VIETNAM’S ENERGY OPPORTUNITY: FROM MARKET POTENTIAL TO INVESTABLE PROJECTS

A Practical Action Plan for Successful Market Entry

Vietnam is entering one of the most consequential periods of energy-sector expansion in Southeast Asia.

Rapid economic growth, industrialization, increasing electricity demand, the continuing relocation and expansion of international manufacturing into Vietnam, growing data-centre demand, and the decarbonization requirements of multinational corporations are converging with an unprecedented expansion of the country’s power system.

Vietnam’s revised Power Development Plan VIII (“PDP8”), approved under Decision No. 768/QD-TTg dated 15 April 2025, significantly expanded the country’s ambitions for renewable energy, battery storage, grid infrastructure and nuclear power. The revised planning framework envisages approximately USD 134.7 billion of investment through 2030 and potentially more than USD 500 billion through 2050. (moit.gov.vn⁠)

For international investors, developers, utilities, infrastructure funds, engineering companies, technology providers and project-management specialists, however, the key question is no longer simply whether Vietnam offers an attractive energy opportunity.

The real question is: how should an international participant enter Vietnam’s energy market in a manner that is commercially viable, scalable, legally secure and capable of producing an investable project?

The answer is not simply to establish a Vietnamese subsidiary and start looking for opportunities.

The more effective sequence is:

Identify the opportunity.
Verify the partner.
Validate the project.
Secure the route to market.
Structure the investment.
Then deploy capital.

That distinction is fundamental.

1. START WITH THE INVESTMENT THESIS – NOT THE CORPORATE VEHICLE

Vietnam should not initially be approached as a conventional greenfield market.

Before establishing a final investment structure, an investor should determine precisely which part of Vietnam’s energy transition best matches its capital, technology, expertise and risk appetite.

The opportunity extends considerably beyond conventional solar and wind generation.

The revised PDP8 substantially increased targets for onshore and nearshore wind, offshore wind and battery storage. It also reintroduced nuclear power and calls for very substantial development of transmission and other energy infrastructure. (Trade.gov⁠)

Potential areas of market entry therefore include:

  • renewable generation, particularly wind and solar;
  • battery energy storage systems (“BESS”);
  • grid and transmission infrastructure;
  • corporate renewable-power and direct power purchase arrangements;
  • industrial-zone energy infrastructure;
  • LNG and gas-to-power;
  • offshore wind and associated marine infrastructure;
  • engineering, programme and project management;
  • smart-grid and digital energy solutions;
  • energy infrastructure for data centres and advanced manufacturing;
  • equipment and technology supply;
  • energy-efficiency solutions; and
  • longer-term nuclear engineering, construction, technology, training and supply-chain opportunities.

The first step should therefore be the preparation of a Vietnam Energy Investment Thesis defining:

What sector do we want to enter?
How much capital are we prepared to deploy?
What level of development risk are we prepared to accept?
Do we seek control, a strategic minority investment or a service position?
What return do we require?
What is our investment horizon?
And how can Vietnam become a scalable regional platform rather than a single isolated transaction?

Only after answering those questions should projects and partners be shortlisted.

2. THE FASTEST ROUTE MAY BE TO BUY OR PARTNER RATHER THAN BUILD FROM ZERO

For many international investors, the most efficient entry route will be an acquisition, joint venture or strategic development partnership with an established Vietnamese developer, rather than developing the first project entirely from greenfield stage.

A capable Vietnamese developer may bring valuable local capabilities:

  • an existing development pipeline;
  • knowledge of the permitting environment;
  • established land-development experience;
  • local implementation capacity;
  • understanding of provincial procedures;
  • familiarity with power-sector institutions; and
  • access to existing project opportunities.

The foreign investor can contribute:

  • capital;
  • technology;
  • international project-development expertise;
  • financing capability;
  • international governance standards;
  • major-project management expertise;
  • global customer relationships; and
  • access to international strategic partners.

If properly structured, that combination can significantly shorten the route from market entry to a bankable project.

But acquiring or partnering in an “energy project” is not enough.

The investor must acquire the right project – and, even more importantly, work with the right partner.

3. APPLY A STRICT INVESTMENT GATE BEFORE CAPITAL IS COMMITTED

Vietnam’s energy opportunity is considerable, but both project quality and partner quality can vary substantially.

A disciplined investor should therefore apply a strict investment-gate system before entering into substantive partnership arrangements or committing material capital.

GATE 1 – COMPLETE DUE DILIGENCE ON THE POTENTIAL PARTNER

This is one of the most important elements of the entire market-entry strategy.

A complete due diligence review of the proposed Vietnamese partner, project sponsor, developer or shareholder group should take place before substantive partnership discussions become advanced.

The investor should know exactly who it is dealing with before deciding how it wishes to invest with them.

This means that partner due diligence should not be postponed until after a joint-venture structure has already been commercially agreed.

It should help determine whether that discussion should take place at all.

The review should examine, among other matters:

  • ultimate beneficial ownership and actual control;
  • ownership history and unexplained changes in shareholders;
  • corporate structure and related companies;
  • financial standing;
  • funding capability;
  • outstanding indebtedness and security arrangements;
  • tax position where material;
  • litigation and arbitration history;
  • enforcement and insolvency history;
  • regulatory and compliance history;
  • anti-bribery and anti-corruption risks;
  • sanctions exposure;
  • politically exposed persons and relationships presenting compliance or reputational concerns;
  • relationships with related parties;
  • actual development track record;
  • experience obtaining and maintaining energy, investment, construction and land approvals;
  • historical dealings with provincial and central authorities;
  • disputes with previous investors, banks, contractors, suppliers or JV partners;
  • market reputation;
  • technical and management capability;
  • the accuracy of claimed project-development achievements;
  • whether the partner genuinely owns or controls the projects or development rights it claims to control; and
  • willingness to operate under transparent international governance, reporting, audit and compliance standards.

This investigation should be sufficiently advanced before the investor:

  • shares substantial commercially sensitive information;
  • enters exclusivity;
  • signs a binding joint-venture framework;
  • advances development funding;
  • pays a significant deposit;
  • becomes dependent upon the proposed partner; or
  • publicly associates its reputation with that partner.

A good project attached to the wrong partner can become a bad investment very quickly.

Likewise, a well-connected partner cannot transform a fundamentally defective project into a bankable one.

GATE 2 – COMPLETE DUE DILIGENCE ON THE PROJECT

Only after the proposed partner has passed preliminary diligence should the investor proceed to detailed assessment of the actual asset or development opportunity.

At minimum, the investor should verify:

Planning:
Is the project properly included within the applicable national, regional or provincial planning and implementation framework?

Investment approvals:
Are the relevant investment approvals valid, complete, current and capable of supporting the contemplated transaction?

Project ownership:
Does the proposed seller, sponsor or joint-venture partner actually own the relevant company, rights, assets and development position?

Land:
Are the project site and land-use arrangements legally secured? Are there outstanding compensation, clearance, lease, land-use-purpose or term issues?

Grid:
Is there a realistic grid-connection solution? What transmission upgrades are required? Who bears their cost? What are the congestion and curtailment risks?

Offtake:
Who ultimately pays for the electricity? Under what contractual structure? What is the credit quality of the counterparty?

DPPA:
Can the project and intended electricity consumers participate in the applicable direct power trading regime?

Permitting:
What environmental, construction, electricity, fire-safety and other approvals have been obtained, and which remain outstanding?

Technical feasibility:
Do resource, design, equipment and site conditions support the projected output?

Financing:
Can lenders obtain an acceptable security package? Is the proposed revenue model sufficiently bankable?

Corporate liabilities:
Does the project company contain historical tax, employment, litigation, shareholder, related-party or other liabilities?

Development timetable:
Can all remaining approvals and implementation milestones realistically be achieved?

Economics:
Does the project remain financially viable when realistic assumptions are applied for connection costs, curtailment, construction costs, financing, taxation and delays?

The investor should then classify the opportunity:

GREEN – partner and project are investable.

AMBER – investment may proceed only after clearly identified conditions are satisfied and risks mitigated.

RED – do not enter the partnership and do not invest.

This front-loaded due diligence can save months of negotiations and substantial professional fees.

The principle should be simple: in Vietnam, due diligence should not begin after the partnership has effectively been agreed. It should determine whether the partnership discussion should begin at all.

4. FOLLOW THE CUSTOMER – THE DIRECT POWER MARKET CHANGES THE INVESTMENT MODEL

One of the most significant developments in Vietnam’s electricity sector is the development of direct electricity trading.

Decree No. 57/2025/ND-CP created the regulatory mechanism for direct electricity trading between renewable-energy generators and large electricity consumers, including arrangements through private connection lines and through the national grid. (Chính Phủ⁠)

That regime was subsequently amended by Decree No. 243/2026/ND-CP, issued and effective on 26 June 2026. (Vanban Chinh Phu⁠)

The commercial significance is substantial.

Instead of beginning with the question:

“Where can we build another power plant?”

investors should increasingly begin with:

“Where are Vietnam’s strongest electricity consumers – and what generation, storage and infrastructure do they need?”

This fundamentally changes project origination.

Industrial parks, major manufacturing centres, electronics producers, data centres and multinational companies increasingly value access to reliable and cleaner electricity.

That allows sophisticated investors to think beyond an isolated generation asset and towards an integrated business model combining:

Generation + Storage + Grid Access + Corporate Demand + Contractual Offtake.

5. BUILD A PORTFOLIO AROUND DEMAND – NOT A COLLECTION OF UNRELATED PROJECTS

A strong Vietnam energy strategy should aim to create a coherent platform rather than accumulate disconnected assets.

The investor should map:

Major load centres → industrial zones → large electricity consumers → available generation → grid capacity → storage requirements → direct power/offtake opportunities.

This may produce substantially greater commercial resilience than investing in isolated projects purely because they happen to be available for sale.

For example, a renewable-generation portfolio combined with BESS and strategically located industrial demand may create a more attractive long-term proposition than a stand-alone generation facility with a single conventional route to market.

The ultimate objective should be to build an energy ecosystem around demand.

6. SELECT THE VIETNAMESE PARTNER AS CAREFULLY AS THE PROJECT

Once the initial partner diligence has been passed, the question becomes whether the parties can construct a durable working relationship.

The joint-venture documentation should therefore be treated as an investment-protection instrument, not merely a company-formation document.

Depending upon the structure, protections should include:

  • clearly defined capital obligations;
  • reserved matters;
  • board representation;
  • minority protections;
  • information rights;
  • audit rights;
  • anti-dilution mechanisms;
  • related-party controls;
  • anti-corruption and compliance undertakings;
  • restrictions on competing activities;
  • transfer restrictions;
  • change-of-control provisions;
  • deadlock procedures;
  • default provisions;
  • valuation mechanisms;
  • call and put rights where appropriate;
  • exit rights;
  • dispute-resolution provisions; and
  • robust governing-law and enforcement arrangements.

The principle is:

Local capability is valuable. Local dependency is dangerous.

An international investor should benefit from its Vietnamese partner’s strengths without becoming unable to protect or exit its own investment.

7. STRUCTURE THE INVESTMENT ONLY AFTER THE OPPORTUNITY HAS BEEN VALIDATED

Once the partner and project have passed preliminary investment gates, the investor can select the most suitable transaction structure.

Depending upon the opportunity, this might include:

Share Acquisition

Acquire an equity interest in an existing Vietnamese project company.

Joint Venture

Establish or invest in a Vietnamese development platform together with a credible domestic partner.

Portfolio Investment

Acquire or develop interests in several projects under a single strategic platform.

Staged Development Partnership

Provide development capital against clearly defined milestones, with further equity deployed only when agreed conditions have been achieved.

Strategic Minority Investment

Take a protected minority interest while retaining rights over material decisions.

Service-Led Market Entry

For engineering, project-management, technology and infrastructure companies, the first entry may be through contracts and mandates rather than capital investment.

This can be particularly effective.

A company can establish market credibility, build relationships and develop proprietary knowledge of Vietnam before making a larger investment decision.

The principle remains:

The corporate structure should follow the commercial opportunity – not determine it.

8. DO NOT IGNORE GRID AND STORAGE

A power project is not valuable merely because it can generate electricity.

That electricity must reach somebody who can use and pay for it.

Vietnam’s rapidly changing generation mix makes transmission, grid management and storage increasingly important.

Under the revised PDP8 framework, Vietnam targets approximately 10,000–16,300 MW of battery storage capacity by 2030. The Ministry of Industry and Trade has also indicated that concentrated solar projects are expected to incorporate storage at a minimum ratio of 10% of installed capacity for two hours. (moit.gov.vn⁠)

This creates a significant investment opportunity in its own right.

BESS should therefore not merely be viewed as an accessory to solar or wind.

It should be analysed as part of the economic architecture of the project.

Likewise, grid analysis should happen before the acquisition decision, not after it.

A project with exceptional renewable resources but serious transmission constraints may be a poor investment.

A project with slightly lower natural resources but excellent grid access, storage capability and a strong customer base may be substantially more valuable.

9. THINK BEYOND RENEWABLE GENERATION

Vietnam’s energy transformation is much broader than the development of wind and solar farms.

The revised PDP8 itself illustrates the scale of required development across generation, storage, transmission, new technologies and the broader electricity system. (Trade.gov⁠)

This creates major opportunities for businesses that do not necessarily wish to own generation assets.

Potential entry points include:

  • programme management;
  • project management;
  • owner’s engineering;
  • EPC and construction management;
  • grid engineering;
  • transmission infrastructure;
  • BESS;
  • offshore-wind supporting infrastructure;
  • port and marine infrastructure;
  • industrial energy systems;
  • data-centre electricity infrastructure;
  • smart-grid technologies;
  • digital energy management;
  • technical consulting;
  • specialist equipment supply; and
  • project controls.

For many international engineering and infrastructure businesses, service-led entry may be the lowest-risk first step into the Vietnamese energy market.

That local operating position can later become the platform from which investment opportunities are originated.

10. NUCLEAR – POSITION NOW, INVEST LATER

Vietnam’s revived nuclear programme should be treated differently from conventional renewable investments.

The revised PDP8 brought nuclear power back into Vietnam’s long-term generation strategy, including the Ninh Thuan nuclear projects. (Trade.gov⁠)

For many international businesses, the immediate opportunity is not necessarily direct investment in an entire nuclear plant.

The more realistic strategy may be to position early in the surrounding ecosystem:

  • engineering;
  • project and programme management;
  • project controls;
  • construction services;
  • technology;
  • nuclear safety;
  • specialist equipment;
  • workforce development;
  • training;
  • localisation;
  • quality assurance; and
  • supply-chain development.

Major infrastructure markets tend to reward early positioning.

Companies that establish credibility and relationships during the preparatory stages may be considerably better placed when significant procurement packages enter the market.

11. THE 100-DAY VIETNAM ENERGY MARKET ENTRY PLAN

A serious investor should be capable of moving from general market interest to a defined investment strategy within approximately 100 days.

DAYS 1–30: MAP AND SCREEN

Define the Vietnam investment thesis.

Select priority energy subsectors.

Define capital limits and required returns.

Identify major electricity-demand centres.

Map industrial parks, manufacturing clusters and other major users.

Identify approximately 10–15 prospective projects and Vietnamese partners.

Immediately undertake preliminary integrity and background diligence on every potential partner.

Eliminate unsuitable counterparties before serious negotiations begin.

Conduct preliminary:

  • planning review;
  • ownership review;
  • land review;
  • grid review;
  • licensing review;
  • project-status review; and
  • offtake analysis.

Reduce the initial universe to approximately three to five credible opportunities.

DAYS 31–60: TEST AND VERIFY

Meet only the shortlisted partners.

Execute appropriate confidentiality arrangements.

Obtain project documentation and data-room access.

Undertake red-flag:

  • legal due diligence;
  • regulatory due diligence;
  • technical due diligence;
  • tax due diligence;
  • financial due diligence;
  • compliance due diligence; and
  • commercial due diligence.

Verify the partner’s claims independently.

Test grid availability and curtailment risk.

Analyse DPPA or other offtake structures.

Meet potential electricity consumers where appropriate.

Determine indicative project valuation.

Estimate the required capital.

Develop preliminary transaction structures.

Select one or two preferred opportunities.

DAYS 61–100: STRUCTURE AND EXECUTE

Negotiate an MoU, term sheet or exclusivity arrangement only after the principal due-diligence gates have been satisfied.

Launch full transaction due diligence.

Confirm the required investment and regulatory approvals.

Determine the optimal acquisition or JV structure.

Develop the financing strategy.

Negotiate the shareholder arrangements.

Secure or advance the offtake strategy.

Establish the Vietnamese investment vehicle where necessary.

Develop the government and regulatory engagement strategy.

Agree the transaction timetable.

Move the selected anchor investment toward signing.

By Day 100, the investor should no longer be “studying Vietnam.”

It should have:

a verified partner;
a selected project;
a clear grid strategy;
an identified customer or route to market;
a regulatory roadmap;
a transaction structure;
a financing plan; and
a defined path toward investment.

CONCLUSION – DO NOT SIMPLY ENTER VIETNAM: ENTER THROUGH THE RIGHT PROJECT

Vietnam’s energy transition presents an exceptional combination of rapidly increasing electricity demand, major industrial growth, enormous infrastructure requirements, international decarbonisation pressure and a policy environment increasingly designed to mobilise substantial private investment.

But a large market does not automatically produce a good investment.

The successful international investor should therefore avoid the temptation to start with a company, office or generic local partnership.

Start with the investment opportunity.

Then follow a disciplined sequence:

1. FIND THE DEMAND

Identify the industrial consumers, manufacturing clusters, data centres and other major users around which an economically resilient energy business can be built.

2. FIND THE PROJECT

Select projects that genuinely fit Vietnam’s planning, grid and regulatory framework.

3. VERIFY THE PARTNER – BEFORE SUBSTANTIVE PARTNERSHIP DISCUSSIONS

Conduct complete legal, financial, compliance, ownership, reputation and track-record due diligence.

If the partner fails the integrity test, stop.

4. VERIFY THE GRID

A generation asset without a commercially realistic route to the customer is not an investment proposition.

5. SECURE THE OFFTAKE

Understand exactly who will buy the electricity, under which mechanism and at what commercial risk.

6. COMPLETE PROJECT DUE DILIGENCE

Validate land, approvals, corporate ownership, technical feasibility, project economics, licensing and implementation timetable.

7. STRUCTURE FOR CONTROL AND PROTECTION

Choose acquisition, JV, staged investment or another structure that protects capital while allowing the project to move forward.

8. INVEST IN STAGES

Where appropriate, tie capital deployment to measurable regulatory, technical and commercial milestones.

9. MAKE THE FIRST TRANSACTION AN ANCHOR – NOT AN END POINT

Use the first investment to establish:

  • local execution capability;
  • government and industry relationships;
  • project-development knowledge;
  • customer relationships;
  • financing capability; and
  • a credible operating track record.

Then scale.

The most effective formula for entering Vietnam’s energy market can therefore be summarized in one line:

Demand → Partner Due Diligence → Project → Grid → Offtake → Full Due Diligence → Structure → Capital → Scale.

That sequence matters.

Do not commit capital and then discover the risks.
Identify the risks first – and let the results determine whether capital should be committed at all.

For many international investors, the optimum first transaction will therefore not be a speculative greenfield development and not a blind acquisition.

It will be a carefully screened investment, acquisition or joint venture in an advanced project or platform, with a fully diligence partner, credible regulatory position, realistic grid access and identifiable bankable demand.

And the first transaction should never be viewed simply as one Vietnamese energy project.

It should be designed as the anchor for a long-term Vietnam energy platform.

From that anchor, the investor can expand into renewable generation, storage, corporate power supply, grid infrastructure, industrial energy solutions, offshore wind, major-project services and, over time, Vietnam’s wider nuclear and energy infrastructure ecosystem.

Vietnam does not lack energy opportunities.

What it lacks—and what sophisticated investors can provide—is the disciplined conversion of those opportunities into properly diligence, financeable and executable investments.

The competitive advantage will therefore belong not to the investor who enters Vietnam first, but to the investor who enters correctly: through the right opportunity, with the right partner, after the right due diligence, using the right structure—and with a clear plan to scale.

That is the practical route into Vietnam’s energy market.

***

For more information on the above, please do not hesitate to contact the author Dr. Oliver Massmann under omassmann@duanemorris.com. Dr. Oliver Massmann is the General Director of Duane Morris Vietnam LLC.

ベトナムにおけるバイオマス発電 2026年 – 融資可能なPPAを巡る競争 第12号通達が外国人投資家にとってゲームチェンジャーとなる理由 – そしてPPAの背後にいる機関や人物を把握することが、プロジェクトの資金調達完了を左右する理由 

執筆:オリバー・マスマン博士 (Dr. Oliver Massmann) デュアン・モリス・ベトナムLLC パートナー兼総支配人

ベトナムのバイオマス発電セクターは、根本的に新たな局面を迎えています。

長年にわたり、外国人投資家は主に固定価格買取制度(FIT)、投資ライセンス、および利用可能な農業残渣という観点からベトナムのバイオマスを評価してきました。 しかし、そのアプローチはもはや十分ではありません。

現在、ベトナムははるかに洗練された電力市場へと移行しつつあります。プロジェクトごとの価格設定、交渉による電力販売契約(PPA)、直接電力購入契約(DPPA)、競争的電力市場への参加、系統へのアクセス、原料の確保、そしてプロジェクト・ファイナンスにおける融資適格性(バンカビリティ)が、バイオマスプロジェクトの成否を決定づけるようになっています。

外国人ディベロッパー、インフラファンド、電力会社、戦略的投資家、および金融機関にとって、これは機会と複雑さの双方をもたらします。

今日における極めて重要な問いは、もはや単なる「ベトナムでバイオマス発電所を開発できるか?」ではありません。 真に問われるべきは以下の点です。

  • 融資可能な(バンカブルな)PPAを交渉できるか?
  • その売電価格でプロジェクト・ファイナンスを支えることができるか?
  • 金融機関は、出力制御、法令変更、契約解除、支払い、および為替リスクに対して十分な保護を得られるか?
  • 債務返済期間およびプロジェクトの全期間を通じて、十分かつ安定した原料確保が可能か?
  • ベトナムのDPPA制度を通じて、プロジェクトは企業のオフテイカー(電力引取者)にアクセスできるか?

そして、おそらく最も重要な問いは次の通りです。 投資家は、ベトナムのどの機関の、どの責任ある意思決定者が、重要な商業的および規制上の課題を実際にコントロールしているかを正確に理解しているか?

本格的な投資家にとって、これらの疑問は、すでに数百万ドルの資金が投じられた後ではなく、プロジェクト開発の初期段階で対処されるべきものです。

1. ベトナムはバイオマス発電の大幅な拡大を計画しています

2025年4月15日付の首相決定第768号/QĐ-TTgにより承認された「改訂版第8次国家電力開発計画(PDP8)」において、バイオマスは将来の電源構成において重要な役割を与えられています。

ベトナムは以下の目標を掲げています。

  • 2030年までに 約1,523~2,699 MWのバイオマス発電
  • 2050年までに 4,829~6,960 MW

政府は、農業、林業、木材加工の残渣を利用し、環境保護とサーキュラーエコノミー(循環型経済)に同時に貢献するバイオマスおよび廃棄物発電プロジェクトを特に奨励しています。(政府方針) これはベトナムにとって特に重要です。

ベトナムには、以下から発生する豊富なバイオマス資源があります。

  • 米の生産
  • サトウキビ
  • コーヒー
  • キャッサバ
  • ココナッツ
  • 林業
  • 木材加工
  • 畜産および農業活動
  • 産業用有機廃棄物

また、バイオマスは不安定な再生可能エネルギーに比べて、技術的に重要な利点を持っています。 太陽光や風力とは異なり、適切に構築されたバイオマス発電所は、給電指令に従った再生可能エネルギーの発電、比較的高い設備利用率、そして適切な場合には熱電併給(コージェネレーション)を提供することができます。

これにより、バイオマスは以下の周辺において特に魅力的なものとなります。

  • 工業団地
  • 製糖工場
  • 精米施設
  • パルプ・製紙工場
  • 木材加工クラスター
  • 食品加工施設
  • 電力と蒸気の両方を必要とする産業消費者

最も強力なプロジェクトとは、エネルギー生産、原料供給、および産業消費が、融資可能な一つの経済的エコシステムとして統合されているものになっていくでしょう。

2. 外国人投資家は過去の「FITはいくらか?」という考え方を捨てなければなりません

歴史的に、ベトナムのバイオマス分野に参入する投資家は、しばしば次のような質問から始めていました。 「バイオマスのFIT(固定価格買取価格)はいくらですか?」 その質問の妥当性は薄れつつあります。

ベトナムは、プロジェクト固有の電力価格設定フレームワークへと移行しており、発電価格とPPAの経済性は、根本的な投資および運営の前提条件によって裏付けられなければならなくなっています。

これは国際的投資家にとって、商業戦略を単に公表されたFITを適用することから、次のようにシフトさせなければならないことを意味します。 すなわち、価格の根拠を構築し、説得力のある財務前提条件を準備し、PPAを交渉し、結果として得られる収益構造が資金調達可能であることを確実にすることです。

これは大きな変化です。 同時に、電力分野の弁護士、財務アドバイザー、技術コンサルタントが、開発サイクルのもっと早い段階で連携しなければならないことも意味しています。

3. 商工省第12/2025/TT-BCT号通達:外国人投資家にとって最も重要なPPAの進展

これは、ベトナムの電力プロジェクトにおける外国人投資家にとって、最も重要な法整備と言えるかもしれません。

商工省(MOIT)の第12/2025/TT-BCT号通達は、PPAの規定された主要内容が、売電者と買電者の間での交渉および署名の基礎となることを明確に定めています。 さらに重要なのは、第19条において、売電者と買電者がベトナムの法律を遵守する限り、追加の契約条項を交渉し合意する権利を有すると明記されている点です。(LuatVietnam)

これは強調に値します。 PPAはもはや、単に受け入れるだけの定型契約として見なされるべきではありません。 第12号通達は、交渉のための明確な規制上の基盤を作り出しました。 これは、資金調達を可能にする(バンカブルにする)ための大きな機会です。

このフレームワークはその後、第54/2025/TT-BCT号通達などによって修正されており、したがって、個々のプロジェクトごとに最新の統合された制度を慎重に検討する必要があります。統合された規定においても、引き続きPPAの交渉による修正と補足が想定されています。(moit.gov.vn)

しかし、国際的な金融機関にとって、PPAが「交渉可能」であることを知るだけでは不十分です。 重要な問いは次の通りです。 「具体的に何を交渉すべきか?」

4. 融資可能な(バンカブルな)バイオマスPPAの条件とは?

バンカブルなPPAとは、単に価格が記載された契約書ではありません。 国際的なプロジェクト・ファイナンスのレンダー(貸し手)は、事実上すべての主要なプロジェクトリスクの配分を精査します。

ベトナムのバイオマスプロジェクトにおいて、投資家はPPAが以下の事項を適切に処理しているかを慎重に評価すべきです。

支払い保証(Payment security 支払いのリスクを誰が負うか? 支払いが遅延した場合、どうなるか? 遅延損害金と執行のメカニズムは適切か? プロジェクトの収益で国内外の債務を安全に返済できるか?

出力制御とみなし発電(Curtailment and deemed generation 発電所が技術的に稼働可能で発電の準備ができているにもかかわらず、系統の混雑、系統運用者の指示、または出力制御により電力の給電ができない場合、どうなるか? レンダーは、プロジェクト会社がそのリスクを全面的に負うのかどうかを確認したがります。

法令変更(Change in law バイオマス発電所は20〜30年間稼働する可能性があります。 その間、電力規制、環境基準、税制、系統ルール、および技術要件がすべて変更される可能性があります。 したがって、PPAに適切な法令変更のメカニズムがあるかを検討する必要があります。

契約解除に伴う補償(Termination compensation これは最も重要なバンカビリティ条項の一つです。 プロジェクトの未返済債務が返済される前にPPAが解除された場合、どのような補償が得られるか? 国際的なレンダーは、契約解除時の支払いが未返済の債務や投資資本を適切に保護しないプロジェクトには融資をしたがらない可能性があります。

レンダーの介入権(Lender step-in rights プロジェクト・ファイナンスのレンダーは通常、プロジェクトの主要契約が解除される前に、デフォルト(債務不履行)を治癒したり、プロジェクトに介入(ステップイン)したりする機会を期待します。 これはPPAだけでなく、以下においても検討されるべきです。

  • 土地の契約
  • 原料供給契約
  • EPC契約
  • O&M契約
  • (法的に可能な場合)プロジェクトの主要な許可

為替リスク(Foreign-exchange risk プロジェクトがベトナム・ドンで収益を受け取る一方で、多額の債務、設備、EPCコストがUSD、EUR、JPY、KRWなどの外貨建てである場合があります。 投資家は、事業の初日からそのミスマッチをモデル化しなければなりません。

不可抗力(Force majeure 定義が重要です。 同様に以下の点も重要です。

  • 通知義務
  • 免責期間
  • 損害軽減義務
  • 長期化する不可抗力
  • 解除権
  • 補償への影響

給電および系統リスク(Dispatch and grid risk PPAは以下と併せて分析されなければなりません。

  • 系統連系契約
  • 系統運用ルール
  • 給電義務
  • 計量に関する取り決め
  • 電力市場ルール
  • NSMOの要件

試運転とCOD(商業運転開始日)(Commissioning and COD 商業運転のメカニズムは以下と整合している必要があります。

  • EPCのスケジュール
  • 資金調達のマイルストーン
  • 系統の可用性
  • 試験手順
  • 性能保証
  • 最終期限(ロングストップ・デート)

紛争解決(Dispute resolution 投資家は、関連する取引スキームの下でベトナム法がどのような紛争解決の選択肢を認めているか、そしてそのメカニズムがレンダーや投資委員会の要件を満たすかどうかを正確に理解する必要があります。

5. 12号通達は機会を創出するが、すべての条項が自動的に受け入れられるわけではない

外国人投資家は現実的になるべきです。 第12号通達があるからといって、国際的なレンダーが要求するすべての条項がベトナムの買電者に自動的に受け入れられるわけではありません。 また、規制上の制限が消滅するわけでもありません。

第12号通達が提供しているのは、極めて価値のあるものです。それは、 当事者がPPAを交渉し、補足するための明確な法的根拠です。

これにより戦略が変わります。 標準の条文の欠陥を単に指摘するのではなく、外国人投資家は構造化された「バンカビリティ交渉パッケージ」を準備すべきです。 提案する各修正案について、投資家は以下の点を説明できなければなりません。

  1. なぜその条項が必要なのか
  2. どのプロジェクトリスクに対処するものか
  3. なぜレンダーがそれを要求するのか
  4. ベトナム法においてそれが許可されているか
  5. 他で同等のリスク配分が存在するか
  6. 同じ目的を達成するための代替案(ドラフト)は何か
  7. そのリスクがプロジェクト会社に残された場合、経済的にどのような影響があるか

したがって、最良のPPA交渉は、外国法のスタイルに基づく修正リストとして行われるものではありません。 それは、「バンカビリティ(融資適格性)に関する対話」として行われるべきなのです。

6. 最も過小評価されている要因:PPAの問題を実際にコントロールしているのは誰かを把握する

外国人投資家はしばしば、「ベトナム政府との交渉」と大まかに語ることがあります。 それでは、電力プロジェクトを成功させるには不正確すぎます。 すべてを決定する単一の機関は存在しません。 問題ごとに、責任を負う機関は異なります。

プロジェクトのスキームにもよりますが、関連する機関のステークホルダーには以下が含まれます。

商工省(MOIT MOITは、電力セクターの政策と規制の中心です。 その電力当局は、以下の点に関して重要な役割を果たしています。

  • 電力価格の算定手法
  • 発電価格のフレームワーク
  • 市場規制
  • 電力法の施行
  • PPAの規制
  • 規制に関するガイダンス

ベトナム電力グループ(EVN EVNはベトナムの電力セクターにおいて最も重要な機関の一つであり、多くの系統連系プロジェクトにおいて不可欠な商業パートナーまたはステークホルダーです。

EVN電力取引会社(EVNEPTC 従来の電力プロジェクトにおいて、EVNEPTCはEVNシステム内で実質的なPPA交渉と電力取引の機能を担っているため、特に重要となります。 外国人投資家は、法人レベルでのEVNだけでなく、問題となっている商業的課題の交渉を実際に担当しているのはどの部門かを理解する必要があります。

国家電力系統・市場運用会社(NSMO NSMOは以下の点で決定的な役割を果たします。

  • 系統運用
  • 給電指令
  • 市場運用
  • 市場の決済
  • 国家系統を利用したDPPAの実施 競争的電力市場に参加するプロジェクトにとって、NSMOの役割は根本的なものとなり得ます。

地方当局 関連する省人民委員会および省の各部局は、以下において重要になる場合があります。

  • プロジェクトの実施
  • 土地
  • 地域計画
  • 建設
  • 環境に関する調整
  • 投資手続き
  • 地域のインフラ

送配電会社および電力公社 関連する送電または配電事業者は、以下に直接影響する問題を管理している場合があります。

  • 系統連系
  • 技術設計
  • 計量
  • 相互接続工事
  • 受電・送電開始

7. PPAの背後にいる関係者を把握することで、プロジェクトの実行力は飛躍的に向上する

この点は正しく理解されるべきです。 これは特別扱いを受けるためのものではありません。 以下を知るためのものです。

  • 特定の問題について法的な責任を負っているのは誰か
  • 技術的な専門知識を持っているのは誰か
  • 交渉の権限を持っているのは誰か
  • 逸脱事項を承認しなければならないのは誰か
  • 規制上の指針を提供しなければならないのは誰か
  • ある機関が行動を起こす前に、どの機関に協議しなければならないか
  • 責任を持って提案を承認する前に、意思決定者がどのような書類を必要としているか

ベトナムの電力プロジェクトは高度に組織的・制度的です。 投資家は、解決する権限を持たない組織を相手に問題を追求し、数ヶ月を無駄にする可能性があります。 逆に、意思決定の構造を適切にマッピング(可視化)する投資家は、効率性を大幅に向上させることができます。

すべての主要なPPAの課題について、機関別の責任マトリックスを作成することをお勧めします。 例:

課題主な窓口機関
PPAの商業交渉関連する電力買電者 / EVNEPTC
発電価格の算定手法MOIT / 管轄の電力当局
系統連系関連する送配電事業者
給電指令NSMO
卸売電力市場NSMO / 管轄の市場機関
DPPAの登録NSMO および関連当事者
土地 / プロジェクトの実施地方当局
環境承認管轄の環境当局

正確な役割分担は、プロジェクトごとに確認する必要があります。 この機関マッピングは、正式なPPA交渉が始まる前に行われるべきです。

8. 新たなルール:プロジェクトが完全に形になる前にPPA交渉の準備をする

従来の開発手順は、しばしば次のようになります。 用地 → 投資ライセンス → EPC → PPA → 資金調達

本格的な外国人投資家にとって、これは危険なアプローチになり得ます。 より良いアプローチは次の通りです。 バンカビリティ(融資適格性)から始めて、逆算する。

多額の開発資金を投入する前に、投資家は以下を理解しておくべきです。 「ファイナンシャル・クローズ(資金調達完了)の際、レンダーは何を要求するのか?」 そして、それに応じてプロジェクトを構築します。

コアとなるパッケージには通常、以下のものが含まれます。 PPA + 原料 + 土地 + 系統 + 許可 + EPC + O&M + 保険 + 資金調達 + 投資保護

これらの文書は独立して作成することはできません。 例えば:

  • PPAのCOD(商業運転開始日)は、EPCのスケジュールと一致していなければなりません。
  • ローンの満期は、プロジェクトと土地の期間に適合していなければなりません。
  • 契約解除時の補償は、未返済の債務と連動していなければなりません。
  • 原料の確保は、予測される発電量を支えるものでなければなりません。
  • 系統の可用性は、財務モデルを裏付けるものでなければなりません。
  • 為替リスクは、債務返済にモデル化されていなければなりません。

これらの問題はすべて、最終的にPPAで交差します。

9. バイオマス特有の融資上の課題:原料(フィードストック)

太陽光発電の投資家は燃料供給契約を交渉しません。 バイオマスの投資家は交渉します。 この違いは決定的です。

5年後に燃料が尽きてしまう発電所であれば、20年間のPPAにはほとんど価値がありません。 したがって、外国人投資家は原料に関する厳密なデューデリジェンスを実施しなければなりません。

それは以下を理解することを意味します。

  • 年間取扱量
  • 競合する用途
  • 収集半径
  • 輸送コスト
  • 季節ごとの供給可能性
  • 水分量
  • 発熱量
  • コンタミネーション(不純物の混入)
  • 保管要件
  • 価格の上昇
  • 代替原料
  • 農業の動向
  • 気候リスク
  • 契約の法的強制力

適切な原料供給契約(Feedstock Supply Agreement)には、以下の事項が明記されている必要があります。

  • 最低年間供給量
  • 品質仕様
  • 納入スケジュール
  • 価格設定手法
  • エスカレーション(価格の段階的引き上げ)
  • 代替対応
  • ペナルティ
  • 担保・保証
  • 不可抗力
  • 契約解除
  • (適切な場合)レンダーへの譲渡または介入権

数千の小規模な農業サプライヤーに依存するプロジェクトの場合、ディベロッパーは以下を必要とするかもしれません。

  • 協同組合
  • アグリゲーター(集約業者)
  • 収集センター
  • 複数の供給契約
  • 緩衝用の在庫(バッファ)
  • 代替燃料への対応能力

このように、バイオマスのバンカビリティは2つの柱の上に成り立っています。 収益面での「PPA」と、運営コスト面での「原料供給契約」です。 その両方がレンダーを満足させるものでなければなりません。

10. DPPAがバイオマスをさらに魅力的にする

ベトナムのDPPA(直接電力購入契約)制度は、さらなる機会を創出しています。

政令第57/2025/NĐ-CP号は、再生可能エネルギー発電事業者と大口電力使用者との間での直接的な電力購入のための枠組みを確立しました。 重要なのは、国家系統を利用するDPPAの適格対象として、以下を利用する再生可能エネルギー発電事業者が明確にカバーされていることです。 風力、太陽光、またはバイオマスを使用し、設備容量が10 MW以上で、国家系統に接続し、競争的卸売電力市場に直接参加するもの。(EVN)

政府はその後、2026年6月26日付の政令第243/2026/NĐ-CP号により、DPPAおよび再生可能エネルギーの枠組みを改正しました。つまり、現在のプロジェクトは2025年の旧ルールのみに依存するのではなく、改正された2026年の制度を使用して構築されなければなりません。(EVN)

これは外国人投資家にとって決定的な2026年のアップデートです。 したがって、バイオマスプロジェクトには、潜在的に2つの非常に異なるオフテイク(電力引取)モデルが存在することになります。

11. 選択肢1:従来の系統連系型PPA

従来のモデルは依然として非常に重要です。 利点としては以下が挙げられます。

  • 確立された電力セクターの契約相手
  • 確立された規制構造
  • 慣れ親しんだ決済メカニズム
  • ベトナムの国家電力システムへの統合

しかし、プロジェクトは依然として、商業的に成り立つ価格と、十分にバンカブルなリスク配分を交渉しなければなりません。 それゆえ、第12号通達が中心的な役割を果たすことになります。 投資家はPPAを受け取った後に単にレビューするべきではありません。 完全に構築されたバンカビリティのポジションを持って交渉に臨むべきです。

12. 選択肢2:企業向けDPPA(直接電力購入契約)

もう一つの選択肢は、DPPA制度の下で大口電力消費者に直接、または契約上リンクした形で供給を行うことです。 これは、以下を求める多国籍企業にとって特に魅力的となる可能性があります。

  • 再生可能電力
  • 脱炭素化
  • ESGコンプライアンス
  • スコープ2排出量の削減
  • 長期的なエネルギー価格の可視性
  • サプライチェーン排出量の削減

バイオマスの場合、産業顧客がバイオマス資源の近くに位置している場合、これは特に強力なモデルとなります。 例えば以下のようなケースです。 精米残渣 → バイオマス発電所 → 産業電力顧客 または: 木材残渣 → コージェネレーション → 電力 + 蒸気 → 製造施設 または: サトウキビのバガス → CHP(熱電併給) → 産業ユーザー + 系統電力

これらのモデルは、同じ燃料源から複数の経済的利益を生み出すことができます。 しかし、DPPAが自動的にバンカビリティを意味するわけではありません。 投資家は以下を分析しなければなりません。

  • 企業のオフテイカー(引取者)の信用力
  • 電力市場へのエクスポージャー
  • ベーシスリスク(価格変動リスク)
  • 決済
  • 系統利用料金
  • 顧客のデフォルト(債務不履行)
  • オフテイカーの代替リスク
  • 契約解除時の補償
  • 担保・保証のアレンジ
  • 規制変更

13. 魅力的なプロジェクトは複数の収益源を持つ可能性がある

洗練されたバイオマス投資家は、必ずしも電力販売だけを唯一の収益源と見なすべきではありません。 技術やプロジェクトの構造によっては、収益は以下のものから得られる可能性があります。

  • 電力
  • 蒸気 / 熱エネルギー
  • 廃棄物の処分または処理
  • バイオ炭
  • 灰またはその他の有用な副産物
  • 炭素関連の環境価値(クレジット等)
  • 産業の脱炭素化サービス

収益構造が多様化していればいるほど、プロジェクトが一つの売電価格に依存する度合いは低くなります。 しかし、それぞれの収益源は法的かつ契約的に保証されていなければなりません。

14. 巨額の資本を投じる前に外国人投資家が答えるべき10の質問

多額の開発費が発生する前に、少なくとも以下の10の質問に対する明確な答えを得ることをお勧めします。

  1. そのプロジェクトは、ベトナムの適用される電力開発計画の枠組みに適合しているか?
  2. 投資および融資の全期間にわたり、土地の権利は確保されているか?
  3. 債務の全期間にわたり、現実的な価格で十分な原料が確保可能か?
  4. 系統連系は技術的および商業的に実行可能か?
  5. 適用される電力価格のフレームワークは何か?
  6. 第12号通達に基づき、バンカビリティを向上させるためにどの条項を交渉できるか?
  7. 従来のPPAとDPPAのどちらが商業的に優れているか?
  8. それぞれの承認、価格設定、系統、およびPPAの問題をコントロールしているのはベトナムのどの機関か?
  9. 外国人投資家にはどのような投資協定上の保護が適用されるか?
  10. 契約パッケージ全体で国際的なプロジェクト・ファイナンスを実現できるか?

投資家がこれらの質問に答えられない場合、そのプロジェクトはおそらくまだ投資の準備が整っていません。

15. 紛争が発生する前に国際的な投資保護を検討しなければならない

外国人投資家はまた、取引の初期段階で投資保護の構造化を検討すべきです。 国籍や企業構造によっては、既存の二国間または多国間の投資協定が、特定の政府の行為に対する保護を提供する場合があります。 CPTPP(環太平洋パートナーシップに関する包括的及び先進的な協定)は、適格なCPTPP管轄の投資家にとって特に関連性があります。 欧州の投資家も、引き続きEU・ベトナム投資保護協定の動向を注視すべきです。

重要なのはタイミングです。 協定を活用するための構造化は、紛争が予見される前に行わなければなりません。 紛争がすでに発生した後で、協定の管轄権を得るためだけに再編できると安易に想定することはできません。 したがって、プロジェクトの構築、資金調達、および投資保護は一緒に検討されるべきです。

16. なぜ第12号通達がバイオマスプロジェクト開発において最も価値のあるツールになり得るのか

第12号通達は考え方を変えるものです。 第12号通達以前、外国人投資家はしばしば、法定契約のどの条項が気に入らないかを特定することが主な法務プロセスであるかのように、ベトナムのPPAにアプローチしていました。 それはもはや、最も生産的なアプローチではありません。

より良い問いは次の通りです。 ベトナムの現行の規制フレームワークの下で、私たちが合法的に交渉できる最もバンカブルなPPAとは何か?

この問いは、はるかに洗練された議論への扉を開きます。 それは以下の関係者間の調整を必要とします。

  • 投資家
  • 法務顧問
  • レンダー
  • 財務アドバイザー
  • 技術アドバイザー
  • EPCコントラクター
  • 原料の専門家
  • 電力買電者
  • EVN / EVNEPTC
  • MOIT
  • NSMO
  • 関連する地方当局

第12号通達はその法的な突破口を提供します。 経験豊富なプロジェクト弁護士は、その法的な突破口を、商業的に有用な契約上の保護へと変換しなければなりません。

17. 当社が推奨するPPA交渉戦略

真剣な外国のバイオマスディベロッパーに対し、私たちは5つのステージを通じてPPAにアプローチすることを推奨します。

ステージ1 – バンカビリティ・ギャップ分析 提案されたベトナムのPPAと、想定される国際的なレンダーの要件を比較します。 以下を特定します。

  • 決定的なギャップ
  • 望ましい改善点
  • ベトナム法の制約
  • 商業的な代替案

ステージ2 – ステークホルダー・マッピング 各問題を実際に誰がコントロールしているかを特定します。 「政府」という一般的な枠組みでアプローチしてはなりません。 どの問題が以下に属するかを決定します。

  • MOIT
  • 電力買電者
  • EVN / EVNEPTC
  • NSMO
  • 送配電機関
  • 地方当局
  • またはその他の管轄機関

ステージ3 – 優先順位付け すべての条項が等しい交渉リソースに値するわけではありません。 資金調達を実際に妨げる可能性のある条項を特定します。 それらを優先すべきです。

ステージ4 – 交渉 修正案を以下とともに提示します。

  • 法的根拠
  • 資金調達上の理由
  • 経済的説明
  • 代替案 目的は対立することではありません。 ベトナムの機関が承認でき、かつ国際的なレンダーが融資できる構造を創り出すことです。

ステージ5 – 資金調達との整合性 商業的な原則が合意されたら、PPAが以下と連動していることを確認します。

  • 融資関連文書
  • EPC契約
  • 原料供給契約
  • 系統連系
  • 土地関連文書
  • O&M契約
  • 保険 これは、一見小さなドラフトの問題が、数百万ドル規模の経済的影響を及ぼす可能性があるフェーズです。

18. 責任ある意思決定者を知ることはプロジェクトの資産である

外国人投資家は、組織・機関に関する経験の価値を過小評価することがあります。 ベトナムにおいて、電力セクターが実際にどのように機能しているかを理解することは、膨大な時間の節約につながります。

成功するプロジェクトチームは以下を知るべきです。

  • 誰と話すべきか
  • いつアプローチすべきか
  • 彼らがどのような権限を持っているか
  • 彼らがどのような情報を必要としているか
  • 彼らがどのような懸念を抱く可能性が高いか
  • 次の機関が行動を起こす前に、どのような承認が必要か

責任ある担当官や商業的パートナーと専門的な関係を築き、透明性のある対話を維持し、彼らの役割・権限を理解することは、プロジェクトの実行効率を飛躍的に高めることができます。 これは法律の代わりになるものではありません。 複雑なインフラストラクチャー事業において、法律が効果的に実行されるための手段なのです。

結論ベトナムのバイオマスにおける機会は本物だが、多くの場合PPAがプロジェクトの成否を決める

ベトナムには資源があります。 ベトナムには電力需要があります。 ベトナムには野心的なバイオマスの目標があります。 現在ベトナムには、近代化された電力フレームワーク、DPPA制度、そして極めて重要なこととして、第12/2025/TT-BCT号通達による、明示的に交渉可能なPPAの枠組みがあります。

外国人投資家にとって、これは大きな機会を意味します。 しかし、勝者は単に最大のバイオマス資源を見つけた者ではありません。 最強のプロジェクトを構築した投資家こそが勝者となるのです。

それは以下を意味します。

  • 安定した原料の確保
  • 融資可能な土地の権利
  • 現実的な系統アクセス
  • 適切な資金調達
  • 洗練されたDPPAまたは従来のオフテイク戦略
  • そして何よりも:バンカブル(融資可能)な電力販売契約(PPA)

したがって、第12号通達は単なる一つの実施規則以上のものとして見なされるべきです。 これは、投資家と電力買電者が、ベトナム法の下で追加のPPA条項を交渉するための法的基盤を生み出しています。

その結果、PPAの準備と交渉の質がこれまで以上に重要になっています。 外国人投資家は、以下の点を明確に理解した上で交渉に臨むべきです。

  • レンダーの要件
  • ベトナムの規制上の制限
  • 価格算定手法
  • EVNおよびEVNEPTCの手続き
  • NSMOの要件
  • 系統の制約
  • 地方での承認
  • DPPAの選択肢
  • そして、各問題に責任を持つ機関の意思決定者

開発プロセスの初期段階から、専門的かつ透明性をもって、PPAの背後にいる人物や機関を知ることは、プロジェクトを構想から交渉へ、交渉から資金調達完了へ、そして資金調達完了から商業運転の成功へと進める見込みを劇的に向上させます。

ベトナムのバイオマスにおける機会は、単に農業残渣を電力に変換することだけではありません。 それは、ベトナムの類まれな再生可能資源を、法的に安全で、商業的に成り立ち、国際的に融資可能なインフラプロジェクトへと変換することなのです。

そして2026年現在、第12号通達とバンカブルなPPAの交渉は、まさにその機会の中心にあります。

上記に関する詳細については、著者であるオリバー・マスマン博士(omassmann@duanemorris.com)までご遠慮なくお問い合わせください。オリバー・マスマン博士は、デュアン・モリス・ベトナムLLCの総支配人を務めています。

Anwalt in Vietnam Dr. Oliver Massmann – Biomassekraft 2026 – Das Rennen um bankfähige PPAs

Warum die Rundverfügung Nr. 12 das Spiel für ausländische Investoren verändert – und warum das Wissen über die Institutionen und Personen hinter dem PPA darüber entscheiden kann, ob ein Projekt den finanziellen Abschluss erreicht

Vietnams Biomasse‑Energiesektor tritt in eine grundlegend neue Phase ein

Über viele Jahre betrachteten ausländische Investoren Biomasse in Vietnam vor allem durch die Brille von Einspeisetarifen, Investitionslizenzen und verfügbaren landwirtschaftlichen Reststoffen. Dieser Ansatz reicht heute nicht mehr aus.

Vietnam bewegt sich nun auf einen deutlich ausgereifteren Strommarkt zu, in dem projektspezifische Preisgestaltung, ausgehandelte Stromabnahmeverträge (PPAs), direkte Stromkaufverträge (DPPA), Teilnahme am Wettbewerbsmarkt für Elektrizität, Netzzugang, Versorgungssicherheit bei Brennstoffen und die Bankfähigkeit der Projektfinanzierung zunehmend darüber entscheiden, ob ein Biomasseprojekt erfolgreich ist.

Für ausländische Entwickler, Infrastrukturfonds, Energieversorger, strategische Investoren und Kreditgeber bedeutet dies gleichermaßen Chance und Komplexität. Die entscheidende Frage lautet heute nicht mehr einfach: „Können wir ein Biomassekraftwerk in Vietnam entwickeln?“

Die eigentlichen Fragen sind:

  • Können wir ein bankfähiges PPA verhandeln?
  • Unterstützt der Tarif die Projektfinanzierung?
  • Erhalten Kreditgeber ausreichenden Schutz gegen Abregelung, Gesetzesänderungen, Vertragsbeendigung, Zahlungsverzug und Wechselkursrisiken?
  • Gibt es genügend gesicherte Brennstoffversorgung für die gesamte Schuldendienst‑ und Projektlaufzeit?
  • Kann das Projekt über das vietnamesische DPPA‑Regime einen industriellen Stromabnehmer erreichen?
  • Und vielleicht am wichtigsten: Versteht der Investor genau, welche vietnamesischen Institutionen – und welche verantwortlichen Entscheidungsträger innerhalb dieser Institutionen – die wesentlichen kommerziellen und regulatorischen Fragen tatsächlich kontrollieren?

Für ernsthafte Investoren sollten diese Fragen gleich zu Beginn der Projektentwicklung beantwortet werden – nicht erst, nachdem bereits Millionen von US‑Dollar gebunden wurden.

1. Vietnam plant deutlich mehr Biomassekraft

Der überarbeitete Stromentwicklungsplan VIII, genehmigt durch Entscheidung Nr. 768/QĐ‑TTg vom 15. April 2025, weist der Biomasse eine wichtige Rolle im zukünftigen Strommix zu.

Vietnam strebt an:

  • etwa 1.523–2.699 MW Biomassekraft bis 2030, und
  • 4.829–6.960 MW bis 2050.

Die Regierung fördert ausdrücklich Biomasse‑ und Waste‑to‑Energy‑Projekte, die landwirtschaftliche, forstwirtschaftliche und holzverarbeitende Reststoffe nutzen und gleichzeitig zum Umweltschutz sowie zur Kreislaufwirtschaft beitragen.

Dies ist für Vietnam besonders bedeutsam. Das Land verfügt über reichhaltige Biomasseressourcen aus:

  • Reisproduktion,
  • Zuckerrohr,
  • Kaffee,
  • Maniok,
  • Kokosnuss,
  • Forstwirtschaft,
  • Holzverarbeitung,
  • Viehzucht und landwirtschaftliche Aktivitäten,
  • industrielle organische Abfallströme.

Biomasse besitzt zudem einen wichtigen technischen Vorteil gegenüber intermittierenden erneuerbaren Energien. Im Gegensatz zu Solar und Wind kann ein entsprechend strukturiertes Biomassekraftwerk steuerbare erneuerbare Erzeugung, vergleichsweise hohe Auslastungsfaktoren und – in geeigneten Fällen – Kraft‑Wärme‑Kopplung bieten.

Dies macht Biomasse besonders attraktiv in der Nähe von:

  • Industrieparks,
  • Zuckerfabriken,
  • Reismühlen,
  • Zellstoff‑ und Papierwerken,
  • Holzverarbeitungsclustern,
  • Lebensmittelverarbeitungsbetrieben,
  • industriellen Verbrauchern mit Bedarf an Strom und Dampf.

Die stärksten Projekte werden zunehmend jene sein, bei denen Energieerzeugung, Brennstoffversorgung und industrieller Verbrauch in einem bankfähigen wirtschaftlichen Ökosystem integriert sind.

2. Ausländische Investoren müssen das alte „Was ist der FIT?“‑Denken vergessen

Historisch begannen Investoren, die sich Vietnams Biomassesektor näherten, häufig mit einer Frage: „Wie hoch ist der Biomasse‑Einspeisetarif?“

Diese Frage verliert zunehmend an Bedeutung. Vietnam bewegt sich hin zu einem projektspezifischen Strompreisrahmen, in dem Erzeugungspreise und die Wirtschaftlichkeit von PPAs zunehmend durch zugrunde liegende Investitions‑ und Betriebsannahmen gestützt werden müssen.

Für internationale Investoren bedeutet dies, dass die kommerzielle Strategie sich wegbewegen muss vom bloßen Anwenden eines veröffentlichten FIT und hin zu:

  • Aufbau eines Tarifmodells,
  • Vorbereitung belastbarer finanzieller Annahmen,
  • Verhandlung des PPA,
  • Sicherstellung, dass die resultierende Erlösstruktur finanzierbar ist.

Das ist eine wesentliche Veränderung. Es bedeutet auch, dass Stromrechtsanwälte, Finanzberater und technische Berater viel früher im Entwicklungszyklus zusammenarbeiten müssen.

3. Rundverfügung 12/2025/TT‑BCT: Die wichtigste PPA‑Entwicklung für ausländische Investoren

Dies könnte die bedeutendste rechtliche Entwicklung für ausländische Investoren in vietnamesischen Energieprojekten sein.

Die Rundverfügung Nr. 12/2025/TT‑BCT des Ministeriums für Industrie und Handel sieht ausdrücklich vor, dass die vorgeschriebenen Hauptinhalte des PPA die Grundlage für die Verhandlung und Unterzeichnung zwischen Stromverkäufer und Stromkäufer bilden.

Noch wichtiger: Artikel 19 stellt ausdrücklich klar, dass Verkäufer und Käufer das Recht haben, zusätzliche Vertragsbestimmungen auszuhandeln und zu vereinbaren, sofern diese mit vietnamesischem Recht vereinbar sind.

Dies verdient besondere Betonung. Das PPA ist nicht länger lediglich als Formularvertrag zu betrachten, der akzeptiert werden muss. Rundverfügung 12 schafft eine ausdrückliche regulatorische Grundlage für Verhandlungen. Das ist eine bedeutende Chance für Bankfähigkeit.

Der Rahmen wurde anschließend geändert, u. a. durch Rundverfügung Nr. 54/2025/TT‑BCT, und das derzeit konsolidierte Regime sollte daher für jedes einzelne Projekt sorgfältig geprüft werden. Die konsolidierten Bestimmungen sehen weiterhin ausgehandelte Änderungen und Ergänzungen von PPAs vor.

Für einen internationalen Kreditgeber reicht es jedoch nicht aus, lediglich zu wissen, dass ein PPA „verhandelbar“ ist. Die entscheidende Frage lautet: Was sollte tatsächlich verhandelt werden?

4. Was macht ein Biomasse‑PPA bankfähig?

Ein bankfähiges PPA ist nicht einfach ein Vertrag mit einem Tarif. Internationale Projektfinanzierer prüfen die Zuweisung praktisch jedes wesentlichen Projektrisikos.

Für Biomasseprojekte in Vietnam sollten Investoren sorgfältig bewerten, ob das PPA die folgenden Punkte angemessen behandelt:

  • Zahlungssicherheit
    • Wer trägt das Zahlungsrisiko?
    • Was passiert bei verspäteter Zahlung?
    • Sind Verzugszinsen und Durchsetzungsmechanismen angemessen?
    • Können Projekterlöse sicher sowohl inländische als auch ausländische Schulden bedienen?
  • Abregelung und fingierte Erzeugung
    • Was passiert, wenn die Anlage technisch verfügbar ist, aber Strom aufgrund von Netzüberlastung, Systemanweisungen oder Abregelung nicht eingespeist werden kann?
    • Ein Kreditgeber wird wissen wollen, ob die Projektgesellschaft dieses Risiko vollständig trägt.
  • Gesetzesänderungen
    • Eine Biomasseanlage kann 20–30 Jahre betrieben werden.
    • Stromregulierung, Umweltstandards, Steuern, Netzregeln und technische Anforderungen können sich in dieser Zeit ändern.
    • Das PPA muss daher geeignete Mechanismen für Gesetzesänderungen enthalten.
  • Entschädigung bei Vertragsbeendigung
    • Eines der wichtigsten Bankfähigkeitskriterien.
    • Wenn das PPA beendet wird, bevor die ausstehenden Projektschulden zurückgezahlt sind, welche Entschädigung steht zur Verfügung?
    • Internationale Kreditgeber könnten sich weigern, ein Projekt zu finanzieren, wenn Beendigungszahlungen die ausstehenden Schulden und das investierte Kapital nicht ausreichend schützen.
  • Rechte der Kreditgeber zum Eingreifen
    • Projektfinanzierer erwarten normalerweise die Möglichkeit, Vertragsverletzungen zu heilen oder in das Projekt einzutreten, bevor die Hauptverträge beendet werden können.
    • Dies sollte nicht nur im PPA berücksichtigt werden, sondern auch in:
      • Grundstücksvereinbarungen,
      • Brennstofflieferverträgen,
      • EPC‑Verträgen,
      • O&M‑Verträgen,
      • wesentlichen Projektgenehmigungen, soweit rechtlich möglich.
  • Wechselkursrisiko
    • Einnahmen können in Vietnamesischem Dong erfolgen, während erhebliche Schulden, Ausrüstungen und EPC‑Kosten in USD, EUR, JPY, KRW oder einer anderen Fremdwährung denominiert sind.
    • Investoren müssen diese Diskrepanz von Anfang an modellieren.
  • Höhere Gewalt
    • Definitionen sind entscheidend.
    • Ebenso:
      • Meldepflichten,
      • Entlastungszeiträume,
      • Minderungspflichten,
      • langanhaltende höhere Gewalt,
      • Kündigungsrechte,
      • Entschädigungsfolgen.
  • Einspeisung und Netzrisiko
    • Das PPA muss zusammen mit folgenden Dokumenten analysiert werden:
      • Netzanschlussvereinbarung,
      • Systembetriebsregeln,
      • Einspeiseverpflichtungen,
      • Messregelungen,
      • Strommarktvorschriften,
      • Anforderungen der NSMO.
  • Inbetriebnahme und COD
    • Der kommerzielle Betriebsmechanismus muss abgestimmt sein mit:
      • EPC‑Zeitplan,
      • Finanzierungsmeilensteinen,
      • Netzverfügbarkeit,
      • Testverfahren,
      • Leistungsgarantien,
      • Long‑Stop‑Terminen.
  • Streitbeilegung
    • Investoren sollten genau verstehen, welche Streitbeilegungsoptionen das vietnamesische Recht im jeweiligen Transaktionsrahmen zulässt und ob diese Mechanismen Kreditgeber und Investitionsausschüsse zufriedenstellen.

5. Rundverfügung 12 schafft eine Chance – aber nicht jede Klausel wird automatisch akzeptiert

Ausländische Investoren sollten realistisch bleiben. Rundverfügung 12 bedeutet nicht, dass jede von einem internationalen Kreditgeber gewünschte Klausel automatisch vom vietnamesischen Käufer akzeptiert wird. Ebenso bedeutet sie nicht, dass regulatorische Beschränkungen verschwinden.

Was Rundverfügung 12 jedoch bietet, ist etwas äußerst Wertvolles: eine ausdrückliche rechtliche Grundlage für die Parteien, das PPA zu verhandeln und zu ergänzen.

Das verändert die Strategie. Anstatt lediglich Defizite im Standardwortlaut zu identifizieren, sollten ausländische Investoren ein strukturiertes Bankability‑Verhandlungspaket vorbereiten.

Für jede vorgeschlagene Änderung sollte der Investor erklären können:

  1. warum die Klausel erforderlich ist;
  2. welches Projektrisiko sie adressiert;
  3. warum Kreditgeber sie verlangen;
  4. ob vietnamesisches Recht sie zulässt;
  5. ob vergleichbare Risikoallokationen anderswo bestehen;
  6. welche alternative Formulierung dasselbe Ziel erreichen könnte;
  7. welche wirtschaftlichen Folgen entstehen, wenn das Risiko bei der Projektgesellschaft verbleibt.

Die besten PPA‑Verhandlungen werden daher nicht als Liste von Änderungen im Stil ausländischer Rechtsordnungen geführt, sondern als Bankability‑Dialog.

6. Der meist unterschätzte Faktor: Wissen, wer die PPA‑Fragen tatsächlich kontrolliert

Ausländische Investoren sprechen manchmal allgemein davon, „mit der vietnamesischen Regierung zu verhandeln“. Das ist zu ungenau, um ein erfolgreiches Energieprojekt zu entwickeln.

Es gibt keine einzelne Institution, die alles entscheidet. Unterschiedliche Fragen fallen in die Zuständigkeit verschiedener Stellen. Je nach Projektstruktur können die relevanten institutionellen Stakeholder umfassen:

  • Ministerium für Industrie und Handel (MOIT) Zentral für Politik und Regulierung im Stromsektor. Seine Behörden spielen wichtige Rollen bei:
    • Strompreis‑Methodologien,
    • Rahmen für Erzeugungspreise,
    • Marktregulierung,
    • Umsetzung des Elektrizitätsgesetzes,
    • PPA‑Regulierung,
    • regulatorische Leitlinien.
  • Vietnam Electricity – EVN Eine der wichtigsten Institutionen im vietnamesischen Stromsektor und ein wesentlicher kommerzieller Vertragspartner oder Stakeholder bei vielen netzgebundenen Projekten.
  • EVN Electric Power Trading Company – EVNEPTC Für konventionelle Energieprojekte besonders wichtig, da sie innerhalb des EVN‑Systems wesentliche PPA‑Verhandlungen und Stromhandelsfunktionen übernimmt. Investoren sollten nicht nur EVN auf Unternehmensebene verstehen, sondern auch, welche Einheit tatsächlich für die Verhandlung des betreffenden kommerziellen Themas zuständig ist.
  • National Power System and Market Operation Company – NSMO Spielt eine zentrale Rolle bei:
    • Systembetrieb,
    • Dispatch,
    • Marktbetrieb,
    • Marktabrechnung,
    • Umsetzung nationaler Netz‑DPPA‑Regelungen. Für Projekte im Wettbewerbsmarkt kann die Rolle der NSMO grundlegend werden.
  • Provinzbehörden Die zuständige Provinzvolkskomitees und Abteilungen sind wichtig für:
    • Projektdurchführung,
    • Grundstücksfragen,
    • lokale Planung,
    • Bau,
    • Umweltkoordination,
    • Investitionsverfahren,
    • lokale Infrastruktur.
  • Netzgesellschaften und Stromkonzerne Die zuständigen Übertragungs‑ oder Verteilungsunternehmen können Fragen kontrollieren, die direkt betreffen:
    • Anschluss,
    • technische Planung,
    • Messung,
    • Netzverknüpfungsarbeiten,
    • Inbetriebnahme.

7. Die Personen hinter dem PPA zu kennen, kann die Projektdurchführung erheblich verbessern

Dieser Punkt sollte richtig verstanden werden. Es geht nicht um bevorzugte Behandlung. Es geht darum zu wissen:

  • wer die rechtliche Verantwortung für ein bestimmtes Thema trägt;
  • wer über technische Expertise verfügt;
  • wer zur Verhandlung befugt ist;
  • wer Abweichungen genehmigen muss;
  • wer regulatorische Leitlinien geben muss;
  • welche Institution konsultiert werden muss, bevor eine andere handeln kann;
  • welche Unterlagen Entscheidungsträger benötigen, bevor sie einen Vorschlag verantwortungsvoll genehmigen können.

Vietnamesische Energieprojekte sind stark institutionell geprägt. Ein Investor kann Monate verlieren, wenn er ein Thema bei einer Organisation verfolgt, die schlicht keine Befugnis zur Lösung hat. Umgekehrt kann ein Investor, der die Entscheidungsstruktur korrekt abbildet, die Effizienz erheblich steigern.

Für jedes wesentliche PPA‑Thema empfehlen wir die Erstellung einer Matrix der institutionellen Zuständigkeiten.

Beispiel:

ThemaHauptinstitutionelle Schnittstelle
PPA‑kommerzielle VerhandlungRelevanter Stromkäufer / EVNEPTC
Methodologie der ErzeugungspreiseMOIT / zuständige Strombehörde
NetzanschlussZuständiges Übertragungs‑/Verteilungsunternehmen
DispatchNSMO
GroßhandelsstrommarktNSMO / zuständige Marktinstitutionen
DPPA‑RegistrierungNSMO und relevante Parteien
Grundstück/ProjektdurchführungProvinzbehörden
UmweltgenehmigungZuständige Umweltbehörde

Die genaue Zuständigkeitsverteilung muss für jedes Projekt bestätigt werden. Diese institutionelle Abbildung sollte vor Beginn formeller PPA‑Verhandlungen erfolgen.

8. Die neue Regel: Vorbereitung auf die PPA‑Verhandlung, bevor das Projekt vollständig entwickelt ist

Die traditionelle Entwicklungsabfolge sieht oft so aus: Standort → Investitionslizenz → EPC → PPA → Finanzierung

Für einen ernsthaften ausländischen Investor kann das gefährlich sein. Ein besserer Ansatz lautet: Mit der Bankfähigkeit beginnen und rückwärts arbeiten.

Bevor erhebliche Entwicklungskapitalmittel gebunden werden, sollte der Investor verstehen: Was werden die Kreditgeber beim Financial Close verlangen? Dann sollte das Projekt entsprechend strukturiert werden.

Das Kernpaket umfasst normalerweise: PPA + Brennstoffversorgung + Grundstück + Netz + Genehmigungen + EPC + O&M + Versicherung + Finanzierung + Investitionsschutz.

Diese Dokumente können nicht unabhängig voneinander entwickelt werden. Beispiele:

  • Ein PPA‑COD‑Datum muss mit dem EPC‑Zeitplan übereinstimmen.
  • Die Kreditlaufzeit muss zur Projekt‑ und Grundstückslaufzeit passen.
  • Entschädigungen bei Vertragsbeendigung müssen mit ausstehenden Schulden interagieren.
  • Brennstoffsicherheit muss die geplante Erzeugung stützen.
  • Netzverfügbarkeit muss das Finanzmodell tragen.
  • Wechselkursrisiken müssen in den Schuldendienst eingepreist werden.

All diese Fragen laufen letztlich im PPA zusammen.

9. Biomasse hat eine einzigartige Bankfähigkeits‑Herausforderung: Brennstoffversorgung

Solarinvestoren verhandeln keine Brennstofflieferverträge. Biomasseinvestoren tun es. Dieser Unterschied ist grundlegend.

Ein 20‑jähriges PPA hat wenig Wert, wenn die Anlage nach fünf Jahren keinen Brennstoff mehr hat. Ausländische Investoren müssen daher eine strenge Due‑Diligence zur Brennstoffversorgung durchführen.

Das bedeutet, zu verstehen:

  • jährliche Volumina,
  • konkurrierende Nutzungen,
  • Sammelradius,
  • Transportkosten,
  • saisonale Verfügbarkeit,
  • Feuchtigkeitsgehalt,
  • Heizwert,
  • Verunreinigungen,
  • Lageranforderungen,
  • Preiseskalation,
  • alternative Brennstoffe,
  • landwirtschaftliche Trends,
  • Klimarisiken,
  • vertragliche Durchsetzbarkeit.

Ein ordnungsgemäßer Brennstoffliefervertrag (Feedstock Supply Agreement) sollte regeln:

  • Mindestjahresmenge,
  • Qualitätsspezifikationen,
  • Lieferplan,
  • Preisgestaltungsmethodik,
  • Eskalation,
  • Substitution,
  • Vertragsstrafen,
  • Sicherheiten,
  • höhere Gewalt,
  • Kündigung,
  • Abtretungs‑ oder Step‑in‑Rechte für Kreditgeber.

Für Projekte, die auf Tausende kleiner landwirtschaftlicher Lieferanten angewiesen sind, können Entwickler benötigen:

  • Genossenschaften,
  • Aggregatoren,
  • Sammelstellen,
  • mehrere Lieferverträge,
  • Pufferlager,
  • alternative Brennstofffähigkeit.

Die Bankfähigkeit von Biomasse ruht daher auf zwei Säulen: dem PPA auf der Erlösseite und dem Brennstoffliefervertrag auf der Kostenseite. Beide müssen Kreditgeber zufriedenstellen.

10. DPPA macht Biomasse noch interessanter

Das vietnamesische DPPA‑Regime schafft eine zusätzliche Chance. Das Dekret Nr. 57/2025/NĐ‑CP etablierte einen Rahmen für direkte Stromkäufe zwischen erneuerbaren Erzeugern und großen Stromverbrauchern.

Wichtig: Die nationale Netz‑DPPA‑Berechtigung umfasst ausdrücklich qualifizierte erneuerbare Erzeuger mit: Wind, Solar oder Biomasse, mit einer Kapazität von 10 MW oder mehr, angeschlossen an das nationale Netz und direkter Teilnahme am Wettbewerbsmarkt für Strom.

Die Regierung änderte das DPPA‑ und Erneuerbare‑Energien‑Regime anschließend durch Dekret Nr. 243/2026/NĐ‑CP vom 26. Juni 2026. Das bedeutet, dass jedes aktuelle Projekt nach dem geänderten Regime von 2026 strukturiert werden muss und nicht allein auf die ursprünglichen Regeln von 2025 vertrauen darf.

Dies ist ein entscheidendes Update für ausländische Investoren im Jahr 2026. Biomasseprojekte haben daher potenziell zwei sehr unterschiedliche Abnahmemodelle.

11. Option Eins: Konventionelles Netz‑PPA

Das konventionelle Modell bleibt hochrelevant. Vorteile können sein:

  • etablierte Vertragspartner im Stromsektor,
  • etablierte regulatorische Strukturen,
  • vertraute Abrechnungsmechanismen,
  • Integration in das nationale Stromsystem Vietnams.

Aber: Das Projekt muss dennoch einen kommerziell tragfähigen Preis und eine ausreichend bankfähige Risikoallokation verhandeln. Rundverfügung 12 wird daher zentral.

Der Investor sollte das PPA nicht erst nach Erhalt prüfen. Er sollte mit einer vollständig entwickelten Bankability‑Position in die Verhandlungen eintreten.

12. Option Zwei: Unternehmens‑DPPA

Die Alternative ist die direkte oder vertraglich gebundene Versorgung großer Stromverbraucher im Rahmen des DPPA‑Regimes. Dies kann besonders attraktiv sein für multinationale Unternehmen, die suchen nach:

  • erneuerbarer Elektrizität,
  • Dekarbonisierung,
  • ESG‑Konformität,
  • Scope‑2‑Reduktionen,
  • langfristiger Energiepreis‑Transparenz,
  • Emissionsminderung in der Lieferkette.

Für Biomasse kann dies besonders wirkungsvoll sein, wenn der industrielle Kunde in der Nähe der Biomassequelle angesiedelt ist.

Beispiele:

  • Reisverarbeitungsreste → Biomassekraftwerk → industrieller Stromverbraucher
  • Holzreste → Kraft‑Wärme‑Kopplung → Strom + Dampf → Produktionsanlage
  • Zuckerrohr‑Bagasse → KWK → industrieller Nutzer + Netzstrom

Diese Modelle können mehrere wirtschaftliche Vorteile aus demselben Brennstoffstrom schaffen.

Allerdings bedeutet DPPA nicht automatisch Bankfähigkeit. Investoren müssen analysieren:

  • Bonität des industriellen Abnehmers,
  • Strommarktrisiko,
  • Basisrisiko,
  • Abrechnung,
  • Netzentgelte,
  • Kundenausfall,
  • Risiko des Ersatzabnehmers,
  • Entschädigung bei Vertragsbeendigung,
  • Sicherheiten,
  • regulatorische Änderungen.

13. Die attraktivsten Projekte können mehrere Einnahmequellen haben

Fortgeschrittene Biomasseinvestoren sollten Stromverkäufe nicht zwingend als einzige Einnahmequelle betrachten. Je nach Technologie und Projektstruktur können Einnahmen potenziell stammen aus:

  • Strom,
  • Dampf / thermische Energie,
  • Abfallentsorgung oder ‑behandlung,
  • Biokohle,
  • Asche oder andere nützliche Nebenprodukte,
  • CO₂‑bezogene Umweltattribute,
  • industrielle Dekarbonisierungsdienste.

Je diversifizierter die Erlösstruktur, desto weniger abhängig ist das Projekt von einem einzigen Tarif. Aber jede Einnahmequelle muss rechtlich und vertraglich abgesichert sein.

14. Zehn Fragen, die ausländische Investoren beantworten sollten, bevor sie ernsthaft Kapital binden

Bevor erhebliche Entwicklungsausgaben getätigt werden, empfehlen wir klare Antworten auf mindestens die folgenden zehn Fragen:

  1. Ist das Projekt mit Vietnams geltendem Stromentwicklungsplan kompatibel?
  2. Sind die Grundstücksrechte für die gesamte Investitions‑ und Finanzierungsperiode gesichert?
  3. Steht ausreichend Brennstoff zu realistischen Preisen für die gesamte Schuldendienstlaufzeit zur Verfügung?
  4. Ist der Netzanschluss technisch und kommerziell machbar?
  5. Welcher Strompreisrahmen gilt?
  6. Welche Bestimmungen können nach Rundverfügung 12 verhandelt werden, um die Bankfähigkeit zu verbessern?
  7. Ist ein konventionelles PPA oder ein DPPA kommerziell überlegen?
  8. Welche vietnamesische Institution kontrolliert jede Genehmigung, jeden Tarif, Netz‑ und PPA‑Aspekt?
  9. Welchen Investitionsschutz durch internationale Verträge hat der ausländische Investor?
  10. Kann das gesamte Vertragswerk internationale Projektfinanzierung erreichen?

Wenn der Investor diese Fragen nicht beantworten kann, ist das Projekt wahrscheinlich noch nicht investitionsreif.

15. Internationaler Investitionsschutz muss vor einem Streitfall berücksichtigt werden

Ausländische Investoren sollten Investitionsschutzstrukturen bereits zu Beginn der Transaktion bedenken. Je nach Nationalität und Unternehmensstruktur können bestehende bilaterale oder multilaterale Investitionsabkommen Schutz gegen bestimmte Formen staatlichen Handelns bieten.

Das CPTPP kann besonders relevant sein für qualifizierte Investoren aus CPTPP‑Jurisdiktionen. Europäische Investoren sollten zudem das EU‑Vietnam‑Investitionsschutzabkommen weiterhin beobachten.

Der entscheidende Punkt ist das Timing. Vertragsstrukturen sollten vor einem absehbaren Streitfall vorgenommen werden. Ein Investor kann nicht sicher annehmen, dass er nach Entstehung eines Konflikts seine Struktur ändern kann, nur um Vertragsgerichtsbarkeit zu erlangen.

Projektstruktur, Finanzierung und Investitionsschutz sollten daher gemeinsam betrachtet werden.

16. Warum Rundverfügung 12 zum wertvollsten Instrument in der Biomasseprojektentwicklung werden könnte

Rundverfügung 12 verändert die Denkweise. Vor Rundverfügung 12 näherten sich ausländische Investoren dem vietnamesischen PPA oft so, als sei die Hauptaufgabe, die ungeliebten Bestimmungen eines gesetzlichen Vertrags zu identifizieren. Das ist nicht mehr der produktivste Ansatz.

Die bessere Frage lautet: Welches ist das bankfähigste PPA, das wir rechtmäßig unter Vietnams aktuellem Regulierungsrahmen verhandeln können?

Diese Frage eröffnet eine wesentlich anspruchsvollere Diskussion. Sie erfordert Koordination zwischen:

  • Investor,
  • Rechtsberater,
  • Kreditgeber,
  • Finanzberater,
  • technischer Berater,
  • EPC‑Unternehmer,
  • Brennstoffspezialisten,
  • Stromabnehmer,
  • EVN/EVNEPTC,
  • MOIT,
  • NSMO,
  • relevante lokale Behörden.

Rundverfügung 12 bietet die rechtliche Öffnung. Erfahrene Projektjuristen müssen diese rechtliche Öffnung dann in kommerziell nützlichen vertraglichen Schutz umwandeln.

17. Unsere empfohlene PPA‑Verhandlungsstrategie

Für ernsthafte ausländische Biomasseentwickler empfehlen wir, das PPA in fünf Phasen anzugehen:

Phase 1 – Bankability‑Gap‑Analyse Vergleichen Sie das vorgeschlagene vietnamesische PPA mit den Anforderungen wahrscheinlicher internationaler Kreditgeber. Identifizieren Sie:

  • kritische Lücken,
  • wünschenswerte Verbesserungen,
  • Beschränkungen nach vietnamesischem Recht,
  • kommerzielle Alternativen.

Phase 2 – Stakeholder‑Mapping Identifizieren Sie, wer tatsächlich jede Frage kontrolliert. Gehen Sie nicht allgemein „auf die Regierung“ zu. Bestimmen Sie, welche Frage gehört zu:

  • MOIT,
  • Stromkäufer,
  • EVN/EVNEPTC,
  • NSMO,
  • Netzgesellschaften,
  • Provinzbehörden,
  • einer anderen zuständigen Institution.

Phase 3 – Priorisierung Nicht jede Klausel verdient gleiches Verhandlungskapital. Identifizieren Sie die Bestimmungen, die die Finanzierung tatsächlich verhindern könnten. Diese sollten Priorität erhalten.

Phase 4 – Verhandlung Präsentieren Sie vorgeschlagene Änderungen zusammen mit:

  • rechtlicher Grundlage,
  • Finanzierungsrationale,
  • wirtschaftlicher Erklärung,
  • Alternativen. Das Ziel sollte nicht Konfrontation sein, sondern eine Struktur, die vietnamesische Institutionen genehmigen und internationale Kreditgeber finanzieren können.

Phase 5 – Finanzierungsabgleich Sobald kommerzielle Prinzipien vereinbart sind, stellen Sie sicher, dass das PPA zusammenpasst mit:

  • Finanzierungsdokumenten,
  • EPC‑Vertrag,
  • Brennstofflieferverträgen,
  • Netzanschluss,
  • Grundstücksdokumenten,
  • O&M‑Vertrag,
  • Versicherung. Hier kann eine scheinbar kleine Formulierungsfrage eine wirtschaftliche Auswirkung in Millionenhöhe haben.

18. Die verantwortlichen Entscheidungsträger zu kennen, ist ein Projektvermögen

Ausländische Investoren unterschätzen manchmal den Wert institutioneller Erfahrung. In Vietnam kann das Verständnis, wie der Stromsektor tatsächlich funktioniert, enorme Zeitersparnis bringen.

Ein erfolgreiches Projektteam sollte wissen:

  • mit wem man sprechen muss,
  • wann man sie ansprechen sollte,
  • welche Befugnisse sie besitzen,
  • welche Informationen sie benötigen,
  • welche Bedenken sie wahrscheinlich haben,
  • welche Genehmigungen erfolgen müssen, bevor die nächste Institution handeln kann.

Der Aufbau professioneller Beziehungen zu den zuständigen Beamten und kommerziellen Vertragspartnern, die Pflege eines transparenten Dialogs und das Verständnis ihres Mandats können die Effizienz der Projektdurchführung erheblich steigern. Dies ersetzt nicht das Gesetz. Es ist die Art und Weise, wie das Gesetz in einem komplexen Infrastrukturprojekt effektiv umgesetzt wird.

Schlussfolgerung – Vietnams Biomassechance ist real, aber das PPA entscheidet oft über das Projekt

Vietnam verfügt über die Ressourcen. Vietnam hat den Strombedarf. Vietnam hat ehrgeizige Biomasseziele. Vietnam hat nun einen modernisierten Stromrahmen, ein DPPA‑Regime und – entscheidend – ein ausdrücklich verhandelbares PPA‑Regime nach Rundverfügung 12/2025/TT‑BCT.

Für ausländische Investoren stellt dies eine große Chance dar. Aber die Gewinner werden nicht einfach diejenigen sein, die die größten Biomasseressourcen finden. Es werden die Investoren sein, die die stärksten Projekte strukturieren.

Das bedeutet:

  • gesicherte Brennstoffversorgung,
  • bankfähige Grundstücksrechte,
  • realistischen Netzzugang,
  • angemessene Finanzierung,
  • eine ausgefeilte DPPA‑ oder konventionelle Abnahmestrategie,
  • und vor allem: ein bankfähiges Power Purchase Agreement.

Rundverfügung 12 sollte daher als weit mehr betrachtet werden als eine weitere Umsetzungsverordnung. Sie schafft die rechtliche Grundlage für Investoren und Stromkäufer, zusätzliche PPA‑Bestimmungen im Rahmen des vietnamesischen Rechts zu verhandeln. Das macht die Qualität der PPA‑Vorbereitung und ‑Verhandlung wichtiger denn je.

Ausländische Investoren sollten in diese Verhandlungen mit einem klaren Verständnis eintreten von:

  • Kreditgeberanforderungen,
  • vietnamesischen regulatorischen Beschränkungen,
  • Tarifmethodologie,
  • Verfahren von EVN und EVNEPTC,
  • Anforderungen der NSMO,
  • Netzbeschränkungen,
  • provinziellen Genehmigungen,
  • DPPA‑Alternativen,
  • den institutionellen Entscheidungsträgern, die für jede Frage verantwortlich sind.

Die Menschen und Institutionen hinter dem PPA – professionell, transparent und früh im Entwicklungsprozess kennenzulernen – kann die Chancen erheblich verbessern, ein Projekt von der Konzeptphase zur Verhandlung, von der Verhandlung zum Financial Close und vom Financial Close zum erfolgreichen kommerziellen Betrieb zu bringen.

Vietnams Biomassechance bedeutet nicht nur, landwirtschaftliche Reststoffe in Strom umzuwandeln. Es bedeutet, Vietnams außergewöhnliche erneuerbare Ressourcen in rechtlich gesicherte, kommerziell tragfähige und international finanzierbare Infrastrukturprojekte zu verwandeln. Und im Jahr 2026 stehen Rundverfügung 12 und die Verhandlung eines bankfähigen PPA im Zentrum dieser Chance.

Für weitere Informationen wenden Sie sich bitte an den Autor Dr. Oliver Massmann unter omassmann@duanemorris.com. Dr. Oliver Massmann ist Generaldirektor von Duane Morris Vietnam LLC.

VIETNAM BIOMASS POWER 2026 – THE RACE FOR BANKABLE PPAs _Why Circular 12 Changes the Game for Foreign Investors – and Why Knowing the Institutions and People Behind the PPA Can Determine Whether a Project Reaches Financial Close

Vietnam’s biomass power sector is entering a fundamentally new phase.

For many years, foreign investors looked at biomass in Vietnam primarily through the lens of feed-in tariffs, investment licences and available agricultural residues.

That approach is no longer sufficient.

Vietnam is now moving towards a much more sophisticated electricity market in which project-specific pricing, negotiated Power Purchase Agreements, Direct Power Purchase Agreements, competitive electricity-market participation, grid access, feedstock security and project finance bankability increasingly determine whether a biomass project succeeds.

For foreign developers, infrastructure funds, utilities, strategic investors and lenders, this creates both opportunity and complexity.

The crucial question today is no longer simply:

“Can we develop a biomass power plant in Vietnam?”

The real questions are:

Can we negotiate a bankable PPA?

Can the tariff support project financing?

Can lenders obtain adequate protection against curtailment, change in law, termination, payment and foreign-exchange risks?

Is there enough secure feedstock for the full debt and project life?

Can the project access a corporate offtaker through Vietnam’s DPPA regime?

And, perhaps most importantly:

Does the investor understand exactly which Vietnamese institutions – and which responsible decision-makers within those institutions – actually control the key commercial and regulatory issues?

For serious investors, these questions should be addressed at the very beginning of project development, not after millions of dollars have already been committed.

1. VIETNAM IS PLANNING FOR MUCH MORE BIOMASS POWER

Vietnam’s Revised Power Development Plan VIII, approved under Decision No. 768/QĐ-TTg dated 15 April 2025, gives biomass an important role in the future electricity mix.

Vietnam targets approximately:

1,523–2,699 MW of biomass power by 2030, and

4,829–6,960 MW by 2050.

The Government specifically encourages biomass and waste-to-energy projects that utilise agricultural, forestry and wood-processing residues and simultaneously contribute to environmental protection and the circular economy. (Chính Phủ)

That is particularly important for Vietnam.

The country possesses abundant biomass resources generated from:

● rice production;

● sugar cane;

● coffee;

● cassava;

● coconut;

● forestry;

● wood processing;

● livestock and agricultural activities; and

● industrial organic waste streams.

Biomass also has an important technical advantage over intermittent renewable energy.

Unlike solar and wind, a properly structured biomass plant can provide dispatchable renewable generation, comparatively high capacity factors and, in appropriate cases, combined heat and power.

This makes biomass particularly attractive around:

● industrial parks;

● sugar mills;

● rice-processing facilities;

● pulp and paper plants;

● wood-processing clusters;

● food-processing operations; and

● industrial consumers requiring both electricity and steam.

The strongest projects will increasingly be those where energy production, feedstock supply and industrial consumption are integrated into one bankable economic ecosystem.

2. FOREIGN INVESTORS MUST FORGET THE OLD “WHAT IS THE FIT?” MINDSET

Historically, investors approaching Vietnam’s biomass sector frequently began with one question:

“What is the biomass feed-in tariff?”

That question is becoming less relevant.

Vietnam has moved towards a more project-specific electricity-pricing framework in which generation prices and PPA economics must increasingly be supported by underlying investment and operating assumptions.

For international investors, this means that the commercial strategy must move away from simply applying a published FIT and towards:

building a tariff case, preparing defensible financial assumptions, negotiating the PPA and ensuring the resulting revenue structure is financeable.

That is a major change.

It also means that electricity lawyers, financial advisers and technical consultants must work together much earlier in the development cycle.

3. CIRCULAR 12/2025/TT-BCT: THE MOST IMPORTANT PPA DEVELOPMENT FOR FOREIGN INVESTORS

This may be the single most important legal development for foreign investors in Vietnamese power projects.

Circular No. 12/2025/TT-BCT of the Ministry of Industry and Trade expressly provides that the prescribed main contents of the PPA constitute the basis for negotiation and signing between the electricity seller and electricity buyer.

More importantly, Article 19 expressly states that the seller and buyer have the right to negotiate and agree additional contractual provisions, provided those provisions comply with Vietnamese law. (LuatVietnam)

This deserves emphasis.

The PPA is no longer properly viewed merely as a form contract to be accepted.

Circular 12 creates an express regulatory foundation for negotiation.

That is a major bankability opportunity.

The framework has subsequently been amended, including through Circular No. 54/2025/TT-BCT, and the current consolidated regime should therefore be reviewed carefully for each individual project. The consolidated provisions continue to contemplate negotiated amendments and supplementation of PPAs. (moit.gov.vn)

For an international lender, however, merely knowing that a PPA is “negotiable” is not enough.

The key question is:

What should actually be negotiated?

4. WHAT MAKES A BIOMASS PPA BANKABLE?

A bankable PPA is not simply a contract containing a tariff.

International project-finance lenders examine the allocation of virtually every major project risk.

For biomass projects in Vietnam, investors should carefully assess whether the PPA adequately deals with the following.

Payment security

Who bears payment risk?

What happens in the event of delayed payment?

Are default interest and enforcement mechanisms adequate?

Can project revenues safely service foreign and domestic debt?

Curtailment and deemed generation

What happens if the plant is technically available and ready to generate, but power cannot be dispatched because of grid congestion, system instructions or curtailment?

A project-finance lender will want to know whether the project company carries that risk entirely.

Change in law

A biomass plant may operate for 20–30 years.

Electricity regulation, environmental standards, taxation, grid rules and technical requirements may all change during that period.

The PPA must therefore be examined for appropriate change-in-law mechanisms.

Termination compensation

This is one of the most important bankability provisions.

If the PPA is terminated before outstanding project debt has been repaid, what compensation is available?

International lenders may be unwilling to finance a project where termination payments do not adequately protect outstanding debt and invested capital.

Lender step-in rights

Project-finance lenders normally expect an opportunity to cure defaults or step into the project before the project’s principal contracts can be terminated.

This should be considered not only in the PPA but also in:

● land arrangements;

● feedstock agreements;

● EPC contracts;

● O&M agreements; and

● major project permits where legally possible.

Foreign-exchange risk

A project may receive revenue in Vietnamese Dong while substantial debt, equipment and EPC costs are denominated in USD, EUR, JPY, KRW or another foreign currency.

Investors must model that mismatch from Day One.

Force majeure

Definitions matter.

So do:

● notification requirements;

● relief periods;

● mitigation obligations;

● prolonged force majeure;

● termination rights; and

● compensation consequences.

Dispatch and grid risk

The PPA must be analysed together with:

● the grid connection agreement;

● system-operation rules;

● dispatch obligations;

● metering arrangements;

● electricity-market rules; and

● NSMO requirements.

Commissioning and COD

Commercial operation mechanics must align with:

● the EPC schedule;

● financing milestones;

● grid availability;

● testing procedures;

● performance guarantees; and

● long-stop dates.

Dispute resolution

Investors should understand precisely what dispute-resolution options Vietnamese law permits under the relevant transaction structure and whether those mechanisms will satisfy lenders and investment committees.

5. CIRCULAR 12 CREATES AN OPPORTUNITY – BUT NOT EVERY CLAUSE WILL AUTOMATICALLY BE ACCEPTED

Foreign investors should be realistic.

Circular 12 does not mean that every clause requested by an international lender will automatically be accepted by the Vietnamese purchaser.

Nor does it mean that regulatory restrictions disappear.

What Circular 12 does provide is something extremely valuable:

an express legal basis for the parties to negotiate and supplement the PPA.

That changes the strategy.

Instead of simply identifying deficiencies in the standard wording, foreign investors should prepare a structured bankability negotiation package.

For each proposed amendment, the investor should be able to explain:

1. why the clause is required;

2. what project risk it addresses;

3. why lenders require it;

4. whether Vietnamese law permits it;

5. whether comparable risk allocation exists elsewhere;

6. what alternative drafting could achieve the same objective; and

7. what the economic consequences are if the risk remains with the project company.

The best PPA negotiations are therefore not conducted as a list of foreign-law-style amendments.

They are conducted as a bankability dialogue.

6. THE MOST UNDERESTIMATED FACTOR: KNOW WHO ACTUALLY CONTROLS THE PPA ISSUES

Foreign investors sometimes speak generally about “negotiating with the Vietnamese Government.”

That is too imprecise to develop a successful power project.

There is no single institution that decides everything.

Different issues fall within the responsibility of different bodies.

Depending on the project structure, the relevant institutional stakeholders may include:

Ministry of Industry and Trade

MOIT is central to electricity-sector policy and regulation.

Its electricity authorities play important roles regarding:

● electricity pricing methodologies;

● generation-price frameworks;

● market regulation;

● implementation of the Electricity Law;

● PPA regulation; and

● regulatory guidance.

Vietnam Electricity – EVN

EVN remains one of the most important institutions in Vietnam’s electricity sector and an essential commercial counterparty or stakeholder in many grid-connected projects.

EVN Electric Power Trading Company – EVNEPTC

For conventional power projects, EVNEPTC can be particularly important because it performs substantial PPA negotiation and electricity-trading functions within the EVN system.

Foreign investors should understand not merely EVN at corporate level, but which unit is actually responsible for negotiating the commercial issue in question.

National Power System and Market Operation Company – NSMO

NSMO plays a critical role in:

● system operation;

● dispatch;

● market operation;

● market settlement; and

● implementation of national-grid DPPA arrangements.

For projects participating in the competitive electricity market, NSMO’s role can become fundamental.

Provincial authorities

The relevant Provincial People’s Committee and provincial departments may be important for:

● project implementation;

● land;

● local planning;

● construction;

● environmental coordination;

● investment procedures; and

● local infrastructure.

Grid companies and Power Corporations

The relevant transmission or distribution entities may control issues that directly affect:

● connection;

● technical design;

● metering;

● interconnection works; and

● energisation.

7. KNOWING THE PEOPLE BEHIND THE PPA CAN DRAMATICALLY IMPROVE PROJECT EXECUTION

This point should be understood correctly.

It is not about obtaining preferential treatment.

It is about knowing:

● who has legal responsibility for a particular issue;

● who possesses technical expertise;

● who is authorised to negotiate;

● who must approve deviations;

● who must provide regulatory guidance;

● which institution must be consulted before another institution can act; and

● what documentation decision-makers need before they can responsibly approve a proposal.

Vietnamese power projects are highly institutional.

An investor may lose months pursuing an issue with an organisation that simply does not have authority to resolve it.

Conversely, an investor that properly maps the decision-making structure can significantly improve efficiency.

For every major PPA issue, we recommend preparing an institutional responsibility matrix.

For example:

|Issue                       |Principal institutional interface        |
|—————————-|—————————————–|
|PPA commercial negotiation  |Relevant electricity purchaser / EVNEPTC |
|Generation-price methodology|MOIT / competent electricity authority   |
|Grid connection             |Relevant transmission/distribution entity|
|Dispatch                    |NSMO                                     |
|Wholesale electricity market|NSMO / competent market institutions     |
|DPPA registration           |NSMO and relevant parties                |
|Land/project implementation |Provincial authorities                   |
|Environmental approval      |Competent environmental authority        |

The precise allocation must be confirmed for each project.

This institutional mapping should happen before formal PPA negotiations begin.

8. THE NEW RULE: PREPARE FOR THE PPA NEGOTIATION BEFORE THE PROJECT IS FULLY DEVELOPED

The traditional development sequence often looks like this:

site → investment licence → EPC → PPA → financing

For a serious foreign investor, that can be dangerous.

A better approach is:

Start with bankability and work backwards.

Before committing substantial development capital, the investor should understand:

What will the lenders require at financial close?

Then structure the project accordingly.

The core package normally includes:

PPA + feedstock + land + grid + permits + EPC + O&M + insurance + financing + investment protection.

These documents cannot be developed independently.

For example:

A PPA COD date must align with the EPC schedule.

The loan maturity must fit the project and land term.

Termination compensation must interact with outstanding debt.

Feedstock security must support projected generation.

Grid availability must support the financial model.

Foreign-exchange risk must be modelled into debt service.

All of these issues ultimately intersect in the PPA.

9. BIOMASS HAS ONE UNIQUE BANKABILITY CHALLENGE: FEEDSTOCK

Solar investors do not negotiate fuel-supply contracts.

Biomass investors do.

That difference is fundamental.

A 20-year PPA has little value if the plant runs out of fuel after five years.

Foreign investors must therefore perform rigorous feedstock due diligence.

That means understanding:

● annual volumes;

● competing uses;

● collection radius;

● transportation costs;

● seasonal availability;

● moisture levels;

● calorific value;

● contamination;

● storage requirements;

● price escalation;

● alternative feedstock;

● agricultural trends;

● climate risks; and

● contractual enforceability.

A proper Feedstock Supply Agreement should address:

● minimum annual quantity;

● quality specifications;

● delivery schedule;

● pricing methodology;

● escalation;

● substitution;

● penalties;

● security;

● force majeure;

● termination; and

● lender assignment or step-in where appropriate.

For projects relying on thousands of small agricultural suppliers, developers may need:

● cooperatives;

● aggregators;

● collection centres;

● multiple supply contracts;

● buffer inventories; and

● alternative-fuel capability.

Biomass bankability therefore rests on two pillars:

the PPA on the revenue side, and the Feedstock Supply Agreement on the operating-cost side.

Both must satisfy lenders.

10. DPPA MAKES BIOMASS EVEN MORE INTERESTING

Vietnam’s DPPA regime creates an additional opportunity.

Decree No. 57/2025/NĐ-CP established a framework for direct power purchases between renewable generators and large electricity users.

Importantly, national-grid DPPA eligibility expressly covers qualifying renewable generators using:

wind, solar or biomass, with capacity of 10 MW or more, connected to the national grid and participating directly in the competitive wholesale electricity market. (EVN)

The Government subsequently amended the DPPA and renewable-energy framework through Decree No. 243/2026/NĐ-CP dated 26 June 2026, meaning any current project must be structured using the amended 2026 regime rather than relying solely on the original 2025 rules. (EVN)

This is a crucial 2026 update for foreign investors.

Biomass projects therefore have potentially two very different offtake models.

11. OPTION ONE: CONVENTIONAL GRID PPA

The conventional model remains highly relevant.

Advantages can include:

● established electricity-sector counterparties;

● established regulatory structures;

● familiar settlement mechanisms; and

● integration into Vietnam’s national electricity system.

But the project must still negotiate a commercially viable price and sufficiently bankable risk allocation.

Circular 12 therefore becomes central.

The investor should not merely review the PPA after receiving it.

The investor should enter negotiations with a fully developed bankability position.

12. OPTION TWO: CORPORATE DPPA

The alternative is direct or contractually linked supply to large electricity consumers under the DPPA regime.

This can be particularly attractive for multinational companies seeking:

● renewable electricity;

● decarbonisation;

● ESG compliance;

● Scope 2 reductions;

● long-term energy-price visibility; and

● supply-chain emissions reductions.

For biomass, this can become especially powerful where the industrial customer is located near the biomass source.

Consider:

rice-processing residues → biomass plant → industrial electricity customer

or:

wood residues → cogeneration → electricity + steam → manufacturing facility

or:

sugar cane bagasse → CHP → industrial user + grid electricity

These models can create multiple economic benefits from the same fuel stream.

However, DPPA does not automatically equal bankability.

Investors must analyse:

● corporate offtaker credit;

● electricity-market exposure;

● basis risk;

● settlement;

● grid charges;

● customer default;

● replacement offtaker risk;

● termination compensation;

● security arrangements; and

● regulatory change.

13. THE MOST ATTRACTIVE PROJECTS MAY HAVE MULTIPLE REVENUE STREAMS

Sophisticated biomass investors should not necessarily view electricity sales as the only source of revenue.

Depending on the technology and project structure, revenue can potentially come from:

electricity

steam / thermal energy

waste disposal or treatment

biochar

ash or other useful by-products

carbon-related environmental attributes

industrial decarbonisation services

The more diversified the revenue structure, the less dependent the project may be on one tariff alone.

But each revenue stream must be legally and contractually secured.

14. TEN QUESTIONS FOREIGN INVESTORS SHOULD ANSWER BEFORE COMMITTING SERIOUS CAPITAL

Before substantial development expenditure is incurred, we recommend obtaining clear answers to at least the following ten questions.

1. Is the project compatible with Vietnam’s applicable electricity-development planning framework?

2. Are the land rights secure for the entire investment and financing period?

3. Is sufficient feedstock available at realistic prices for the full debt tenor?

4. Is grid connection technically and commercially feasible?

5. What electricity-price framework applies?

6. What provisions can be negotiated under Circular 12 to improve bankability?

7. Is a conventional PPA or DPPA commercially superior?

8. Which Vietnamese institution controls each approval, tariff, grid and PPA issue?

9. What investment-treaty protection is available to the foreign investor?

10. Can the entire contractual package achieve international project financing?

If the investor cannot answer these questions, the project is probably not yet investment-ready.

15. INTERNATIONAL INVESTMENT PROTECTION MUST BE CONSIDERED BEFORE A DISPUTE EXISTS

Foreign investors should also consider investment-protection structuring at the beginning of the transaction.

Depending on nationality and corporate structure, existing bilateral or multilateral investment treaties may provide protections against certain forms of governmental conduct.

CPTPP can be particularly relevant for qualifying investors from CPTPP jurisdictions.

European investors should also continue to monitor the EU-Vietnam Investment Protection Agreement.

The important point is timing.

Treaty structuring should be undertaken before a dispute is foreseeable.

An investor cannot safely assume that it can restructure after a dispute has already arisen simply to obtain treaty jurisdiction.

Project structuring, financing and investment protection should therefore be considered together.

16. WHY CIRCULAR 12 MAY BECOME THE MOST VALUABLE TOOL IN BIOMASS PROJECT DEVELOPMENT

Circular 12 changes the mindset.

Before Circular 12, foreign investors often approached the Vietnamese PPA as though the principal legal exercise was identifying which provisions of a statutory contract they disliked.

That is no longer the most productive approach.

The better question is:

What is the most bankable PPA we can lawfully negotiate under Vietnam’s current regulatory framework?

That question opens a much more sophisticated discussion.

It requires coordination among:

● investor;

● legal counsel;

● lenders;

● financial adviser;

● technical adviser;

● EPC contractor;

● feedstock specialists;

● electricity purchaser;

● EVN/EVNEPTC;

● MOIT;

● NSMO; and

● relevant local authorities.

Circular 12 provides the legal opening.

Experienced project counsel must then convert that legal opening into commercially useful contractual protection.

17. OUR RECOMMENDED PPA NEGOTIATION STRATEGY

For serious foreign biomass developers, we recommend approaching the PPA through five stages.

Stage 1 – Bankability Gap Analysis

Compare the proposed Vietnamese PPA against the requirements of likely international lenders.

Identify:

● critical gaps;

● desirable improvements;

● Vietnamese-law constraints; and

● commercial alternatives.

Stage 2 – Stakeholder Mapping

Identify who actually controls each issue.

Do not approach “the Government” generically.

Determine which issue belongs to:

● MOIT;

● the electricity purchaser;

● EVN/EVNEPTC;

● NSMO;

● grid entities;

● provincial authorities; or

● another competent institution.

Stage 3 – Prioritisation

Not every clause deserves equal negotiating capital.

Identify the provisions that could actually prevent financing.

Those should receive priority.

Stage 4 – Negotiation

Present proposed amendments together with:

● legal basis;

● financing rationale;

● economic explanation; and

● alternatives.

The objective should not be confrontation.

It should be to create a structure that Vietnamese institutions can approve and international lenders can finance.

Stage 5 – Financing Alignment

Once commercial principles are agreed, ensure the PPA works together with:

● financing documents;

● EPC contract;

● feedstock agreements;

● grid connection;

● land documents;

● O&M agreement; and

● insurance.

This is where an apparently small drafting issue can have a multi-million-dollar economic consequence.

18. KNOWING THE RESPONSIBLE DECISION-MAKERS IS A PROJECT ASSET

Foreign investors sometimes underestimate the value of institutional experience.

In Vietnam, understanding how the electricity sector actually functions can save enormous amounts of time.

A successful project team should know:

who to speak to;

when to approach them;

what authority they possess;

what information they require;

what concerns they are likely to have;

and

what approvals must occur before the next institution can act.

Developing professional relationships with the responsible officials and commercial counterparties, maintaining transparent dialogue and understanding their mandate can dramatically increase project execution efficiency.

This is not a substitute for law.

It is how the law is effectively implemented in a complex infrastructure project.

CONCLUSION – VIETNAM’S BIOMASS OPPORTUNITY IS REAL, BUT THE PPA WILL OFTEN DECIDE THE PROJECT

Vietnam has the resources.

Vietnam has the electricity demand.

Vietnam has ambitious biomass targets.

Vietnam now has a modernised electricity framework, a DPPA regime and—crucially—an expressly negotiable PPA framework under Circular 12/2025/TT-BCT.

For foreign investors, this represents a major opportunity.

But the winners will not simply be those who locate the largest biomass resource.

They will be the investors who structure the strongest projects.

That means:

secure feedstock;

bankable land rights;

realistic grid access;

appropriate financing;

a sophisticated DPPA or conventional offtake strategy;

and above all:

A BANKABLE POWER PURCHASE AGREEMENT.

Circular 12 should therefore be viewed as much more than another implementing regulation.

It creates the legal basis for investors and electricity purchasers to negotiate additional PPA provisions within Vietnamese law.

That makes the quality of PPA preparation and negotiation more important than ever.

Foreign investors should enter those negotiations with a clear understanding of:

● lender requirements;

● Vietnamese regulatory limitations;

● tariff methodology;

● EVN and EVNEPTC procedures;

● NSMO requirements;

● grid constraints;

● provincial approvals;

● DPPA alternatives; and

● the institutional decision-makers responsible for each issue.

Getting to know the people and institutions behind the PPA—professionally, transparently and early in the development process—can dramatically improve the prospects of moving a project from concept to negotiation, from negotiation to financial close, and from financial close to successful commercial operation.

Vietnam’s biomass opportunity is not merely about converting agricultural residues into electricity.

It is about converting Vietnam’s extraordinary renewable resources into legally secure, commercially viable and internationally financeable infrastructure projects.

And in 2026, Circular 12 and the negotiation of a bankable PPA are at the very heart of that opportunity.

***

For more information on the above, please do not hesitate to contact the author Dr. Oliver Massmann under omassmann@duanemorris.com. Dr. Oliver Massmann is the General Director of Duane Morris Vietnam LLC.

ベトナムの魔法の9月:フロンティア時代の終焉とグローバル投資時代の幕開け

FTSEラッセルによる2026921日の新興国市場への格上げグローバル株式投資家が今なすべきこと、機会の所在、および今後12ヶ月間のポジショニングについて

執筆: オリバー・マスマン博士(Dr. Oliver Massmann)、Duane Morris Vietnam LLC パートナー兼ゼネラルディレクター

2026年9月は、ベトナムの資本市場にとって大きな転換点となります。 2026年9月21日、ベトナムはFTSEラッセルにより「フロンティア市場」から「セカンダリー・エマージング市場(新興国市場)」へと再分類される予定です。 グローバル株式投資家にとって、重要な問題はもはやベトナムが格上げされるかどうかではありません。 今問われているのは、「投資家は今、何をすべきか」ということです。

答えはシンプルです。格上げ前に準備を整え、選択的に投資を行い、9月21日以降を見据えて行動することです。

なぜ921日が重要なのか

この格上げにより、ベトナムは世界の主流な新興国市場投資ユニバースへと移行します。 基準を満たすベトナム株は、以下の主要なFTSEグローバル・ベンチマークの対象となります。

  • FTSEエマージング・マーケッツ(FTSE Emerging Markets)
  • FTSEオール・ワールド(FTSE All-World)
  • FTSEグローバル・オール・キャップ(FTSE Global All Cap)

これらのインデックスは、国際的な資産運用会社、機関投資家、パッシブ・インデックス・ファンドに連動されているため、極めて重要です。 したがって、ベトナムはグローバル資本からより一層注目を集めることになります。 しかし、投資家はこの出来事を誤解すべきではありません。

9月21日は終着点ではなく、始まりに過ぎないのです。

FTSE12ヶ月かけてベトナムを段階的に組み入れます

ベトナムは、新興国市場インデックスに直ちに完全なウェイトで組み入れられるわけではありません。 FTSEラッセルは、以下の4つの段階を経て格上げを実施します。

  • 2026年9月21日:10%の組み入れ
  • 2027年3月22日:20%追加(累計30%)
  • 2027年6月21日:35%追加(累計65%)
  • 2027年9月20日:35%追加(累計100%)

つまり、投資家はこれを単日のインデックス・イベントとみなすべきではありません。 これは12ヶ月にわたる資本配分プロセスなのです。

どの銘柄が重要か?

FTSEラッセルは、同社のグローバル株式インデックス・シリーズに組み入れる対象として、100以上のベトナム銘柄を特定しました。 最も注目される大型および中型株には以下が含まれます。

  • ベトコムバンク(Vietcombank)– VCB
  • ビングループ(Vingroup)– VIC
  • ビンホームズ(Vinhomes)– VHM
  • BIDV – BID
  • ホアファット・グループ(Hoa Phat Group)– HPG
  • VPバンク(VPBank)– VPB

しかし、投資家は単に最大手の銘柄を購入すべきではありません。 真の課題は、以下の条件を備えた企業を特定することです。

  • 強力な収益成長
  • 妥当なバリュエーション
  • 十分な外国人投資家保有枠
  • 高い流動性
  • 健全なコーポレートガバナンス
  • 持続可能な競争優位性

インデックスというストーリーを買うのではなく、企業を買うべきです。

921日より前に投資家がなすべきこと

1. 今すぐ候補リスト(ショートリスト)を作成する

FTSEの組み入れがなくても魅力的な企業に焦点を当ててください。 以下の点を見直します:バリュエーション、収益、バランスシート、浮動株、外国人保有枠の制限、流動性、ガバナンス。

2. 外国人保有枠(Foreign Ownership Room)を確認する

これは引き続き極めて重要です。 新興国市場への分類は、外国人投資家があらゆるベトナム株を無制限に購入できることを意味するものではありません。 有望な投資アイデアであっても、外国人保有枠が上限に達していれば投資不可能となります。

3. インフラを整備する

外国人投資家は、以下の準備が整っていることを確認する必要があります。

  • 証券およびカストディの手配
  • ブローカーとの関係構築
  • 外国人投資家としての登録
  • 決済手続き
  • 通貨両替の手配
  • コンプライアンスの承認

9月21日を待たずに、市場アクセスの手配を行ってください。

4. ボラティリティを予期する

9月18日から21日の前後には、以下の事象が見られる可能性があります。

  • 取引量の増加
  • 強力な海外資金の流入
  • 通常とは異なるクロージング・オークション(引け値決定)の動向
  • 短期的な価格の歪み

テクニカルなインデックス買いをファンダメンタルな価値と混同しないでください。

やってはいけないこと

投資家は次の3つの間違いを避けるべきです。

  • すべてのFTSE構成銘柄を追わない: インデックスへの組み入れは、質の高さを保証するものではありません。
  • 921日が完璧な買い場であると思い込まない: 段階的なエントリー戦略のほうが賢明である可能性があります。
  • バリュエーションを無視しない: 格上げの期待はすでに価格に織り込まれている場合があります。

より大きな機会

最も興味深い展開は、初期の格上げに対する熱狂の後に訪れるかもしれません。 ベトナムは、以下の分野へのエクスポージャーを提供します。

  • 銀行、テクノロジー、工業生産、消費者の成長、航空、鉄鋼・素材、証券、インフラ、不動産、および継続的な中間層の拡大。

また、この格上げにより、以下が向上する可能性もあります。

  • 国際的な認知度、流動性、機関投資家の保有率、ガバナンスへのプレッシャー、情報開示基準、市場の長期的な株式リスクプロファイル。

これが、パッシブなインデックス資金流入を超えて、この格上げが重要である理由です。

グローバル投資家のための12ヶ月のアクションプラン

現在から2026年9月18日まで

  • 準備を整える。
  • ウォッチリストを作成する。
  • バリュエーションと外国人枠を確認する。
  • カストディおよび執行の手配が整っているか確認する。

2026年9月18日~21日

  • 規律を保つ。
  • ボラティリティを予期する。
  • パッシブフローを追及しない。
  • 価格の歪みを選択的に活用する。

2026年10月~2027年3月

  • 再評価する。
  • 格上げの熱狂の恩恵を受けただけの銘柄と、実際の収益成長をもたらしている企業を区別する。
  • 2027年3月の第2回FTSEトランシェに備える。

2027年3月~9月

  • 戦略的に思考する。
  • 次の2つの大きな組み入れウェーブの前にエクスポージャーを見直す。
  • より深く持続可能な国際的な機関投資家層を引き付けている企業を特定する。

結論ベトナムの魔法の9

長年にわたり、外国人投資家はベトナムがいつフロンティア市場の地位から脱却するのかを問い続けてきました。 その答えは今や明らかです:2026年9月21日です。 しかし、真の投資ストーリーは単一の日付ではありません。 それに続く12ヶ月間なのです。

FTSEラッセルによるベトナムの格上げは、国際的な投資家にとっての市場の認知度、アクセスしやすさ、そして重要性を高めるでしょう。 パッシブな資金流入をもたらす可能性があります。 アクティブな機関投資家資本を引き付ける可能性があります。 流動性を改善する可能性があります。 より良いガバナンスと情報開示への圧力を高める可能性があります。 しかし、リスクが排除されるわけではありません。

したがって、勝利のための戦略は、やみくもにベトナムを買うことではありません。 慎重に準備を行い、選択的に投資することです。

外国人投資家が今すべきこと:

  • 銘柄を知る。
  • バリュエーションを知る。
  • 外国人保有枠を確認する。
  • 市場アクセスの準備をする。
  • ボラティリティを予期する。
  • 選択的にポジションを構築する。
  • 1日だけでなく、FTSEの4つの段階(ウェーブ)で考える。

ベトナムのフロンティア時代は終わろうとしています。 グローバルな新興国市場時代が幕を開けるのです。

投資家にとっての疑問は、もはやベトナムを注視すべきかどうかではありません。

グローバル資本が流入する中で、どのベトナム企業を所有したいかということです。

新たなサイバーセキュリティ・フレームワークに関するご質問や詳細情報をご希望の場合は、オリバー・マスマン博士(omassmann@duanemorris.com)までご遠慮なくお問い合わせください。

Anwalt in Vietnam Dr. Oliver Massmann -VIETNAMS MAGISCHER SEPTEMBER: DIE FRONTIER-ÄRA ENDET – DIE ÄRA GLOBALER INVESTITIONEN BEGINNT

FTSE Russells Emerging-Market-Aufstufung am 21. September 2026 – Was globale Aktieninvestoren jetzt tun müssen, wo die Chancen liegen und wie man sich für die nächsten 12 Monate positioniert

Der September 2026 markiert einen Wendepunkt für Vietnams Kapitalmärkte. Am 21. September 2026 wird Vietnam von FTSE Russell von einem Frontier Market zu einem Secondary Emerging Market hochgestuft.

Für globale Aktieninvestoren stellt sich nicht mehr die Frage, ob Vietnam aufgestuft wird. Die Frage lautet: WAS SOLLTEN INVESTOREN JETZT TUN?

Die Antwort ist einfach: sich vor der Aufstufung vorbereiten, selektiv investieren und über den 21. September hinausdenken.

WARUM DER 21. SEPTEMBER WICHTIG IST

Die Aufstufung bringt Vietnam in das Mainstream-Universum der globalen Emerging-Market-Investments. Qualifizierte vietnamesische Aktien werden für wichtige FTSE-Benchmarks zugelassen, darunter:

  • FTSE Emerging Markets
  • FTSE All-World
  • FTSE Global All Cap

Dies ist bedeutsam, da diese Indizes von internationalen Vermögensverwaltern, institutionellen Investoren und passiven Indexfonds verfolgt werden. Vietnam wird dadurch wesentlich sichtbarer für globales Kapital.

Aber Investoren sollten das Ereignis nicht missverstehen: DER 21. SEPTEMBER IST NICHT DAS ENDE DER GESCHICHTE. ES IST DER ANFANG.

FTSE WIRD VIETNAM ÜBER 12 MONATE PHASENWEISE AUFNEHMEN

Vietnam wird nicht sofort mit voller Gewichtung in die Emerging-Market-Indizes aufgenommen. FTSE Russell setzt die Aufstufung in vier Phasen um:

    1. September 2026: 10 % Aufnahme
  •  
  • März 2027: zusätzliche 20 % – kumuliert 30 %
  •  
  • Juni 2027: zusätzliche 35 % – kumuliert 65 %
  •  
  • September 2027: zusätzliche 35 % – kumuliert 100 %

Das bedeutet: Investoren sollten dies nicht als einmaliges Index-Ereignis betrachten, sondern als einen 12-monatigen Kapitalallokationsprozess.

WELCHE AKTIEN SIND WICHTIG?

FTSE Russell hat über 100 vietnamesische Aktien für die Aufnahme in seine globale Indexserie identifiziert. Zu den prominentesten Large- und Mid-Cap-Namen gehören:

  • Vietcombank – VCB
  • Vingroup – VIC
  • Vinhomes – VHM
  • BIDV – BID
  • Hoa Phat Group – HPG
  • VPBank – VPB

Doch Investoren sollten nicht einfach die größten Namen kaufen. Die eigentliche Aufgabe besteht darin, Unternehmen zu identifizieren mit:

  • starkem Gewinnwachstum
  • angemessenen Bewertungen
  • ausreichendem Spielraum für ausländische Beteiligungen
  • hoher Liquidität
  • solider Corporate Governance
  • nachhaltigen Wettbewerbsvorteilen

KAUFEN SIE NICHT DIE INDEXGESCHICHTE. KAUFEN SIE DAS UNTERNEHMEN.

WAS SOLLTEN INVESTOREN VOR DEM 21. SEPTEMBER TUN?

1. JETZT EINE SHORTLIST ERSTELLEN Konzentrieren Sie sich auf Unternehmen, die auch ohne FTSE-Aufnahme attraktiv wären. Prüfen Sie:

  • Bewertung
  • Gewinne
  • Bilanz
  • Free Float
  • Grenzen für ausländische Beteiligungen
  • Liquidität
  • Governance

2. FREIEN AUSLÄNDERANTEIL PRÜFEN Dies bleibt entscheidend. Die Einstufung als Emerging Market bedeutet nicht, dass ausländische Investoren unbegrenzt jede vietnamesische Aktie kaufen können. Eine starke Investmentidee kann uninvestierbar werden, wenn der Ausländeranteil ausgeschöpft ist.

3. INFRASTRUKTUR VORBEREITEN Ausländische Investoren sollten sicherstellen, dass sie verfügen über:

  • Wertpapier- und Verwahrungsvereinbarungen
  • Broker-Beziehungen
  • Registrierungen für ausländische Investoren
  • Abwicklungsverfahren
  • Währungsumtausch-Vereinbarungen
  • Compliance-Genehmigungen

Warten Sie nicht bis zum 21. September, um den Marktzugang zu organisieren.

4. VOLATILITÄT ERWARTEN Der Zeitraum um den 18.–21. September könnte Folgendes mit sich bringen:

  • höhere Handelsvolumina
  • starke ausländische Zuflüsse
  • ungewöhnliche Aktivitäten in der Schlussauktion
  • kurzfristige Preisverzerrungen

Verwechseln Sie technisches Index-Kaufen nicht mit fundamentalem Wert.

WAS NICHT ZU TUN IST

Investoren sollten drei Fehler vermeiden:

  • Nicht jeder FTSE-Wert ist ein Kauf. Indexaufnahme garantiert keine Qualität.
  • Nicht annehmen, dass der 21. September der perfekte Kaufzeitpunkt ist. Eine gestaffelte Einstiegsstrategie kann sinnvoller sein.
  • Bewertungen nicht ignorieren. Manche Erwartungen sind bereits eingepreist.

DIE GRÖSSERE CHANCE

Der interessanteste Teil der Geschichte könnte nach der ersten Aufstufungs-Euphorie kommen. Vietnam bietet Zugang zu:

  • Banken
  • Technologie
  • Industrieller Fertigung
  • Konsumwachstum
  • Luftfahrt
  • Stahl und Materialien
  • Wertpapierhandel
  • Infrastruktur
  • Immobilien
  • dem weiteren Ausbau der vietnamesischen Mittelschicht

Die Aufstufung könnte außerdem verbessern:

  • internationale Sichtbarkeit
  • Liquidität
  • institutionelle Beteiligung
  • Governance-Druck
  • Offenlegungsstandards
  • das langfristige Aktienrisikoprofil des Marktes

Darum ist die Aufstufung mehr als nur passive Indexzuflüsse.

DER 12-MONATS-AKTIONPLAN FÜR GLOBALE INVESTOREN

JETZT BIS 18. SEPTEMBER 2026 Vorbereiten. Watchlist erstellen. Bewertungen und Ausländeranteile prüfen. Sicherstellen, dass Verwahrung und Ausführung bereitstehen.

18.–21. SEPTEMBER 2026 Diszipliniert bleiben. Volatilität erwarten. Keine passiven Zuflüsse jagen. Preisverzerrungen selektiv nutzen.

OKTOBER 2026 – MÄRZ 2027 Neu bewerten. Unterscheiden zwischen Aktien, die nur von der Aufstufungs-Euphorie profitierten, und Unternehmen mit echtem Gewinnwachstum. Vorbereitung auf die zweite FTSE-Tranche im März 2027.

MÄRZ – SEPTEMBER 2027 Strategisch denken. Engagement vor den nächsten beiden großen Aufnahmephasen überprüfen. Unternehmen identifizieren, die nachhaltiges institutionelles Eigentum anziehen.

FAZIT – VIETNAMS MAGISCHER SEPTEMBER

Jahrelang fragten ausländische Investoren, wann Vietnam den Frontier-Markt-Status hinter sich lassen würde. Die Antwort ist nun klar: 21. SEPTEMBER 2026.

Doch die eigentliche Investmentgeschichte ist nicht ein Datum. Es sind die 12 Monate danach.

Die FTSE-Russell-Aufstufung Vietnams wird die Sichtbarkeit, Zugänglichkeit und Relevanz des Marktes für internationale Investoren erhöhen. Sie könnte passive Zuflüsse bringen. Sie könnte aktives institutionelles Kapital anziehen. Sie könnte die Liquidität verbessern. Sie könnte den Druck auf bessere Governance und Offenlegung erhöhen.

Aber sie beseitigt das Risiko nicht. Die Gewinnerstrategie ist daher nicht, Vietnam blind zu kaufen. Sondern sorgfältig vorzubereiten und selektiv zu investieren.

AUSLÄNDISCHE INVESTOREN SOLLTEN JETZT:

  • die Aktien kennen
  • die Bewertungen prüfen
  • den Ausländeranteil kontrollieren
  • den Marktzugang vorbereiten
  • Volatilität erwarten
  • Positionen selektiv aufbauen
  • in vier FTSE-Wellen denken, nicht an einem Tag

Vietnams Frontier-Ära endet. Seine globale Emerging-Market-Ära beginnt.

Die Frage für Investoren lautet nicht mehr, ob sie Vietnam beobachten sollen. Sondern welche vietnamesischen Unternehmen sie besitzen wollen, wenn globales Kapital eintrifft.

Für weitere Informationen oder Fragen zum neuen Cybersecurity-Rahmenwerk wenden Sie sich bitte an Dr. Oliver Massmann unter omassmann@duanemorris.com.

VIETNAM’S MAGIC SEPTEMBER: THE FRONTIER ERA ENDS – THE GLOBAL INVESTMENT ERA BEGINS _FTSE Russell’s 21 September 2026 Emerging-Market Upgrade – What Global Equity Investors Must Do Now, Where the Opportunities Are, and How to Position for the Next 12 Months

September 2026 is a turning point for Vietnam’s capital markets.

On 21 September 2026, Vietnam is scheduled to be reclassified by FTSE Russell from Frontier Market to Secondary Emerging Market status.

For global equity investors, the key question is no longer whether Vietnam will be upgraded.

It is:

WHAT SHOULD INVESTORS DO NOW?

The answer is simple: prepare before the upgrade, invest selectively, and think beyond 21 September.

WHY 21 SEPTEMBER MATTERS

The upgrade moves Vietnam into the mainstream global emerging-market investment universe.

Qualifying Vietnamese stocks become eligible for major FTSE global benchmarks, including:

  • FTSE Emerging Markets;
  • FTSE All-World; and
  • FTSE Global All Cap.

This matters because these indices are followed by international asset managers, institutional investors and passive index funds.

Vietnam will therefore become significantly more visible to global capital.

But investors should not misunderstand the event.

SEPTEMBER 21 IS NOT THE END OF THE STORY. IT IS THE BEGINNING.

FTSE WILL PHASE VIETNAM IN OVER 12 MONTHS

Vietnam will not enter the emerging-market indices at full weight immediately.

FTSE Russell is implementing the upgrade in four stages:

21 September 2026: 10% inclusion
22 March 2027: additional 20% – cumulative 30%
21 June 2027: additional 35% – cumulative 65%
20 September 2027: additional 35% – cumulative 100%

That means investors should not view this as a one-day index event.

It is a 12-month capital-allocation process.

WHICH STOCKS MATTER?

FTSE Russell has identified more than 100 Vietnamese stocks for inclusion across its global equity index series.

The highest-profile large- and mid-cap names include:

  • Vietcombank – VCB
  • Vingroup – VIC
  • Vinhomes – VHM
  • BIDV – BID
  • Hoa Phat Group – HPG
  • VPBank – VPB

But investors should not simply buy the largest names.

The real work is to identify companies with:

  • strong earnings growth;
  • reasonable valuations;
  • sufficient foreign ownership room;
  • high liquidity;
  • sound corporate governance; and
  • sustainable competitive advantages.

DO NOT BUY THE INDEX STORY. BUY THE COMPANY.

WHAT SHOULD INVESTORS DO BEFORE 21 SEPTEMBER?

1. BUILD A SHORTLIST NOW

Focus on companies that would be attractive even without FTSE inclusion.

Review:

  • valuation;
  • earnings;
  • balance sheet;
  • free float;
  • foreign ownership limits;
  • liquidity;
  • governance.

2. CHECK FOREIGN OWNERSHIP ROOM

This remains critical.

Emerging-market classification does not mean foreign investors can buy unlimited quantities of every Vietnamese stock.

A strong investment idea can become uninvestable if foreign room is exhausted.

3. GET THE INFRASTRUCTURE READY

Foreign investors should make sure they have:

  • securities and custody arrangements;
  • broker relationships;
  • foreign-investor registrations;
  • settlement procedures;
  • currency-conversion arrangements;
  • compliance approvals.

Do not wait until 21 September to organize market access.

4. EXPECT VOLATILITY

The period around 18–21 September may see:

  • higher trading volumes;
  • strong foreign flows;
  • unusual closing-auction activity;
  • short-term price distortions.

Do not confuse technical index buying with fundamental value.

WHAT NOT TO DO

Investors should avoid three mistakes.

Do not chase every FTSE constituent

Index inclusion is not a guarantee of quality.

Do not assume 21 September is the perfect buying day

A staged entry strategy may be more sensible.

Do not ignore valuation

Some upgrade expectations may already be priced in.

THE BIGGER OPPORTUNITY

The most interesting part of the story may come after the initial upgrade excitement.

Vietnam offers exposure to:

  • banking;
  • technology;
  • industrial manufacturing;
  • consumer growth;
  • aviation;
  • steel and materials;
  • securities;
  • infrastructure;
  • real estate;
  • the continued expansion of the Vietnamese middle class.

The upgrade may also improve:

  • international visibility;
  • liquidity;
  • institutional ownership;
  • governance pressure;
  • disclosure standards;
  • the long-term equity risk profile of the market.

This is why the upgrade matters beyond passive index flows.

THE 12-MONTH ACTION PLAN FOR GLOBAL INVESTORS

NOW TO 18 SEPTEMBER 2026

Prepare.

Build the watchlist.

Check valuations and foreign room.

Make sure custody and execution arrangements are ready.

18–21 SEPTEMBER 2026

Stay disciplined.

Expect volatility.

Do not chase passive flows.

Use price dislocations selectively.

OCTOBER 2026–MARCH 2027

Reassess.

Separate stocks that merely benefited from upgrade enthusiasm from companies delivering real earnings growth.

Prepare for the second FTSE tranche in March 2027.

MARCH–SEPTEMBER 2027

Think strategically.

Review exposure before the next two major inclusion waves.

Identify the companies attracting deeper and more sustainable international institutional ownership.

CONCLUSION – VIETNAM’S MAGIC SEPTEMBER

For years, foreign investors asked when Vietnam would leave frontier-market status behind.

The answer is now clear:

21 SEPTEMBER 2026.

But the real investment story is not one date.

It is the 12 months that follow.

Vietnam’s FTSE Russell upgrade will increase the market’s visibility, accessibility and relevance to international investors.

It may bring passive inflows.

It may attract active institutional capital.

It may improve liquidity.

It may increase pressure for better governance and disclosure.

But it does not eliminate risk.

The winning strategy is therefore not to buy Vietnam blindly.

It is to prepare carefully and invest selectively.

FOREIGN INVESTORS SHOULD NOW:

Know the stocks.
Know the valuations.
Check foreign ownership.
Prepare market access.
Expect volatility.
Build positions selectively.
Think in four FTSE waves, not one day.

Vietnam’s frontier era is ending.

Its global emerging-market era is beginning.

THE QUESTION FOR INVESTORS IS NO LONGER WHETHER TO WATCH VIETNAM.

IT IS WHICH VIETNAMESE COMPANIES THEY WANT TO OWN AS GLOBAL CAPITAL ARRIVES.

Please do not hesitate to contact Dr. Oliver Massmann at omassmann@duanemorris.com if you have any questions or would like further information regarding the new cybersecurity framework.

Anwalt in Vietnam Dr. Oliver Massmann Vietnams Neuausrichtung der Cybersicherheit: Drei neue Dekrete definieren die Compliance-Anforderungen für ausländische Investoren und Unternehmen mit ausländischer Beteiligung neu

Vietnam hat einen bedeutenden Schritt zur Stärkung seiner regulatorischen Architektur im Bereich der Cybersicherheit unternommen.

Am 19. August 2026 hat die Regierung drei neue Dekrete erlassen, die die Verpflichtungen für Unternehmen in Vietnam erheblich erweitern:

  1. Dekret 331/2026/NĐ-CP – Cybersicherheitsschutz für Informationssysteme;
  2. Dekret 332/2026/NĐ-CP – Voraussetzungen für die Geschäftstätigkeit mit Cybersicherheitsprodukten und -dienstleistungen; sowie
  3. Dekret 333/2026/NĐ-CP – detaillierte Umsetzung des Gesetzes über Cybersicherheit.

Alle drei Dekrete traten unmittelbar am 19. August 2026 in Kraft.

Für ausländische Investoren und Unternehmen mit ausländischer Beteiligung („Foreign-Invested Enterprises“ oder FIEs) ist dieser neue Rechtsrahmen von erheblicher Bedeutung. Er führt klarere Anforderungen an die Klassifizierung von Informationssystemen, Lizenzierungsvorschriften für Cybersicherheitsunternehmen, erweiterte betriebliche Pflichten sowie detaillierte Anforderungen zur Datenlokalisierung ein.

Die Botschaft ist eindeutig: Die Einhaltung der Cybersicherheitsvorschriften in Vietnam wird zunehmend zu einer zentralen Voraussetzung für den Marktzugang und den Geschäftsbetrieb und ist nicht mehr lediglich eine IT-Frage.

1. Ein fünfstufiges Klassifizierungssystem für Cybersicherheit

Dekret 331 führt in Vietnam ein fünfstufiges Klassifizierungssystem für Informationssysteme ein.

Das Regime gilt unmittelbar für Organisationen, die Informationssysteme errichten, verwalten, betreiben oder modernisieren, welche der IT-Infrastruktur staatlicher Einrichtungen oder der Erbringung digitaler öffentlicher Dienstleistungen dienen. Andere Organisationen werden dazu angehalten, dieselben Standards freiwillig anzuwenden. Der Rahmen kann zudem relevant werden, wenn staatliche Auftraggeber entsprechende vertragliche Verpflichtungen gegenüber Dienstleistern des privaten Sektors vorsehen.

Das Klassifizierungssystem reicht von Stufe 1, die interne Systeme mit geringem Risiko umfasst, welche ausschließlich öffentliche Informationen verarbeiten, bis hin zu Stufe 5, die strategische Verteidigungs- und nationale Sicherheitssysteme, zentrale nationale Datenspeicher, internationale Verbindungsinfrastrukturen sowie besonders sensible industrielle Steuerungssysteme umfasst.

Je höher die Klassifizierungsstufe, desto strenger die Anforderungen.

Mindestens müssen Organisationen über folgende Elemente verfügen:

  1. Richtlinien und Verfahren zur Cybersicherheit;
  2. entsprechend qualifiziertes Personal;
  3. ein sicheres Systemdesign;
  4. operative Sicherheitskontrollen;
  5. Risikomanagementsysteme;
  6. Überwachungs- und Monitoringkapazitäten;
  7. Backup- und Wiederherstellungslösungen; sowie
  8. Mechanismen zur Reaktion auf Sicherheitsvorfälle.

Für Systeme der Stufen 3 und 4 müssen Cloud- und Rechenzentrumsumgebungen logisch voneinander getrennt sein.

Für Systeme der Stufe 5 ist eine physische Trennung von Systemen, Speichern und zentralen Netzwerkkomponenten erforderlich, ergänzt durch eine verpflichtende unabhängige Bewertung durch lizenzierte Prüfer.

Auch die Meldepflichten bei Sicherheitsvorfällen sind von erheblicher Bedeutung. Schwerwiegende Vorfälle müssen grundsätzlich innerhalb von 24 Stunden gemeldet werden, gefolgt von einem vollständigen Bericht innerhalb von 72 Stunden. Vorfälle mit Auswirkungen auf die nationale Sicherheit sind unverzüglich anzuzeigen.

Für FIEs, die Cloud-, Rechenzentrums-, Managed-Service- oder Infrastrukturleistungen erbringen, können diese Anforderungen insbesondere dann relevant werden, wenn Dienstleistungen für staatliche Stellen oder Betreiber kritischer Infrastruktur erbracht werden.

2. Cybersicherheitsprodukte und -dienstleistungen werden zu einem lizenzpflichtigen Geschäftsbereich

Dekret 332 führt ein formelles Lizenzierungssystem für Unternehmen ein, die in Vietnam Geschäfte mit Cybersicherheitsprodukten und Cybersicherheitsdienstleistungen betreiben. Die zivile Kryptografie ist hiervon ausgenommen.

Erforderlich ist eine Cybersicherheitsgeschäftslizenz des Ministeriums für öffentliche Sicherheit (Ministry of Public Security – MPS), die für zehn Jahre gültig ist.

Zu den allgemeinen Lizenzierungsvoraussetzungen gehören:

  1. Gründung nach vietnamesischem Recht;
  2. ordnungsgemäßer rechtlicher Status des Unternehmens;
  3. ein geeigneter gesetzlicher Vertreter oder bevollmächtigter Geschäftsführer;
  4. qualifiziertes technisches Personal;
  5. angemessene technische Ausstattung, Einrichtungen und Technologien; sowie
  6. Einhaltung spezifischer fachlicher Anforderungen.

Für Unternehmen mit ausländischer Beteiligung besteht eine besonders wichtige Voraussetzung darin, dass die verbleibende Laufzeit des Investitionsprojekts in Vietnam zum Zeitpunkt der Lizenzerteilung mehr als fünf Jahre betragen muss.

Für bestimmte Tätigkeiten im Bereich Cybersicherheit gelten zusätzliche Anforderungen.

Cybersicherheitsprüfungen und Beratung

Anbieter müssen über mindestens fünf qualifizierte technische Fachkräfte verfügen, die ihren Wohnsitz in Vietnam haben. Darüber hinaus muss der gesetzliche Vertreter vietnamesischer Staatsbürger sein.

Cybersicherheits-Monitoringdienste

Anbieter müssen mindestens zwölf qualifizierte technische Fachkräfte beschäftigen. Auch hier muss der gesetzliche Vertreter vietnamesischer Staatsangehöriger sein.

Herstellung, Handel, Import und Export von Cybersicherheitsprodukten

Unternehmen müssen geeignete Geschäfts- und Technologiepläne vorhalten, die einschlägigen technischen Standards erfüllen, Qualitätskontrollmaßnahmen umsetzen und Dokumentationen über die Endverwendung der betreffenden Produkte führen.

Import- und Exportgeschäfte unterliegen zusätzlich einer produktbezogenen Genehmigung des MPS, die jeweils zwei Jahre gültig ist.

Anträge sind in vietnamesischer Sprache einzureichen. Nach Einreichung vollständiger Unterlagen beträgt die gesetzliche Prüfungsfrist 28 Arbeitstage.

Lizenzierte Unternehmen müssen ferner bis zum 31. Januar eines jeden Jahres einen jährlichen Compliance-Bericht beim MPS einreichen.

Für internationale Cybersicherheitsunternehmen, die einen Markteintritt in Vietnam erwägen, sollten diese Anforderungen nunmehr Bestandteil der anfänglichen Investitions- und Strukturierungsanalyse sein.

3. Datenlokalisierung: Ein entscheidender Unterschied zwischen FIEs und Offshore-Anbietern

Dekret 333 enthält detailliertere Regelungen zu den Anforderungen an die Datenlokalisierung und die lokale Präsenz nach dem vietnamesischen Cybersicherheitsgesetz.

Die Vorschriften unterscheiden sich wesentlich danach, ob ein Unternehmen in Vietnam gegründet wurde oder seine Dienstleistungen grenzüberschreitend aus dem Ausland erbringt.

In Vietnam gegründete Unternehmen, einschließlich FIEs

In Vietnam gegründete Unternehmen unterliegen einer automatischen Pflicht zur lokalen Speicherung bestimmter Datenkategorien, die sich auf Nutzer in Vietnam beziehen.

Hierzu gehören insbesondere:

  1. personenbezogene Daten von Nutzern in Vietnam; sowie
  2. vom Nutzer erzeugte Daten wie Kontonamen, Nutzungszeiten von Diensten, Kreditkarteninformationen, E-Mail-Adressen, die zuletzt verwendeten Login- und Logout-IP-Adressen sowie Telefonnummern, die mit Benutzerkonten oder Daten verknüpft sind.

Für in Vietnam gegründete FIEs stellt sich daher nicht mehr die Frage, ob künftig Lokalisierungspflichten eingeführt werden könnten, sondern vielmehr, ob ihre bestehende Datenarchitektur diesen Anforderungen bereits entspricht.

Dies kann Unternehmen dazu veranlassen, ihre Cloud-Architektur, Serverstandorte, Lieferanten- und Dienstleisterbeziehungen, konzerninterne Datenflüsse sowie Outsourcing-Vereinbarungen zu überprüfen.

Ausländische Offshore-Unternehmen

Für Offshore-Dienstleister gilt die Verpflichtung nicht automatisch, sondern nur unter bestimmten Voraussetzungen.

Zu den betroffenen Branchen gehören unter anderem:

  1. Telekommunikation;
  2. Cloud- und Datenspeicherdienste;
  3. Domain-Name-Dienste;
  4. E-Commerce;
  5. Online-Zahlungsdienste;
  6. Transportplattformen;
  7. soziale Medien;
  8. Online-Spiele;
  9. Messaging-Dienste;
  10. VoIP-Dienste;
  11. E-Mail-Dienste; sowie
  12. sonstige Online-Informationsdienste.

Ein Offshore-Dienstleister unterliegt den Anforderungen zur Datenlokalisierung und lokalen Präsenz nur dann, wenn sämtliche drei nachstehenden Voraussetzungen kumulativ erfüllt sind:

  1. der Dienst wurde im Zusammenhang mit Verstößen gegen das Cybersicherheitsgesetz genutzt;
  2. die spezialisierte Cybersicherheitseinheit des Ministeriums für öffentliche Sicherheit (MPS) hat innerhalb eines Zeitraums von höchstens sechs Monaten dreimal schriftliche Ersuchen um Zusammenarbeit, Prävention oder Ermittlungsunterstützung übermittelt; und
  3. das Unternehmen beseitigt das Problem nicht, erfüllt die Anforderungen nicht vollständig oder behindert beziehungsweise vereitelt die geforderten Schutzmaßnahmen.

Sind diese Voraussetzungen erfüllt, kann der Minister für öffentliche Sicherheit eine formelle Anordnung erlassen, wonach das betreffende Unternehmen Daten in Vietnam speichern und eine Niederlassung oder Repräsentanz in Vietnam errichten muss.

Das Unternehmen hat anschließend zwölf Monate Zeit, diesen Anforderungen nachzukommen.

Die Mindestaufbewahrungsfrist für die betreffenden Daten beträgt grundsätzlich 24 Monate ab dem Datum der Speicherungsanordnung beziehungsweise solange die Anordnung in Kraft bleibt.

Für Ermittlungszwecke erforderliche Systemprotokolle müssen mindestens zwölf Monate aufbewahrt werden. Gleiches gilt für Protokolle über die Zuweisung von IP-Adressen im Telekommunikations- und Internetbereich, die vollständig, fortlaufend und sicher gespeichert werden müssen.

4. Was ausländische Investoren und FIEs jetzt tun sollten

Der neue Rechtsrahmen sollte Anlass für eine sofortige Überprüfung der Cybersicherheits-Compliance geben.

Ausländische Investoren und FIEs sollten insbesondere die folgenden Maßnahmen in Betracht ziehen.

Prüfung der Betroffenheit durch die Systemklassifizierung

Es sollte festgestellt werden, ob von dem Unternehmen entwickelte, verwaltete oder betriebene Systeme in den verpflichtenden Anwendungsbereich von Dekret 331 fallen oder durch Verträge mit staatlichen Auftraggebern beziehungsweise Betreibern kritischer Infrastrukturen vergleichbaren Anforderungen unterliegen könnten.

Überprüfung der Lizenzanforderungen im Bereich Cybersicherheit

Unternehmen, die Cybersicherheitsprodukte oder -dienstleistungen anbieten, sollten unverzüglich prüfen, ob eine MPS-Lizenz erforderlich ist und ob ihre derzeitige Unternehmensstruktur, Personalausstattung und Projektlaufzeit die entsprechenden Lizenzvoraussetzungen erfüllen.

Überprüfung von Governance und Personalstruktur

Unternehmen, die Dienstleistungen im Bereich Cybersicherheitsprüfung, -beratung oder -überwachung anbieten, sollten sicherstellen, dass sie die Anforderungen hinsichtlich eines vietnamesischen gesetzlichen Vertreters sowie die geltenden Mindestanforderungen an das Fachpersonal erfüllen.

Prüfung der Datenarchitektur

In Vietnam gegründete FIEs sollten sicherstellen, dass die vorgeschriebenen Kategorien von Nutzerdaten vietnamesischer Nutzer tatsächlich in Vietnam gespeichert werden.

Offshore-Anbieter digitaler Dienstleistungen sollten interne Verfahren einführen, um Anfragen des MPS frühzeitig zu erkennen und angemessen darauf zu reagieren, da solche Anfragen langfristig Lokalisierungspflichten auslösen können.

Einführung von Berichts- und Meldeverfahren

Lizenzierte Cybersicherheitsunternehmen sollten interne Compliance-Kalender etablieren, um die fristgerechte jährliche Berichterstattung gegenüber dem MPS bis spätestens zum 31. Januar sicherzustellen.

Durchführung einer rechtlichen und technischen Gap-Analyse

Da alle drei Dekrete unmittelbar in Kraft getreten sind, sollten Unternehmen eine koordinierte rechtliche, technische und operative Prüfung durchführen und das Thema nicht ausschließlich als IT-Frage behandeln.

5. Warum dies für die Investitionsstrategie wichtig ist

Vietnam gehört zu den am schnellsten wachsenden digitalen Volkswirtschaften Südostasiens.

Die zunehmende Verbreitung von Cloud Computing, FinTech, E-Commerce, digitaler Infrastruktur, künstlicher Intelligenz, Rechenzentren, intelligenter Fertigung und Online-Diensten führt dazu, dass Cybersicherheitsregulierung zu einem immer wichtigeren Bestandteil jeder Investitionsstrategie wird.

Die neuen Dekrete haben daher Auswirkungen weit über den Cybersicherheitssektor hinaus.

Sie betreffen insbesondere:

  1. die Strukturierung des Markteintritts;
  2. Investitionsgenehmigungen;
  3. Cloud-Architekturen;
  4. Data Governance;
  5. Outsourcing-Strukturen;
  6. M&A-Due-Diligence-Prüfungen;
  7. Technologieverträge;
  8. den Betrieb in regulierten Branchen;
  9. interne Compliance-Systeme; sowie
  10. die langfristige Sicherstellung der Geschäftskontinuität.

Für internationale Investoren muss die Einhaltung von Cybersicherheitsvorschriften zunehmend genauso behandelt werden wie Steuerrecht, Lizenzierungsanforderungen, Wettbewerbsrecht, Arbeitsrecht oder ausländisches Investitionsrecht: als grundlegender Bestandteil des Marktzugangs in Vietnam.

Fazit – Cybersicherheit wird Teil der regulatorischen Betriebslizenz

Die Verabschiedung der Dekrete 331, 332 und 333 markiert eine bedeutende Weiterentwicklung des vietnamesischen Cybersicherheitsregimes.

Die Richtung ist eindeutig.

Vietnam entwickelt sich hin zu einem stärker strukturierten, durchsetzbaren und institutionell überwachten Cybersicherheitsrahmen mit klareren Anforderungen in Bezug auf Systemschutz, Lizenzierung von Cybersicherheitsunternehmen, Datenlokalisierung, Personalanforderungen, Berichterstattung und Reaktion auf Sicherheitsvorfälle.

Für ausländische Investoren und FIEs ist die praktische Konsequenz ebenso klar:

Cybersicherheit kann nicht länger erst nach dem Markteintritt behandelt werden. Sie muss zunehmend bereits in der Phase der Investitionsstrukturierung berücksichtigt werden.

Unternehmen, die frühzeitig handeln, werden besser positioniert sein, ihre Datenarchitektur, Lizenzstrukturen, Personalressourcen, Verträge und operativen Systeme rechtzeitig anzupassen, bevor Probleme entstehen.

Unternehmen, die dies versäumen, können mit Verzögerungen bei Genehmigungen, Umstrukturierungskosten, verstärkter regulatorischer Kontrolle oder operativen Beeinträchtigungen konfrontiert werden.

Vietnam bleibt eines der attraktivsten Investitionsziele Asiens. Je digitaler, komplexer und stärker vernetzt sich die Wirtschaft entwickelt, desto anspruchsvoller werden jedoch auch die regulatorischen Erwartungen an Investoren.

Der Wettbewerbsvorteil wird daher zunehmend denjenigen Investoren gehören, die verstehen, dass die Einhaltung von Cybersicherheitsvorschriften kein Hindernis für geschäftliche Aktivitäten in Vietnam darstellt, sondern vielmehr Teil der rechtlichen Infrastruktur wird, die für einen erfolgreichen Geschäftsbetrieb erforderlich ist.

Bitte zögern Sie nicht, Dr. Oliver Massmann unter omassmann@duanemorris.com zu kontaktieren, falls Sie Fragen haben oder weitere Informationen zu dem neuen Cybersicherheitsrahmen wünschen.

Anwalt in Vietnam Dr. Oliver Massmann – VIETNAM SCHLÄGT EIN NEUES KAPITEL AUF: EINE WEGWEISENDE PARLAMENTSENTSCHEIDUNG ERÖFFNET DIE NÄCHSTE PHASE DER KERNENERGIEENTWICKLUNG IN NINH THUẬN 2

Vietnam hat einen der bedeutendsten rechtlichen und institutionellen Schritte seit der Entscheidung zur Wiederaufnahme seines Kernenergieprogramms unternommen.

Am 24. August 2026 hat die Nationalversammlung offiziell die Aufteilung des Kernkraftprojekts Ninh Thuận in drei rechtlich unabhängige Projekte beschlossen: das Projekt für Entschädigung, Unterstützung und Umsiedlung, das Kernkraftwerksprojekt Ninh Thuận 1 sowie das Kernkraftwerksprojekt Ninh Thuận 2.

Die Entscheidung wurde mit einer außergewöhnlich starken parlamentarischen Unterstützung angenommen: 476 von 481 anwesenden Abgeordneten der Nationalversammlung stimmten dafür, was 95,2 % entspricht. Die Resolution trat unmittelbar nach ihrer Verabschiedung in Kraft.

Dies ist weit mehr als eine bloße administrative Umstrukturierung.

Für Ninh Thuận 2 bedeutet dies die Schaffung eines klareren rechtlichen Weges von einer nationalen kernenergiepolitischen Vision hin zu einem eigenständig strukturierten, finanzierbaren und letztlich umsetzbaren Infrastrukturprojekt.

Von einem Gesamtprogramm zu unabhängigen Einzelprojekten

Das ursprüngliche Kernenergieprogramm wurde durch die Resolution Nr. 41/2009/QH12 der Nationalversammlung genehmigt. Dieser Rechtsrahmen wurde geschaffen, bevor Vietnams heutige Gesetze zu Investitionen und öffentlichen Investitionen in Kraft traten, und etablierte Ninh Thuận 1 und Ninh Thuận 2 nicht vollständig als unabhängige Projekte im Sinne der heutigen Investitionsgenehmigungsverfahren.

Diese historische Struktur hatte sich inzwischen zu einem rechtlichen Hindernis entwickelt.

Die neue Resolution der Nationalversammlung löst genau dieses Problem, indem sie den einzelnen Projekten einen eigenständigen Rechtsstatus verleiht. Dadurch können die jeweiligen Investitionsverfahren und Umsetzungszeitpläne unabhängig voneinander vorangetrieben werden.

Für Ninh Thuận 2 ist diese Unterscheidung von grundlegender Bedeutung.

Anstatt weiterhin lediglich Bestandteil eines zusammengefassten historischen Programms zu sein, kann Ninh Thuận 2 nun einen eigenen Weg hinsichtlich Investitionsgrundsatzgenehmigung, Projektparametern, Finanzierungsstruktur, Umsetzungszeitplan und Vertragsgestaltung einschlagen.

Ninh Thuận 2 kann nun eigenständig voranschreiten

Die praktische Bedeutung der Entscheidung der Nationalversammlung ist erheblich.

Nach dem derzeitigen vietnamesischen Rechtsrahmen fallen Kernkraftwerksprojekte grundsätzlich in die Zuständigkeit des Premierministers hinsichtlich der Genehmigung der Investitionspolitik. Sollte Ninh Thuận 2 jedoch besondere Mechanismen oder Regelungen erfordern, die in die Kompetenz der Nationalversammlung fallen, würde die Entscheidung über die Investitionspolitik wieder der Nationalversammlung vorgelegt werden.

Unabhängig davon besteht nun ein klar definierter rechtlicher Weg.

Die Umstrukturierung schafft somit die Grundlage, auf der die nächste Generation von Entscheidungen für Ninh Thuận 2 schrittweise aufgebaut werden kann: Projektkonfiguration, Technologieauswahl, Finanzierung, staatliche Unterstützungsstrukturen, nukleare Genehmigungen, EPC-Verträge (Engineering, Procurement and Construction) und weitere wesentliche Vertragspakete, Infrastruktur-Schnittstellen sowie letztlich die Bauausführung.

Wichtig ist, dass die Trennung nicht bedeutet, wieder bei null zu beginnen. Die Resolution erlaubt es den zuständigen Behörden und Investoren, bereits genehmigte Projektdaten und bisherige Arbeitsergebnisse gemäß den geltenden gesetzlichen Bestimmungen weiter zu nutzen. Dadurch wird wertvolle Vorarbeit erhalten, während die neuen unabhängigen Projekte im Rahmen des modernen regulatorischen Systems voranschreiten können.

Warum dies für internationale Investoren und Kreditgeber wichtig ist

Für internationales Kapital ist die rechtliche Architektur eines Projekts beinahe ebenso wichtig wie die technische Ausgestaltung.

Kernenergieprojekte erfordern außergewöhnlich lange Investitionszeiträume, enorme Kapitalaufwendungen und komplexe Schnittstellen zwischen Regierungen, Projektträgern, Technologieanbietern, Kreditgebern, Exportkreditagenturen, Auftragnehmern, Regulierungsbehörden und Beratern.

Unsicherheiten hinsichtlich der rechtlichen Identität oder des Genehmigungswegs eines Projekts können daher ein erhebliches Hindernis für die Finanzierung darstellen.

Die Resolution vom 24. August adressiert einen wesentlichen Teil dieser Unsicherheit.

Durch die Etablierung von Ninh Thuận 2 als unabhängiges Projekt schafft Vietnam die Voraussetzungen dafür, dass Risikoverteilung, Finanzierungsstruktur, staatliche Unterstützungsmechanismen und vertragliche Rahmenbedingungen gezielt auf die spezifischen Anforderungen von Ninh Thuận 2 zugeschnitten und bewertet werden können.

Diese Unterscheidung wird zunehmend an Bedeutung gewinnen, wenn die Diskussionen von politischen Grundsatzfragen zur tatsächlichen Finanzierbarkeit übergehen.

Unabhängigkeit bedeutet nicht Fragmentierung

Vietnam hat zugleich erkannt, dass zwei unabhängige Kernkraftwerke nicht institutionell isoliert voneinander betrieben werden können.

Die Regierung wurde daher beauftragt, Mechanismen für eine koordinierte Umsetzung, eine effiziente Nutzung gemeinsamer technischer Infrastruktur sowie eine klare Aufgabenverteilung in den Bereichen nukleare Sicherheit, Schutzmaßnahmen, Umweltschutz sowie nationale Verteidigungs- und Sicherheitsinteressen zu schaffen.

Ein bereits bestehender staatlicher Lenkungsmechanismus für die Entwicklung der Kernenergie wird weiterhin die Koordinierung wesentlicher ressortübergreifender Fragen übernehmen.

Diese Kombination ist entscheidend: projektbezogene Unabhängigkeit bei gleichzeitiger programmbezogener Koordination.

Sie ermöglicht es potenziell jedem Kernenergieprojekt, sich entsprechend seiner eigenen Investitionsstruktur weiterzuentwickeln, während gleichzeitig eine zentrale Aufsicht über projektübergreifende Fragestellungen gewährleistet bleibt.

Wie geht es nun mit Ninh Thuận 2 weiter?

Die Entscheidung der Nationalversammlung stellt noch nicht die endgültige Investitionsentscheidung für Ninh Thuận 2 dar.

Ebenso wenig legt sie die Technologie, die Finanzierungsstruktur oder die EPC-Strategie fest.

Stattdessen schafft sie etwas, das in dieser Entwicklungsphase möglicherweise noch grundlegender ist: die rechtliche Plattform, auf deren Grundlage diese Entscheidungen nun getroffen werden können.

Die nächsten Meilensteine sollten daher aufmerksam verfolgt werden, insbesondere die Vorbereitung und Genehmigung einer eigenständigen Investitionspolitik für Ninh Thuận 2 sowie die Ausgestaltung seiner projektspezifischen Finanzierungs-, Technologie-, Regulierungs- und Vertragsarchitektur.

Für Investoren, Kreditgeber, Exportkreditagenturen, Technologieanbieter, Auftragnehmer und professionelle Berater werden diese Entwicklungen den Übergang von der politischen Wiederbelebung des Programms zur tatsächlichen Projektumsetzung markieren.

Fazit – Ninh Thuận 2 hat eine institutionelle Schwelle überschritten

Die Entscheidung Vietnams vom 24. August 2026 sollte nicht lediglich als Aufteilung eines Kernenergieprogramms in drei administrative Teilprojekte verstanden werden.

Vielmehr handelt es sich um einen institutionellen Neustart.

Erstmals im Rahmen des modernen vietnamesischen Investitionsrechts befindet sich Ninh Thuận 2 nun auf einem klaren Weg zu einem rechtlich eigenständigen Kernenergieprojekt mit einem eigenen Genehmigungsverfahren, einer eigenen Finanzierungsarchitektur und einer eigenständigen Umsetzungsstrategie.

Das ist von enormer Bedeutung.

Die technische Herausforderung bleibt gewaltig. Die Finanzierung wird erhebliche Anforderungen mit sich bringen. Nukleare Sicherheit, regulatorische Kapazitäten, Fachkräfteentwicklung, Lokalisierung, Infrastruktur und die langfristige Verteilung von Risiken werden ein außergewöhnliches Maß an Disziplin und Professionalität erfordern.

Doch Großprojekte können erst dann finanzierbar werden, wenn ihre rechtlichen Grundlagen ausreichend klar definiert sind.

Vietnam hat nun einen dieser grundlegenden Bausteine geschaffen.

Die Bedeutung der Entscheidung der Nationalversammlung liegt daher nicht nur in dem, was am 24. August 2026 beschlossen wurde, sondern vor allem in den Möglichkeiten, die dadurch eröffnet werden.

Ninh Thuận 2 tritt aus dem Schatten des historischen Kernenergieprogramms heraus und entwickelt sich hin zu einer eigenständigen Projektstruktur. Die nächste Phase wird darüber entscheiden, wie diese Struktur in Finanzierungskonzepte, Vertragswerke, Bauvorhaben und letztlich in die Stromversorgung für Vietnams schnell wachsende Wirtschaft umgesetzt wird.

Für internationale Investoren und Kreditgeber, die den Wandel des vietnamesischen Energiesektors beobachten, ist Ninh Thuận 2 damit zu einem Projekt geworden, das noch deutlich größere Aufmerksamkeit verdient.

Zögern Sie bitte nicht, Dr. Oliver Massmann (den Architekten des Marktzugangs) unter omassmann@duanemorris.com zu kontaktieren, falls Sie Fragen haben oder weitere Informationen zu den vorstehenden Ausführungen benötigen.

Dr. Oliver Massmann ist Generaldirektor der Duane Morris Vietnam LLC.

Vietnam’s Cybersecurity Reset: Three New Decrees Redefine Compliance for Foreign Investors and FIEs

Vietnam has taken a major step in strengthening its cybersecurity regulatory architectureOn 19 August 2026, the Government issued three new decrees that materially expand the obligations applicable to businesses operating in Vietnam:

  • Decree 331/2026/ND-CP – cybersecurity protection for information systems;
  • Decree 332/2026/ND-CP – conditions for conducting business in cybersecurity products and services; and
  • Decree 333/2026/ND-CP – detailed implementation of the Cybersecurity Law.

All three Decrees took effect immediately on 19 August 2026.

For foreign investors and foreign-invested enterprises (“FIEs”), the new framework is highly significant. It introduces clearer system-classification requirements, licensing rules for cybersecurity businesses, expanded operational obligations, and detailed data-localization requirements.

The overall message is clear: cybersecurity compliance in Vietnam is becoming a core market-access and operational issue, not merely an IT concern.

1. A Five-Level Cybersecurity Classification System

Decree 331 establishes a five-level classification framework for information systems in Vietnam.

The regime applies directly to organizations that build, manage, operate or upgrade information systems serving state-agency IT infrastructure and online public services. Other organizations are encouraged to apply the same standards voluntarily, and the framework may also become relevant where government customers impose equivalent contractual obligations on private-sector service providers.

The classification framework ranges from Level 1, covering lower-risk internal systems processing only public information, through to Level 5, covering strategic defense and national-security systems, centralized national data storage, international-connection infrastructure and particularly sensitive industrial-control systems.

The higher the classification level, the more stringent the obligations become.

At a minimum, organizations must maintain:

  • cybersecurity policies and procedures;
  • appropriately qualified personnel;
  • secure system design;
  • operational security controls;
  • risk-management systems;
  • monitoring capabilities;
  • backup arrangements; and
  • incident-response mechanisms.

For Level 3 and Level 4 systems, cloud and data-center environments must be logically segregated.

For Level 5 systems, physical segregation of systems, storage and principal network equipment is required, together with mandatory independent licensed assessment.

The incident-reporting obligations are also significant. Serious incidents must generally be reported within 24 hours, followed by a full report within 72 hours, while incidents affecting national security require immediate notification.

For FIEs operating cloud, data-center, managed-service or infrastructure businesses, these requirements may become especially important when providing services to government bodies or other critical-sector customers.

2. Cybersecurity Products and Services Become a Licensed Business Sector

Decree 332 introduces a formal licensing regime for entities conducting business in cybersecurity products and services in Vietnam, excluding civil cryptography.

A cybersecurity business license issued by the Ministry of Public Security (“MPS”) is required and is valid for 10 years.

General licensing conditions include:

  • establishment under Vietnamese law;
  • good standing;
  • an eligible legal representative or authorized manager;
  • qualified technical personnel;
  • appropriate equipment, facilities and technology; and
  • compliance with specific professional requirements.

For foreign-invested economic organizations, one particularly important condition is that the remaining term of the Vietnam investment project must exceed five years at the time of license issuance.

Additional conditions apply to particular cybersecurity activities.

Cybersecurity assessment and consultancy

Providers must have at least five qualified technical personnel residing in Vietnam, and the legal representative must be a Vietnamese national.

Cybersecurity monitoring services

Providers must have at least 12 qualified technical personnel, and again the legal representative must be a Vietnamese national.

Manufacturing, trading, importing and exporting cybersecurity products

Businesses must maintain suitable business and technical plans, satisfy relevant technical standards, implement quality-control measures and maintain documentation concerning the end use of the relevant products.

Import and export activities are subject to an additional shipment-specific MPS license, valid for two years.

Applications must be submitted in Vietnamese, with a statutory review period of 28 working days after submission of a complete dossier.

Licensed entities must also submit annual compliance reports to MPS by 31 January each year.

For international cybersecurity companies considering market entry into Vietnam, these requirements should now form part of the initial investment-structuring analysis.

3. Data Localization: A Critical Distinction Between FIEs and Offshore Providers

Decree 333 provides greater detail on the data-localization and local-presence requirements under Vietnam’s Cybersecurity Law.

The rules differ materially depending on whether the enterprise is incorporated in Vietnam or operates offshore.

Vietnam-incorporated enterprises, including FIEs

Vietnam-incorporated companies are subject to an automatic local-storage obligation for specified categories of data relating to users in Vietnam.

These include:

  • personal information of users in Vietnam; and
  • user-generated data such as account names, service-use times, credit-card information, email addresses, recent login/logout IP addresses and telephone numbers associated with user accounts or data.

For Vietnam-incorporated FIEs, the question is therefore no longer whether localization may be imposed in the future, but whether the company’s current data architecture already complies.

This may require businesses to review cloud architecture, server locations, vendor arrangements, intra-group data flows and outsourcing agreements.

Offshore foreign enterprises

For offshore service providers, the obligation is conditional rather than automatic.

The relevant sectors include, among others:

  • telecommunications;
  • cloud and data-storage services;
  • domain-name services;
  • e-commerce;
  • online payments;
  • transport platforms;
  • social media;
  • online games;
  • messaging;
  • VoIP;
  • email; and
  • other online information services.

An offshore provider becomes subject to localization and local-presence requirements only where three cumulative conditions are satisfied:

  1. the service has been used in connection with cybersecurity-law violations;
  2. the specialized MPS cybersecurity force has issued written cooperation, prevention or investigation requests three times within a period of up to six months; and
  3. the enterprise fails to remedy the issue, fails to comply fully, or obstructs or neutralizes the required protective measures.

If those conditions are triggered, the Minister of Public Security may issue a formal decision requiring the enterprise to store data in Vietnam and establish a branch or representative office.

The enterprise then has 12 months to comply.

The minimum data-retention period is generally 24 months from the date of the storage request, or for as long as the request remains in force.

System logs required for investigation purposes must be retained for at least 12 months, while telecom and internet IP-allocation logs must also be retained for at least 12 months in a complete, continuous and secure manner.

4. What Foreign Investors and FIEs Should Do Now

The new framework should prompt an immediate cybersecurity compliance review.

Foreign investors and FIEs should in particular consider the following actions.

Assess system-classification exposure

Determine whether any systems built, managed or operated by the business fall within the mandatory scope of Decree 331 or may become subject to equivalent requirements through contracts with government customers or critical-sector operators.

Review cybersecurity licensing requirements

Businesses involved in cybersecurity products or services should determine immediately whether an MPS license is required and whether current corporate, personnel and investment-term arrangements satisfy the licensing conditions.

Review governance and staffing

Companies providing cybersecurity assessment, consultancy or monitoring services should confirm compliance with the Vietnamese-national legal-representative requirement and the applicable minimum staffing thresholds.

Audit data-storage architecture

Vietnam-incorporated FIEs should confirm that the required categories of Vietnamese user data are stored in Vietnam.

Offshore digital-service providers should establish internal procedures to identify and respond promptly to MPS requests that could eventually trigger localization obligations.

Implement reporting procedures

Licensed cybersecurity businesses should establish internal compliance calendars to ensure timely annual reporting to MPS by 31 January.

Conduct a legal and technical gap analysis

Because the three Decrees became effective immediately, businesses should conduct a coordinated legal, technical and operational review rather than treat the matter as a purely IT exercise.

5. Why This Matters for Investment Strategy

Vietnam is one of Southeast Asia’s fastest-growing digital economies.

The expansion of cloud computing, fintech, e-commerce, digital infrastructure, AI, data centers, smart manufacturing and online services makes cybersecurity regulation increasingly central to investment strategy.

The new Decrees therefore have implications far beyond the cybersecurity sector itself.

They affect:

  • market-entry structuring;
  • investment licensing;
  • cloud architecture;
  • data governance;
  • outsourcing;
  • M&A due diligence;
  • technology contracts;
  • regulated-sector operations;
  • internal compliance systems; and
  • long-term business continuity.

For international investors, cybersecurity compliance must increasingly be treated in the same way as tax, licensing, competition, employment and foreign-investment regulation: as a fundamental component of Vietnam market access.

Conclusion – Cybersecurity Is Becoming Part of the Investment License to Operate

The issuance of Decrees 331, 332 and 333 marks a significant evolution in Vietnam’s cybersecurity regime.

The direction of travel is unmistakable.

Vietnam is moving toward a more structured, enforceable and institutionally supervised cybersecurity framework, with clearer obligations concerning system protection, cybersecurity business licensing, data localization, staffing, reporting and incident response.

For foreign investors and FIEs, the practical consequence is equally clear:

cybersecurity can no longer be addressed only after a business has entered Vietnam. It must increasingly be considered at the investment-structuring stage itself.

Companies that act early will be better positioned to align their data architecture, licensing structure, personnel, contracts and operational systems before issues arise.

Those that do not may face licensing delays, restructuring costs, regulatory scrutiny or operational disruption.

Vietnam remains one of Asia’s most compelling investment destinations. But as its economy becomes more digital, sophisticated and interconnected, the regulatory expectations imposed on investors are also becoming more sophisticated.

The competitive advantage will therefore increasingly belong to investors who understand that cybersecurity compliance is not an obstacle to doing business in Vietnam — it is becoming part of the legal infrastructure required to do business successfully.

Please do not hesitate to contact Dr. Oliver Massmann at omassmann@duanemorris.com if you have any questions or would like further information regarding the new cybersecurity framework.

© 2009- Duane Morris LLP. Duane Morris is a registered service mark of Duane Morris LLP.

The opinions expressed on this blog are those of the author and are not to be construed as legal advice.

Proudly powered by WordPress