The current solar Feed-in-Tariff for on-grid projects in Vietnam is 2,086 Vietnamese dong/kWh (equivalent to 9.35 UScents/kWh) (VAT excluded). According to Decision 11/2017/QD-TTg, this solar FIT applies for projects which come into operation before 30 June 2019 and within 20 years from the commercially operational date (“COD”) (i.e., the date when the solar plant is ready to sell electricity to the buyer – EVN).
However, from our informal high level contact within the MOIT recently, it is very likely that the solar FIT of US9.35 cents/kWh will continue to apply beyond the original COD (i.e. 30 June 2019). The deadline shall be likely extended for another half a year or another year for solar projects across Vietnam, except for projects in Ninh Thuan. This policy is not yet formally adopted but very likely will be publicized at the end of this year.
For solar projects in Ninh Thuan, the COD deadline extension will be longer (i.e. for another one and a half year from 30 June 2019). This is due to the fact that, in Ninh Thuan province, nuclear energy development has been stopped and the Government would like to develop solar energy there to support the province’s economic development.The special policy for solar projects in Ninh Thuan will be coming very soon, according to our MOIT contact. He informed us that the Deputy Prime Minister has already approved this special policy for Ninh Thuan and all await formal procedures.
We will closely monitor to update on any further changes.
Please contact Dr. Oliver Massmann under omassmann@duanemorris.com if you have questions on the topic or any other lawyer in our office listing. Dr. Oliver Massmann is the General Director of Duane Morris LLC.