Shortly thereafter, the contractor alleged breaches of the subcontract, terminated the agreement, and took possession of the equipment. The contractor then filed a lawsuit seeking compensation for delays and additional costs resulting from the defendants’ defective work. In response, the defendants counterclaimed for breach of contract and sought foreclosure of mechanic’s liens. They also filed a third-party claim against the property owner and its surety, seeking to foreclose on the liens.

The court dismissed the defendants’ counterclaims and third-party claims, highlighting the defendants’ reliance on unsigned and unnotarized requisitions and change orders, which failed to meet the contractual requirements. The court citing precedent underscored that payment requisitions must be both signed and notarized, and that change orders must be formally documented and mutually approved in strict compliance with the terms of the contract.[2]

Additionally, the court found that the contractor had provided sufficient evidence to support its claims for delay damages. The contractor presented documentation detailing additional work performed by other vendors, as well as payments made to replacement subcontractors, due to the delays attributed to the defendants. The court found that such evidence raised genuine issues of material fact regarding the impact of the defendants’ actions on the project’s timeline and costs, prompting the court to deny the defendants’ motion for summary judgment on this issue.

The court also rejected the defendants’ claims for unpaid equipment rental, as they were unable to demonstrate that the proposed monthly rental rates had been agreed upon. The subcontract specified only a 12-month rental period, and the defendants could not provide evidence of any additional rental terms beyond that period.

This decision highlights the  importance of adhering to contractual documentation and approval processes in construction projects. It serves as a reminder to contractors and subcontractors alike to ensure that all requisitions and change orders are properly signed, notarized, and approved to avoid disputes and potential legal challenges. Furthermore, the ruling underscores the necessity of maintaining thorough records and evidence to substantiate claims for damages and delays. The court’s decision reinforces the judiciary’s commitment to enforcing strict compliance with agreed upon contract terms.

Jose A. Aquino (@JoseAquinoEsq on X) is a special counsel in the New York office of Duane Morris LLP, where he is a member of the Construction Group and of the Cuba Business Group.  Mr. Aquino focuses his practice on construction law, lien law and government procurement law. This blog is prepared and published for informational purposes only and should not be construed as legal advice. The views expressed in this blog are those of the author and do not necessarily reflect the views of the author’s law firm or its individual attorneys.

[1] Hudson Meridian Construction Group LLC v. Bayport Construction Corp., 228 A.D.3d 531, 215 N.Y.S.3d 78 (1st Dept. 2024)

[2] F. Garofalo Elec. Co. v. New York Univ., 270 A.D.2d 76, 80, 705 N.Y.S.2d 327 (1st Dept. 2000), lv dismissed 95 N.Y.2d 825, 712 N.Y.S.2d 450, 734 N.E.2d 762 (2000); Martin Iron & Constr. Corp. v. Howell Co., 242 A.D.2d 608, 609, 664 N.Y.S.2d 746 (2d Dept. 1997).

NY Governor Vetoes Bill To Allow Delay Damages On Public Contracts

New York Governor Andrew Cuomo ended 2018 by vetoing New York Senate Bill 6686 to amend the state finance law by adding a new section 138-b to allow contractors working on public construction projects seek delay damages against government agencies. The vetoed bill would have required all public contracts to contain a clause allowing a contractor, subcontractor or supplier to make a claim for costs due to excusable delays resulting from actions or omissions by a public owner or any of its representatives. The bipartisan bill sponsored by Senators Michael Ranzenhofer (Republican) and Luis Sepulveda (Democrat) passed the Assembly by a vote of 103 to 40 and the Senate 59 to 0. The text of the bill can be seen here.

Jose A. Aquino (@JoseAquinoEsq on Twitter) is a special counsel in the New York office of Duane Morris LLP, where he is a member of the Construction Group and of the Duane Morris Cuba Business Group. Mr. Aquino focuses his practice on commercial litigation with a concentration in construction law, mechanics’ lien law and government procurement law. This blog is prepared and published for informational purposes only and should not be construed as legal advice. The views expressed in this blog are those of the author and do not necessarily reflect the views of the author’s law firm or its individual attorneys.

Eastern District of New York Issues Decision in Recent Construction Contracts Case

By Michael L. Chartan, partner in the Construction Group in Duane Morris’ New York office

Construction contracts in New York and in other states frequently include provisions that bar recovery of damages for delay and require extra work to be authorized in writing. These types of provisions are enforceable. Exceptions exist that will permit recovery of delay damages and for extra work in the face of these exculpatory provisions. In Bricklayers Ins. & Welfare Fund v. Minhas Gen. Contrs. Co., LLC, 2015 U.S. Dist. LEXIS 151965, Judge Frederic Block sitting in the United States District Court for the Eastern District of New York, denied summary judgment finding triable issues of material fact. Subcontractors and general contractors have limited leverage to remove these types of provisions from the contract. Nonetheless, review of project records by a knowledgeable attorney may well reveal facts to overcome these provisions.

Importance Of Using Consistent Terms In A Construction Contract

A recent decision of the Supreme Court of the State of New York reminds us of the importance of using consistent terms when drafting a construction contract. In Clinton Assoc. For A Renewed Envt. Inc. v. Monadock Constr. Inc., defendants, pursuant to a contract (the “Contract”), agreed to provide architectural services and contract administration services to plaintiffs.[i] As part of their work, defendants prepared architectural plans, including specifications for the design system and choice of materials for the exterior masonry wall system. The Certificate of Substantial Completion was signed on March 29, 2006 and, at or about that time, the masonry walls began to fail, causing the walls to bulge and take on water. It was determined that the walls could not withstand the weather cycles to which they were exposed. Following Substantial Completion of the project, defendants worked extensively to cure the flaws in the masonry walls by, among other things, creating an alternate design and supervising the corrective work until August 18, 2008, when an Architect’s Certificate approving the repairs was issued.

Continue reading “Importance Of Using Consistent Terms In A Construction Contract”

© 2009- Duane Morris LLP. Duane Morris is a registered service mark of Duane Morris LLP.

The opinions expressed on this blog are those of the author and are not to be construed as legal advice.

Proudly powered by WordPress