Mechanic’s Liens and Licensing Laws: Court Ruling Highlights Strict Enforcement

The recent decision by the Supreme Court, Appellate Division, Second Department, New York, in the case of Mikoma Electric, LLC, et al. v. Otek Builders, LLC, et al.,  emphasizes the importance of adhering to licensing requirements within the construction industry. The case revolves around a dispute where plaintiffs, Mikoma Electric, LLC (Mikoma Electric), and Mikoma Technology of Power and Lights Wiring and Control Limited Liability Partnership (Mikoma Tech), sought to recover damages for breach of contract from Otek Builders, LLC, the general contractor for various WeWork properties.

Mikoma Tech, which was not licensed to perform electrical work in New York City, subcontracted with Otek Builders to carry out electrical work on several properties. Although Mikoma Electric, a licensed entity, obtained the necessary permits and allegedly supervised the work, the court found that this arrangement did not satisfy the licensing requirements stipulated by the Administrative Code of the City of New York § 27–3017(a), This section mandates that electrical work must be performed by a licensed master electrician or under their direct supervision.

The defendants moved to dismiss the complaint and discharge the mechanic’s liens filed by Mikoma Tech, arguing that Mikoma Tech’s lack of a proper license barred its recovery. The Supreme Court initially denied this motion, but upon appeal, the Appellate Division reversed the decision. The appellate court held that the documentary evidence provided by the defendants, which included printouts from the New York City Department of Buildings’ webpage, did not meet the criteria for documentary evidence under CPLR 3211(a)(1). However, the court agreed that Mikoma Tech’s failure to obtain the required license precluded it from recovering under breach of contract or quantum meruit theories and from foreclosing on its mechanic’s liens. Consequently, the Appellate Court dismissed the complaint as to Mikoma Tech and discharged the mechanic’s liens filed by Mikoma Tech.

This decision underscores the strict interpretation of licensing statutes aimed at protecting public health and welfare. The court emphasized that employing or subcontracting work to a licensed entity does not fulfill the statutory requirements if the primary contractor is unlicensed. Consequently, Mikoma Tech’s argument that it should recover because Mikoma Electric, a licensed subcontractor, performed the work was deemed insufficient.

The ruling serves as a critical reminder for contractors and subcontractors in New York City to ensure compliance with licensing regulations to avoid forfeiting their lien rights and the right to recover payments for their work. It also highlights the importance of understanding and adhering to legal requirements in contractual agreements within the construction industry.

Jose A. Aquino (@JoseAquinoEsq on X) is a special counsel in the New York office of Duane Morris LLP, where he is a member of the Construction Group and of the Cuba Business Group.  Mr. Aquino focuses his practice on construction law, lien law and government procurement law. This blog is prepared and published for informational purposes only and should not be construed as legal advice. The views expressed in this blog are those of the author and do not necessarily reflect the views of the author’s law firm or its individual attorneys.

Appellate Court Ruling Clarifies Legal Boundaries of Surety Roles in Mechanic’s Liens

The Supreme Court, Appellate Division, First Department, New York, recently issued a decision in Thorobird Grand LLC et al. v. M. Melnick & Co., Inc., et al., affirming the lower court’s ruling that granted the plaintiffs’ motion for summary judgment on their cause of action alleging willful exaggeration of mechanic’s liens by the defendant Surety.[1] The court invalidated and discharged the Surety’s liens but denied the plaintiffs’ claim for damages under Lien Law § 39-a.

The court determined that the plaintiffs had demonstrated the Surety did not meet the statutory definition of a contractor under Lien Law § 2, thereby invalidating its liens. The plaintiffs had engaged M. Melnick & Co., Inc. as their general contractor for certain projects. In accordance with their agreement, Melnick, along with the Surety acting as Melnick’s guarantor, executed payment and performance bonds. Upon Melnick’s termination, which triggered the Surety’s obligations under the performance bond, the Surety elected to retain Melnick to complete the project.

Subsequently, the plaintiffs initiated an action asserting breach of contract claims against both Melnick and the Surety. In response, the Surety filed three mechanic’s liens for unpaid work, while Melnick filed its own liens. The Surety also counterclaimed against the plaintiffs and additional counterclaim defendants, asserting causes of action for breach of contract, quantum meruit, unjust enrichment, declaratory relief, and lien foreclosures. The plaintiffs then filed an amended complaint that included, among other claims, a cause of action for willful exaggeration of liens.

The plaintiffs moved for partial summary judgment on the willful exaggeration claim, contending that the Surety’s liens were invalid as a matter of law because sureties lack the right to file mechanic’s liens. In opposition, the Surety argued that it qualified as a contractor with standing to file liens and had not waived its lien rights by contract.

The court concluded that the takeover agreement between the parties was clear and unambiguous, establishing that the Surety remained in its capacity as a surety and did not assume the role of a contractor. As a result, the court found the Surety lacked standing to file mechanic’s liens. However, it declined to award damages to the plaintiffs under Lien Law § 39-a, noting that such damages are unavailable when a lien is discharged for reasons other than willful exaggeration.

This decision underscores the importance of precise contractual language and the legal distinction between a surety and a contractor in disputes involving mechanic’s liens.

Jose A. Aquino (@JoseAquinoEsq on X) is a special counsel in the New York office of Duane Morris LLP, where he is a member of the Construction Group and of the Cuba Business Group.  Mr. Aquino focuses his practice on construction law, lien law and government procurement law. This blog is prepared and published for informational purposes only and should not be construed as legal advice. The views expressed in this blog are those of the author and do not necessarily reflect the views of the author’s law firm or its individual attorneys.

[1] 2024 WL 5080524 (1st Dep’t  December 12, 2024)

Mechanic’s Liens: Examining and Enforcing Through Foreclosure Actions vs. Special Proceedings

In the matter of Arcadia Landing, LLC v. CVM Construction Corp., the Supreme Court, Appellate Division, Second Department, New York, recently rendered a decision concerning a mechanic’s lien filed by CVM Construction Corp. The petitioner, Arcadia Landing, LLC, demanded an itemized statement of the lien pursuant to Lien Law § 38, which CVM Construction Corp. provided along with supporting exhibits. However, Arcadia Landing deemed the response insufficient and sought further details through an amended petition.

The Supreme Court, Nassau County, presided over by Judge Eileen C. Daly-Sapraicone, denied the amended petition and dismissed the proceeding. Upon appeal, the Appellate Division affirmed the lower court’s order.

Lien Law § 38 mandates that a lienor must furnish a written statement detailing the labor and materials that constitute the lien, along with the terms of the contract. In this instance, CVM Construction Corp. complied by listing the items of work and asserting that the work was completed. The petitioner disputed the completion of the work, but the court determined that such disputes are more appropriately resolved in an action to enforce the mechanic’s lien rather than through additional demands for information in the special proceeding under Lien Law § 38.

This decision is consistent with the precedent established in Matter of Mr. White, L.L.C. v. Pink Shirt Constr., Inc., where the court exercised its discretion to vacate and cancel a mechanic’s lien because the respondent failed to commence an action to enforce the lien as required by Lien Law § 59. The validity of the lien and any disputes regarding the completion of work were to be resolved in a foreclosure action, which the respondent in that case admitted it never commenced. Similarly, in the Arcadia Landing case, the court emphasized that the appropriate forum for resolving disputes about the completion of work is in a foreclosure action, not through procedural demands for more detailed statements.

This decision underscores the critical importance of resolving factual disputes concerning the completion of work delineated in a mechanic’s lien within the context of a foreclosure action, rather than through a special proceeding seeking an itemization of the lien. The appellate court’s affirmation of the lower court’s decision elucidates the judiciary’s position on the adequacy of compliance with Lien Law § 38 and delineates the proper procedural avenues for addressing such disputes.

Jose A. Aquino (@JoseAquinoEsq on X) is a special counsel in the New York office of Duane Morris LLP, where he is a member of the Construction Group and of the Cuba Business Group.  Mr. Aquino focuses his practice on construction law, lien law and government procurement law. This blog is prepared and published for informational purposes only and should not be construed as legal advice. The views expressed in this blog are those of the author and do not necessarily reflect the views of the author’s law firm or its individual attorneys.

© 2009-2025 Duane Morris LLP. Duane Morris is a registered service mark of Duane Morris LLP.

The opinions expressed on this blog are those of the author and are not to be construed as legal advice.

Proudly powered by WordPress