Court Affirms Default Finding in Public Contract Dispute

In a recent decision from the New York Supreme Court, Appellate Division, Second Department, In the Matter of New York Constr. & Renovation, Inc. v. City of New York Dep’t of Parks & Recreation, the court affirmed the dismissal of a hybrid proceeding brought by New York Construction & Renovation, Inc. (NYCR) against the City of New York Department of Parks and Recreation. The dispute arose from a construction contract awarded to NYCR in for the development of a comfort station in Canarsie Park in Brooklyn, New York. Although the Parks Department initially directed NYCR to begin work on March 1, 2019, it granted a one-month extension to April 1, 2019, in response to NYCR’s request. NYCR failed to commence work by the revised start date, prompting the Parks Department to issue a notice in September 2019 requiring NYCR to show cause why it should not be declared in default. Following a meeting, the Parks Department issued a default determination on October 30, 2019.

NYCR challenged the default determination through a hybrid New York Civil Practice Law and Rules (CPLR) Article 78 proceeding and sought declaratory relief. An Article 78 proceeding is the legal mechanism in New York that allows individuals or entities to seek judicial review of actions or decisions made by administrative agencies or public officials. It is commonly used to challenge determinations that are claimed to be unlawful, arbitrary, or procedurally flawed.

In this case, the Parks Department moved to dismiss the declaratory judgment claims, citing a contractual provision that limited NYCR’s remedies to judicial review under Article 78. The court agreed, holding that the parties’ contract expressly restricted post-default remedies and that the Parks Department’s determination was neither arbitrary nor capricious.

In an Article 78 proceeding, the court’s review is limited to whether the agency’s determination was made in violation of lawful procedure, was affected by an error of law, was arbitrary and capricious, or lacked a rational basis. Applying this standard, the court found that the Parks Department acted rationally in concluding that NYCR had defaulted. The agency’s decision was based on NYCR’s failure to submit an acceptable progress schedule, provide necessary submittals, and obtain a required permit from the Department of Buildings, all of which contributed to project delays.

NYCR argued that a moratorium on gas line applications by National Grid prevented it from obtaining the necessary permit, but the court declined to consider this claim because it had not been raised during the administrative process. The court also rejected NYCR’s due process argument, finding no procedural violations. Additionally, the court found no error of law and concluded that there were no factual issues requiring a trial.

Ultimately, the court upheld the Parks Department’s motion to dismiss, denied NYCR’s petition, and affirmed the agency’s default determination. The decision shows the importance following contractual and agency procedures when disputing government actions.

Jose A. Aquino (@JoseAquinoEsq on X) is a special counsel at Duane Morris LLP’s New York office, where he is a member of Construction Group,  specializing in construction law, lien law, and government procurement law. He is also a member of the Cuba Business Group.

This blog is prepared and published for informational purposes only and should not be construed as legal advice. The views expressed herein are those of the author and do not necessarily reflect the views of Duane Morris LLP or its individual attorneys.

Judicial Caution in Determining Liability for Withheld Payments Under Public Works Contracts

In public construction projects, disputes over payment obligations between contractors and subcontractors often depend not only on the terms of the contract but on the resolution of underlying factual questions. A recent decision from the Appellate Division, First Department in Brownie Companies of Long Island, LLC v. Volmar Construction, Inc., illustrates the court’s cautious approach to summary judgment where material facts remain unresolved. The case, arising from work performed under New York City’s Build It Back Program, underscores the issues that can arise when payments are withheld due to alleged delays and potential liquidated damages. This blog examines the court’s reasoning and considers its implications for payment disputes arising from public construction contracts.

The subcontractor had entered into an agreement with the contractor to perform house lifting and repair services for homes damaged by Superstorm Sandy. The subcontractor alleged that the contractor breached the subcontract by failing to pay $474,000 for work performed and invoiced.

The court found that the subcontractor established a breach of contract, as the contractor failed to pay for work that had already been paid for by the City. It further held that, under established case law, contractors are obligated to pay subcontractors amounts received from the owner for their work. However, unresolved factual issues precluded summary judgment.

The court noted that key factual issues remained unresolved, including how damages should be calculated and whether the City had reduced its payments to the contractor due to delays caused by the subcontractor. The contractor had withheld payments in anticipation of liquidated damages the City intended to impose. The court acknowledged that such delays if proven could justify the withholding. As a result, the judgment in favor of the subcontractor was vacated, and the matter was remanded for further proceedings to address factual questions.

The court also held that the contractor’s motion for leave to amend its answer should have been granted. Through the proposed amendment, the contractor sought to assert counterclaims for indemnification, contending that if the City’s deductions were upheld and exceeded the amount remaining unpaid to the subcontractor, the subcontractor should be liable for the difference.

The decision highlights the importance of resolving factual disputes prior to summary judgment. By vacating the judgment and permitting amended pleadings, the court left open questions regarding the parties’ payment obligations, requiring further proceedings.

Jose A. Aquino (@JoseAquinoEsq on X) is a special counsel at Duane Morris LLP’s New York office, where he is a member of Construction Group,  specializing in construction law, lien law, and government procurement law. He is also a member of the Cuba Business Group.

This blog is prepared and published for informational purposes only and should not be construed as legal advice. The views expressed herein are those of the author and do not necessarily reflect the views of Duane Morris LLP or its individual attorneys.

Court Reinforces Limits on “Piggybacking” in Public Bidding

In New York, “piggybacking” refers to a procurement method authorized by General Municipal Law §103(16), which allows a municipality or school district to purchase goods or services through another governmental entity’s contract without conducting its own bidding process, if certain conditions are met. The original contract must have been awarded through competitive bidding or a process that satisfies the legal equivalent under New York law, and it must permit other public entities to make purchases from it. While intended to promote efficiency and cost savings, piggybacking is strictly limited in scope and is not a blanket exemption from public bidding requirements.

On February 13, 2025, the Supreme Court of New York, Broome County, issued decision in Daniel J. Lynch, Inc. v. Board of Ed. of the Maine-Endwell Central School Dist., addressing the limits of “piggybacking” under General Municipal Law (GML) §103(16) in the context of public construction contracts.

The case arose from a capital improvement project for which the School District awarded a sitework contract to Smith Site Development, LLC. Several contractors, including plaintiff, challenged the award, arguing that the District improperly relied on a piggybacking arrangement to avoid traditional competitive bidding procedures. Specifically, the District piggybacked on a municipal contract that had not been awarded through sealed bidding as required by GML §103.

The Court held that the District’s use of piggybacking was impermissible. The Court found that GML §103(16) only authorizes piggybacking when the original contract was awarded through a process compliant with GML §103’s requirements – namely, public advertisement and sealed competitive bidding. Furthermore, the Court interpreted the statutory term “vendor” as applying only to suppliers of apparatus, materials, equipment, or related services, and not to contractors performing construction or alteration of buildings. Because the original contract did not meet these criteria, the piggybacking arrangement was invalid.

This decision cautions that piggybacking under GML §103(16) is restricted to eligible vendor contracts and cannot be used to bypass competitive bidding rules for construction projects. The ruling provides a clear precedent for challenging awards made through improper reliance on piggybacking.

Jose A. Aquino (@JoseAquinoEsq on X) is a special counsel at Duane Morris LLP’s New York office, where he is a member of both the Construction Group and of the Cuba Business Group,  specializing in construction law, lien law, and government procurement law.

This blog is prepared and published for informational purposes only and should not be construed as legal advice. The views expressed herein are those of the author and do not necessarily reflect the views of Duane Morris LLP or its individual attorneys.

NY Governor Vetoes Bill To Allow Delay Damages On Public Contracts

New York Governor Andrew Cuomo ended 2018 by vetoing New York Senate Bill 6686 to amend the state finance law by adding a new section 138-b to allow contractors working on public construction projects seek delay damages against government agencies. The vetoed bill would have required all public contracts to contain a clause allowing a contractor, subcontractor or supplier to make a claim for costs due to excusable delays resulting from actions or omissions by a public owner or any of its representatives. The bipartisan bill sponsored by Senators Michael Ranzenhofer (Republican) and Luis Sepulveda (Democrat) passed the Assembly by a vote of 103 to 40 and the Senate 59 to 0. The text of the bill can be seen here.

Jose A. Aquino (@JoseAquinoEsq on Twitter) is a special counsel in the New York office of Duane Morris LLP, where he is a member of the Construction Group and of the Duane Morris Cuba Business Group. Mr. Aquino focuses his practice on commercial litigation with a concentration in construction law, mechanics’ lien law and government procurement law. This blog is prepared and published for informational purposes only and should not be construed as legal advice. The views expressed in this blog are those of the author and do not necessarily reflect the views of the author’s law firm or its individual attorneys.

Duane Morris’ Charles Fastenberg to Present Lorman Educational Services Webinar on “Understanding New York Public Contracts and Procurement Regulations”

Duane Morris special counsel Charles Fastenberg of the firm’s New York office will present the Lorman Educational Services webinar, “Understanding New York Public Contracts and Procurement Regulations,” on Thursday, October 6, 2016, from 1:00 p.m. to 2:30 p.m. (Eastern time). This webinar will provide insights for contractors and vendors so they are aware of unanticipated issues they may face when submitting bids for contracts.

For more information, please see the event posting on the Duane Morris website.

© 2009- Duane Morris LLP. Duane Morris is a registered service mark of Duane Morris LLP.

The opinions expressed on this blog are those of the author and are not to be construed as legal advice.

Proudly powered by WordPress