VIETNAM – SOLAR POWER – NEW FEED IN TARIFFS – NEW GUIDANCE FOR SOLAR ENERGY DEVELOPMENT – WHAT YOU MUST KNOW:

It has been 10 month waiting after Decision 11/QDD-TTg expired, now the Prime Minister has issued Decision 13/2020 on the incentive mechanism for solar power development. We would like to update the very new key issues as follows:

1. FIT scheme

Following notification No. 402/TB-VPCP of Prime Minister Nguyen Xuan Phuc, now FIT scheme is confirmed that it only applies for the following projects:

– For grid-connected projects: the projects that: (i) has in-principle investment decision before 23/11/2019, and (ii) COD of the whole or part(s) of project from 01/7/2019 to 31/12/2020.
– For grid-connected projects in Ninh Thuan: (i) the projects that were included into power development plans, (ii) COD before 01/01/2021, and (iii) the accumulated capacity not exceeding 2,000 MW.
It is noted that regarding grid-connected projects, FIT scheme is only applied for projects with solar cell’s capacity more than 16% or module more than 15%.

– For rooftop projects: the projects that are brought into operation, generate electricity and have electricity meter readings confirmed from 01/7/2019 to 31/12/2020.
The term of FIT scheme for the above projects shall be applied for 20 years from COD.

2. FIT2

FIT2 are as follows:
– Floating solar energy projects: UScent 7.69
– Ground mounted solar energy projects: UScent 7.09
– Rooftop energy solar energy projects: UScent 8.38

For Ninh Thuan province, grid-connected solar power projects that (ii) COD before 01/01/2021, and (iii) the accumulated capacity not exceeding 2,000 MW will be applied the FiT of UScent 9.35.

3. Competitive mechanism

The projects that do not fall with the scope of FIT scheme shall be subject to competitive scheme.

4. COD definition

COD of the whole or part(s) of the grid-connected project is defined as the date that the whole or part(s) of the project is ready to sell electricity to the buyer and satisfy the follows:
a) Has finished the initial tests for the whole or part(s) of the construction;
b) Has been issued electricity operation license;
c) Has agreed to the index of the electricity meter in order to make payment.

5. Rooftop project definition

Rooftop projects are the projects have photovoltaic panels installed on the rooftop of the construction and have the capacity not exceeds 01 MW, connect to the grids which is less than 35kV.

*************

Please do not hesitate to contact Dr. Oliver Massmann under omassmann@duanemorris.com if you have any questions or want to know more details on the above. Dr. Oliver Massmann is the General Director of Duane Morris Vietnam LLC.

VIETNAM – SOLAR POWER – LATEST NEWS ON FEED IN TARIFF AND FIT-ELIGIBILITY – WHAT YOU MUST KNOW:

After the Government Office’s notification No. 402/TB-VPCP dated 22 November 2019 on solar power FiT2 and auction scheme, the MOIT has coordinated and consulted with EVN, MOF and MOJ to finalize its draft solar power FIT2. On 31 December 2019, a final draft submission letter from MOIT (with signature but no stamp) (NB: no draft FiT2 PM Decision attached also) for FiT2 PM Decision has been internally circulated. To our knowledge, this submission letter and the draft FiT2 PM Decision would be duly executed and submitted to the Prime Minister no later than COB next week. Please kindly find below our highlights of this draft submission letter of MOIT.

1. FIT2 Eligibility

The MOIT insisted that in order to be eligible for FiT2, solar power projects must (i) have been in principle approved, and added in the relevant power development planning, (ii) have signed PPAs with EVN, (iii) be “under construction” prior to 23 November 2019, and (iv) reach COD by end of 2020.

The MOIT document defined what “under construction” means for this purpose. It takes a narrow view, referring to Article 6.1.b of Decree 59/2015/ND-CP dated 18 June 2015 re management of construction projects to suggest that for a project to be considered “under construction” the project must have completed appraisal of either detailed or technical construction design (as the case may be) prior to 22 November 2019. Based on the reports of EVN dated 2&12 December 2019, MOIT determined there are only 7 solar power projects of 320 MW which are currently eligible for FiT2. The list of FiT2 eligible solar power projects is attached at Schedule 1 of the draft FiT2 PM Decision which has not yet been disclosed.

The MOIT also mentioned (i) Schedule 2 for solar power projects have been in principle approved, and added in power development planning, signing PPA, (ii) Schedule 3 for list of 30 solar power projects in Ninh Thuan province of 1,933 MW, and (iv) Schedule 4 for list of 22 projects that have been appraised for master plan addition and reported to the Prime Minister. The foregoing schedules have not yet been disclosed.

As reported before, EVN sent letter no. 6774/EVN-TTD dated 12/12/2019 to MOIT to suggested FiT2 to be applied to the projects which have construction contracts before 22 November 2019 (of any part of the project) and have evidence on the implementation of the project. In addition, EVN suggested that MOIT may consider decreasing the FiT2 in proportion to the construction delay status of relevant projects (e.g., 5% of FIT2 for any quarter failing to meet construction deadline). However, the MOIT did not agree with this proposal from EVN.

2. FIT2 Price for Solar Power Projects / Rooftop Solar (RTS) Projects

The submission letter is not very clear on the FiT2 price but very likely MOIT will keep the last draft FiT2 price structure i.e., (i) 7.06 UScent per Kwh for ground-mounted solar power projects and (ii) 7.69 UScent per Kwh for floating solar power projects.

In terms of RTS projects, MOIT proposed the price to be 8.38 UScent per Kwh. The MOIT did not agree with EVN’s proposal to remain 9.35 UScent per Kwh for RTS projects during 2020.

***
Please do not hesitate to contact Dr. Oliver Massmann under omassmann@duanemorris.com or any other lawyer in our office listing if you have any questions or want to know more details on the above topic. Dr. Oliver Massmann is General Director of Duane Morris Vietnam LLC.

VIETNAM – RENEWABLE ENERGY – NEW FEED IN TARIFFS FOR WIND ENERGY – AMAZING DEVELOPMENT – SOLAR POWER – SPECIAL POLICY FOR NINH THUAN AND ONGOING DRAFT POLICY

RECENT DEVELOPMENT
Until June 2018, approx. 286 solar power projects of total capacity of 19,300 MW have been submitted to the licensing authorities to be supplement to the Power Master Plans, but only 100 projects have been approved (approx. 4,700 MW). We also note that 90% projects are still in other licensing processes such as application for investment registration license, construction permit, etc.
At least 10 solar power projects that investors have signed PPAs with EVN recently. By end of September 2018, the first solar energy project will connect to the national power grid (35 MW in Hue province).
With regards to the remaining projects have not yet been included in the Power Master Plans, the Deputy PM Trinh Dinh Dung has decided and instructed that MOIT must consider and approve to addition if such solar energy projects satisfy one of the following conditions:
• MOIT has completed the investigation process of the application to supplement to Power Master Plan of such project; or
• Projects have submitted the application to supplement to Power Master Plan to MOIT and such projects are located in provinces that have potential to develop solar energy projects.

SPECIAL POLICY ONLY FOR NINH THUAN – NOT FOR OTHER PROVINCES
On 31 August 2018, the Prime Minister Nguyen Xuan Phuc issued Resolution 115/NQ-CP (“Resolution 115”) to finally decide that the commercial operation date (COD) deadline (previously 30 June 2019) for solar projects in Ninh Thuan province to enjoy the 9.35 US cents feed in tariff has been extended to the end of 2020. This extension applies to those solar energy projects approved in the relevant Power Master Plan. Resolution 115 took effect on 31 August 2018 and lays to rest the badly kept secret that Ninh Thuan, a literal hot spot for solar projects, will enjoy more favorable terms than projects in other locations which remain bound to the 30 June 2019 COD deadline (as noted below).

NEW REGULATIONS FOR SOLAR ENERGY PROJECTS AFTER 30 JUNE 2019?
The Government will issue new FIT and new PPA for projects coming into operation after 30 June 2019. Such new FIT will be much more lower than the current one (verbally confirmed by Mr. Nguyen Ninh Hai, Deputy Director of New and Renewable Energy Department, MOIT).
The Government is now also working on a Competition Auction System for solar power projects that may be completed at around the 2020. The new FIT will be applied only until the Competition Auction System is decided and implemented.

ON GOING DRAFT POLICY ON NEW FIT FOR WIND ENERGY PROJECTS
MOIT has proposed the below a new and very promising FIT for wind energy projects to PM for his consideration and approval:
o FIT for Onshore project: 8.5 cents
o FIT for Offshore project: 9.8 cents
FYI, in current draft available to us, onshore and offshore projects are defined as below:
“Onshore wind power project means on-grid wind power project that having its wind turbines to be built and operated on inland areas and coastal zones (NB: boundary of such inland areas and coastal zones is the average low water line for 18.6 years)
Offshore wind-power project means on-grid wind power project that having its wind turbines to be built and operated outside inland areas and coastal zones to the sea.”

*************
Please do not hesitate to contact Dr. Oliver Massmann under omassmann@duanemorris.com or any lawyers in our office listing if you have any questions or want to know more details on the above. Dr. Oliver Massmann is the General Director of Duane Morris Vietnam LLC.

Vietnam – Solar Energy – Action plan for getting deals done with the new Power Purchase Agreement

Interview with Dr. Oliver Massmann\

1. Which significant changes does the new PPA contain for the solar energy sector?

Decision 11 introduces the Feed-in-Tariff (FiT) rate of UScents 9.35 per kWh. The FiT rate is only applicable for on-grid solar power project with efficiency of solar cells greater than 16% or with efficiency of the modules greater than 15%. The FiT rate depends on the currency exchange rate of the Vietnamese Dong and the US-Dollar. The rate remains the same throughout the whole year. It is adjusted by the Vietnamese State Bank on the last working day of the year for being used in the following year.

As a result, the financial planning is easier and it grants certain security for investors such as protection against currency fluctuation.

2. Which aspects in the new PPA have changed compared with the draft PPA from April 2017?

Compared with the draft PPA, the FiT rate is now indicated in the final version and there is reference to the adjustment of the FiT in case of USD/VND exchange rate fluctuation.

The MoIT made no big changes regarding the shortcomings of the draft of the PPA from April 2017.

The investor still has to bear the biggest risk.

3. Is the PPA bankable?

No, in general the PPA is not bankable in its final version.

4. Is there a way to make it bankable?

Yes, it is possible to make the PPA bankable. We have 20 years of experience making PPAs bankable for gas and coal fired power plants and wind energy plants in Vietnam. The investor should use all business channels and experienced negotiators to make the PPA bankable.

It is a matter of negotiation and experience. Decision 11 is granting investors the possibility to negotiate the conditions with EVN. The price remains fixed.

Agreements such as the EU – Vietnam Free Trade Agreement (“EVFTA”) or the Trans-Pacific Partnership (“TPP”), which is now called the Comprehensive and Progressive Agreement for the Trans-Pacific Partnership (“CPTPP”), lay a big milestone for making the PPA bankable.

The EVFTA was signed in 2015 and is expected to be ratified by all member countries by 2018. It is probably going to take effect in 2019. It is estimated to generate an increasing GDP and to liberalize the economy of Vietnam. Another aspect is the elimination of almost all custom duties (over 99% of all tariff lines). As a result, there will be a huge impact on trade development and the interest of investors.

Another important agreement is the CPTPP. On 4th February 2016 the TPP was signed between 12 countries. The signing nations made up 28% of the global trade and 40% of the global GDP. However, at the beginning of 2017, the US President Trump decided to withdraw from the TPP. The remaining 11 member states discussed the future of the TPP in APEC event in Da Nang, Vietnam and agreed to push ahead with the TPP but now under the name of CPTPP. Furthermore, the states agreed to work out a new framework agreement, which includes changes to the previous TPP agreement. The largest amendment was made in the field of intellectual property, for example, easing the protection of copyright or the special protection of biologics and pharmaceuticals.

However, the level of market access is still the same as in the first TPP. For some countries, further negotiations have to take place and they need time to adapt their laws to the CPTPP rules. The negotiators have set the goal of signing the revised TPP by the first quarter of 2018. After 6 countries have ratified the partnership, it will come into effect.

With the CPTPP, market access to more sectors will be opened than the WTO such as telecommunication, distribution of goods, manufacturing and fabrication. However, there will remain a few restrictions in the power/energy sector as discussed below.

As a result of the EVFTA and the TPP, Vietnam will get access to a huge part of international markets. This gives Vietnam the possibility to increase the amount of imports and exports (estimated up to 37% higher until 2025) and to improve foreign investments.

Another essential instrument is the Investor-State Dispute Settlement (ISDS)[N1] which is going to be applied under the EVFTA and the TPP. Under that provision, for investment related disputes, the investors have the right to bring claims to the host country by means of international arbitration. The arbitration proceedings shall be made public as a matter of transparency in conflict cases. In relation to the TPP, the scope of the ISDS was reduced by removing references to “investment agreements” and “investment authorization” as result of the discussion about the TPP’s future on the APEC meetings on 10th and 11th November 2017.

As a conclusion, the bankability of the PPA will get enhanced as a consequence of the EVFTA and TPP in the next few years if the legislative framework is being reformed in the right direction. The economy will become more dynamic because of access to other markets and further foreign investments. With the implementation of the ISDS in the TPP, investors will be more secured in relation to dispute resolution and protection against the risks of international trading. As a result, banks will be more willing to finance PPAs.

Our recommendations: For now, the bankability of the PPA is not as it is expected. But you should be aware of the upcoming agreements which will lead to a big impact on the economy growth and the economy itself. If everything is improving in the right direction as it is now, the PPAs will be more bankable in the future and there will be better investment opportunities.

5. How was the bankability issue handled in the past years?

The TPP and the EVFTA are not the only agreements regarding the bankability of the PPA.

Vietnam and the USA signed the Bilateral Trade Agreement (BTA) in 1999 which was implemented in 2001. It was a huge success and very important agreement for the economy of Vietnam. It was the first opening of the Vietnamese market and important for the creation of more business opportunities and new standards for financing projects.

Another important fact was Vietnam’s accession to the WTO in 2007. This has improved trade relations between Vietnam and other countries by removing trade barriers and the commitment to non-discrimination. It was also a political sign to show Vietnam’s will to get integrated in the international trade by accepting international trading rules.

To be able to fulfill the commitments, it is necessary to make legislative adjustments and adopt laws that ensure the viability and efficiency of the projects. In the last years, many important laws have been introduced. They have helped to enhance the bankability of the PPA, for example, the 2014 Investment Law, 2014 Enterprise Law, 2012 Labor Law, etc.

In addition, in 2011, the legal framework for wind power projects was introduced.

Our recommendation: You should use existing international agreements and local laws as the bases for negotiation. Remember to rely on existing precedents and keep in mind that there are some difficulties for project development. But with a well-structured project development, it is still possible to getting a bankable PPA done.

6. What are the main risks of the PPA for investors?

With many solar projects currently focused on a few central locations, the capacity of existing facilities to absorb power must be a cause of some concerns given the PPA’s transfer of such risk to power producers.

EVN holds a monopoly of distribution, repair, maintenance, inspection and examination of the grid.

There is a big risk because of the lack of the government’s guarantee for EVN’s payment obligation in cases energy is provided from the producer but cannot be transmitted due to interruption of EVN’s grid connection. One solution for bridging that guarantee gap can be the use of the MIGA backup from the Worldbank (Multilateral Investment Guarantee Agency) or backup from the Asean Development Bank.

Reasons for the interruption can be, for example: force majeure or termination of contracts. EVN can refuse transmitting the energy in cases of maintenance or repairing.

Circular 16 does not contain any guarantee or compensation for investors in these cases.

Our recommendations for avoiding potential risks: Be aware of veto rights of EVN and Vietnamese authorities. You have to be patient because the decision making process in Vietnam goes through many levels and takes time.

7. There will be conflicts between the investors and EVN because of the shift of risks to the investors. Which means of conflict resolution does the PPA grant to investors?

In general, the PPA is governed by the Vietnamese law.

The PPA does not provide for international arbitration as a means of dispute resolution.

Conflicts can be submitted to the Department of Electricity and Renewable Energy. If this option fails, investors can seek help at the Electricity Regulatory Authority of Vietnam (ERAV) or with application to a Vietnamese court.

The PPA implicitly allows the involvement of domestic and offshore arbitration. However, whether it can be a prior agreement with EVN in the PPA or only until there is an arising dispute simply lies in the hands of EVN.

Our recommendations for successful negotiations with EVN: You have to understand how EVN is working and what their targets are. Be aware of their monopoly position in the energy sector in Vietnam. Don’t try “to reinvent the wheel”!

Do not overexert them with too ambitious intentions related to the development proposal. They might be afraid of so many new things. Rely on workable precedent strategies and make reference to successful projects.

8. Which view does the MoIT hold regarding the shortcomings of the PPA?

The MoIT knows about the shortcomings of the PPA and is aware about the fact that the PPA will not attract investors to meet the power demand or to solve problems regarding the development of renewable energy.

The MoIT also knows that the solar energy sector in Vietnam has a lot of potentials.

Finally, the MoIT expects to attract smaller investment projects where bankability is not really an issue for the investors.

9. Is the view of the MoIT realistic?

In our opinion, the MoIT’s view is not realistic. It may lead to unfeasible projects because of the existing risks of the final version of PPA and without assurance for supportive services from a bank. Furthermore the success of projects depends on the result of the negotiation with EVN.

10. Which advice can you give to future investors regarding their project development?

Be aware! You have to take care of your project on a step-by-step-base and get well prepared for the negotiations with EVN when you decide to invest in an on-grid power project.

***

Please do not hesitate to contact Dr. Oliver Massmann under omassmann@duanemorris.com if you have any questions or want to know more details on the above. Dr. Oliver Massmann is the General Director of Duane Morris Vietnam LLC.

 

Thank you!

 

 

 

Lawyer in Vietnam Dr. Oliver Massmann – Solar Power Development in Vietnam – what you must know:

 

  1. What can you tell me about the policies Vietnam now has in place to support solar development?

The legal framework is almost complete. I expect the solar PPA template will be issued within this year so that the investors have full guidance to develop projects in Vietnam. However, as I see from the recent draft solar PPA, it repeats the same mistakes in other renewable PPAs that make projects not bankable. This issue needs to be sorted out soon so that solar development will be on fast track in near future.

  1. Total PV installations in Vietnam are still quite low — what has been holding back development?

Because the latest Prime Minister’s Decision promulgating solar FIT was only issued on 11 April 2017. In addition, solar energy is still expensive and less stable throughout the year compared with other sources of energy. Bankability of the PPA is also a worth-noting issue.

Bankability of PPAs has been achieved for other power projects in the past in Vietnam. We are now working on solutions for the solar power sector. It can be done.

  1. How do you see the solar market evolving through the end of this decade, both in terms of manufacturing and project development?

I foresee a rapid development in the sector. This is due to the Government’s change of focus on clean energy and environment protection policies. I can see many foreign investors visiting Vietnam recently to look for investment opportunities and many of them have managed to reach a deal with local partners.

  1. Where are the opportunities in Vietnamese PV and how should prospective investors and developers approach the market?

Vietnam is an untapped market for solar. The Government offers many good incentives to attract foreign investment, for example, exemption of land rental within 3 years from the operation date, CIT 10%, etc. Investors and developers should first establish close contact with local authorities and conduct careful due diligence on local partners. BOT is the most recommended investment form. In addition, investors and developers may consider taking part in different segments such as equipment supply, solar panels manufacturing, or assembling, etc.

  1. What can you tell me about the availability of financing?

IFC and ADB are the most active financiers. Local banks are also more and more interested in lending to renewable projects in general and solar projects in particular. However, due to poor performance and credit of EVN, the financing resources are still limited. We recommend MIGA (Multilateral Investment Guarantee Agency) support for on-grid utility scale solar power projects (above 50 MW).

***

If you have any question on the above, please do not hesitate to contact Dr. Oliver Massmann under omassmann@duanemorris.com, Dr. Oliver Massmann is the General Director of Duane Morris Vietnam LLC.

Thank you very much!

 

 

 

© 2009- Duane Morris LLP. Duane Morris is a registered service mark of Duane Morris LLP.

The opinions expressed on this blog are those of the author and are not to be construed as legal advice.

Proudly powered by WordPress