Judicial Caution in Determining Liability for Withheld Payments Under Public Works Contracts

In public construction projects, disputes over payment obligations between contractors and subcontractors often depend not only on the terms of the contract but on the resolution of underlying factual questions. A recent decision from the Appellate Division, First Department in Brownie Companies of Long Island, LLC v. Volmar Construction, Inc., illustrates the court’s cautious approach to summary judgment where material facts remain unresolved. The case, arising from work performed under New York City’s Build It Back Program, underscores the issues that can arise when payments are withheld due to alleged delays and potential liquidated damages. This blog examines the court’s reasoning and considers its implications for payment disputes arising from public construction contracts.

The subcontractor had entered into an agreement with the contractor to perform house lifting and repair services for homes damaged by Superstorm Sandy. The subcontractor alleged that the contractor breached the subcontract by failing to pay $474,000 for work performed and invoiced.

The court found that the subcontractor established a breach of contract, as the contractor failed to pay for work that had already been paid for by the City. It further held that, under established case law, contractors are obligated to pay subcontractors amounts received from the owner for their work. However, unresolved factual issues precluded summary judgment.

The court noted that key factual issues remained unresolved, including how damages should be calculated and whether the City had reduced its payments to the contractor due to delays caused by the subcontractor. The contractor had withheld payments in anticipation of liquidated damages the City intended to impose. The court acknowledged that such delays if proven could justify the withholding. As a result, the judgment in favor of the subcontractor was vacated, and the matter was remanded for further proceedings to address factual questions.

The court also held that the contractor’s motion for leave to amend its answer should have been granted. Through the proposed amendment, the contractor sought to assert counterclaims for indemnification, contending that if the City’s deductions were upheld and exceeded the amount remaining unpaid to the subcontractor, the subcontractor should be liable for the difference.

The decision highlights the importance of resolving factual disputes prior to summary judgment. By vacating the judgment and permitting amended pleadings, the court left open questions regarding the parties’ payment obligations, requiring further proceedings.

Jose A. Aquino (@JoseAquinoEsq on X) is a special counsel at Duane Morris LLP’s New York office, where he is a member of Construction Group,  specializing in construction law, lien law, and government procurement law. He is also a member of the Cuba Business Group.

This blog is prepared and published for informational purposes only and should not be construed as legal advice. The views expressed herein are those of the author and do not necessarily reflect the views of Duane Morris LLP or its individual attorneys.

Appellate Court Reaffirms Limits on Delay Damages in Construction Contracts

On June 5, 2025, the Appellate Division, First Department of the New York Supreme Court issued an opinion in Gamma USA, Inc. v. Pavarini McGovern, LLC, addressing the enforceability of a no-damages-for-delay clause in a construction contract between the subcontractor and contractor. The subcontractor had brought breach of contract claims based on alleged project delays, but the court dismissed those claims, citing the clause in the subcontract that barred recovery for delay-related damages..

The court found that the subcontract’s unambiguous Section 6.3 barred the subcontractor from recovering delay damages, regardless of other terms in the agreement. Section 6.3 provided:

“Notwithstanding any other provisions of this Subcontract, the Subcontractor agrees to make no claim for additional costs on account of, and assumes the risk of, any and all loss and expense for delay.”

This language was central to the ruling. It clearly allocated the risk of delay to the subcontractor and took precedence over any conflicting provision. The court rejected claims of ambiguity or conflicting terms and dismissed the case based on established precedent.

The subcontractor argued that exceptions to the no-damages-for-delay rule applied, including bad faith, reckless indifference, and breaches of fundamental obligations. The court rejected those arguments, concluding that the alleged conduct—such as poor planning, lack of scheduling detail, and removal of a crane—did not amount to intentional wrongdoing or fundamental breach. These were characterized as “inept administration,” which was insufficient to overcome the no-damage-for-delay clause.

The court also rejected the argument that the delays were unexpected. The subcontract clearly covered delays in starting, carrying out, and finishing the work. The subcontractor’s claim of a year-long delay did not alter the outcome, as the subcontract anticipated such delays.

The subcontractor’s claim that the contractor breached a fundamental obligation by failing to provide a crane was also dismissed. The subcontract stated that hoist size and capacity were limited, placed responsibility for oversized materials on the subcontractor, and gave the contractor discretion over site logistics. The court found no basis to support the argument that crane availability constituted a fundamental obligation under the subcontract.

This decision confirms that New York courts enforce no-damages-for-delay clauses that are clear and specific. Exceptions like bad faith or uncontemplated delays will not apply unless they involve conduct that goes beyond mere poor planning or administrative missteps. Subcontractors seeking to avoid the impact of such clauses must show that delays stemmed from deliberate misconduct or circumstances undisputably outside the scope of the agreement.

Jose A. Aquino (@JoseAquinoEsq on X) is a special counsel at Duane Morris LLP’s New York office, where he is a member of Construction Group,  specializing in construction law, lien law, and government procurement law. He is also a member of the Cuba Business Group.

This blog is prepared and published for informational purposes only and should not be construed as legal advice. The views expressed herein are those of the author and do not necessarily reflect the views of Duane Morris LLP or its individual attorneys.

© 2009- Duane Morris LLP. Duane Morris is a registered service mark of Duane Morris LLP.

The opinions expressed on this blog are those of the author and are not to be construed as legal advice.

Proudly powered by WordPress